LIFTING PLAN Date

:

Location

:

Crane

:

Material Name

:

Crane 1

Crane 2

Working Radius (m)

Working Radius (m)

Boom Length

Boom Length

Lifting Capacity

Lifting Capacity

Safety Factor Calculation

Safety Factor Calculation

Load

:

Ton

Load

:

Ton

Hook Block Weight

:

Ton

Hook Block Weight

:

Ton

Total Weight

:

Ton

Total Weight

:

Ton

Safety Factor Calculation: Lifting Capacity Total Weight

Safety Factor Calculation: Lifting Capacity Total Weight

: :

: %

:

Angle LOAD (T)

Radius (m)

Prepared by Company:

Name & sign: Name & sign:

LOAD (T)

Radius (m)

%

LIFTING PLAN Material to be lift: Date

:

Location

:

Crane 1

:

Crane 2

:

Material

:

Total Weight

: Safety Factor Calculation

Crane 1

Crane 2

Weight

:

Weight

:

Hook block

:

Hook block

:

Lifting Tackles

:

Lifting Tackles

:

Total Weight

:

Total Weight

:

Working Radius

:

Working Radius

:

Lifting Capacity

:

Lifting Capacity

:

Safety Factor

:

Safety Factor

:

R2

Prepared by

Acknowledge by

Name:

Sign:

Sign:

Name:

Sign:

Name:

LIFTING PLAN DISMANTLING SILO TANK Date Location Crane 1 Crane 2 Material

: 03/29/2012 : Bulk Plant Area : Latice Boom Sumitomo : Telescopic Boom Kato : Silo Tank

Load Chart Latice Boom Sumitomo Length LengthBoom Boom

Load Chart Telescopic Boom Kato Length Boom Boom

18.5 m

Working Radius (m)

21.8 m Working Radius (m)

5 6 7 8 9 10

25 21.5 18 15.4 13.2 11.6

4 5 6 7 8 9

15.5 15.5 13 11.4 10.1 9.05

Safety Factor Calculation Weight Silo Tank Hook block Lifting Tackles Total Weight

: 6.5 Ton (50% total beban) : 0.4 Ton : 0.06 Ton : 6.96

Weight Silo Tank Hook block Lifting Tackles Total Weight

: 6.5 Ton : 0.4 Ton : 0.06 Ton : 6.96

Working Radius Lifting Capacity Safety Factor

:7 M : 18 Ton : 2.59

Working Radius Lifting Capacity Safety Factor

:6 M : 13 Ton : 1.87

3. Loading Silo Tank Onto Trailer SWING RIGHT SWING LEFT

R1

KTP

Prepared by Irsan Pane Didit K

R2

(50% total beban)