40 1 81KB
Item Descriptions Nos 1 Bar Bending Works Slab & Beam Footing
2
3
4
5 6
7
8
crew Fiter Helper Fiter Helper
Formwork Fixing & is a Removal Slab & Beam Carpenter Helper Footing Carpenter Helper Column box fix Carpenter Helper Column Starter fix Carpenter Helper Formwork Making Beam Side Carpenter Helper Column box fix Carpenter Helper Starter Carpenter Helper Concrete Slab & Beam Mason Helper Block Mason Helper Plastering Internal Mason Helper External Mason Helper Ceiling Mason Helper Corner beading fixing Mason Helper Mesh fixing & packing Mason Helper Earth Works Excavation Manual Excavation DL Machine Operated Water Proofing horizontal membrane application applicator Helper vertical membrane application applicator Helper brush on application applicator Helper
crew nos
Production per 8hrs
1 1.5 1 1.5
170
Kg/day
21.25
Kg/hrs
200
Kg/day
25
Kg/hrs
1 1.5 1 1.5 1 2 1 2
5
Sqm/day
0.625
Sqm/hrs
7
Sqm/day
0.875
Sqm/hrs
20
Sqm/day
2.5
Sqm/hrs
6
Nos/day
0.75
Nos/hrs
1 1 1 1 1 1
6
Sqm/day
0.75
Sqm/hrs
3
Sqm/day
0.375
Sqm/hrs
5
Nos/day
0.625
Nos/hrs
1 1 1 1.5
20
M3/day
2.5
M3/hrs
6
M2/day
0.75
M2/hrs
1 1.5 1 1.5 1 1.5 1 1 1 1.5
10
M2/day
1.25
M2/hrs
12
M2/day
1.5
M2/hrs
12
M2/day
1.5
M2/hrs
7
Nos/day
0.875
Nos/hrs
60
Running ft/d
2
2.83 60
M3/day M3/day
0.35375 7.5
M3/hrs M3/hrs
1 1 1 2 1 1
150
m2/day
18.75
m2/hrs
50
m2/day
6.25
m2/hrs
20
m2/day
2.5
m2/hrs
Unit
Production per hrs
7.5
Unit
Running ft/hrs
bore packing 9
Plumbing Works toilet chasing waterline fixing sanitary line fixing sanitary &cp fitting
applicator Helper chipper plumber helper plumber helper plumber helper
1 1
3
No/day
0.375
No/hrs
1 1 1.5 1 2 1.5 3
7 3
Rmt/day toilet/day
0.875 0.375
Rmt/hrs toilet/hrs
3
toilet/day
0.375
toilet/hrs
4
toilet+kitch
0.5
toilet+kitchen/hrs
Running ft/hrs
toilet+kitchen/hrs
Ite m 1 1.1 1.2
1.3 1.4
1.5 1.6
2 2.1
2.2
2.3 2.4 2.5 2.6 2.7 2.8 2.9 3 3.1
3.2
3.3
4
Description Excavation & Earth Work Site clearing to remove depth of 20cm Trench Excavation in ordinary soil a. To a depth of 1.2m b. To a depth of 2.2m c. To a depth of 3.00m Bulk excavation in ordinary soil a. To a depth of 1.5m Cart Away a. To 500m away from the site b. To 1km away from the site Hard-coring 25cm thick Back fill around foundation: a. Loose soil b. Aggregate Concrete Work Lean concrete a. 5cm thick b. 8cm thick Floor Slab a. 8cm thick b. 10cm thick c. 15cm thick Ground beam Footing Foundation column Upper tie beam Lintel Column up to 2m Column above 2m Masonry Work Stone Masonry sub-structure. a. 40cm thick b. 50cm thick c. 60cm thick Stone Masonry super structure a. 40cm thick b. 50cm thick c. 60cm thick Brick Masonry Wall for plastering. a. 25cm thick up to 2m b. 12cm thick up to 2m c. 25cm thick from 2-4m d. 12cm thick from 2-4m
Time
Production per 8hrs
Production per hrs
Unit
1D. L
8hr
10
1.250
m2
1D.L 1D.L 1D.L
8hr 8hr 8hr
1.25 1 0.75
0.156 0.125 0.094
m3 m3 m3
1D.L
8hr
1.5
0.188
m3
1D.L 1D.L 1M+4D.L
8hr 8hr 8hr
1.5 1 18
0.188 0.125 2.250
m3 m3 m2
1D.L 1D.L
8hr 8hr
2 5.5
0.250 0.688
m3 m3
1M+6D.L 1M+6D.L
8hr 8hr
20 15
2.500 1.875
m2 m2
1M+6D.L 1M+6D.L 1M+6D.L 1M+6D.L 1M+6D.L 1M+6D.L 1M+6D.L 1M+6D.L 1M+6D.L 1M+6D.L
8 hr 8hr 8hr 8hr 8hr 8hr 8hr 8hr 8hr 8hr
15 12.5 10 1.5 1.5 1.25 1.5 1 1 1.25
1.875 1.563 1.250 0.188 0.188 0.156 0.188 0.125 0.125 0.156
m2 m2 m2 m3 m3 m3 m3 m3 m3 m3
2M+6D.L 2M+6D.L 2M+6D.L
8hr 8hr 8hr
5 6 7
0.625 0.750 0.875
m3 m3 m3
2M+6D.L 2M+6D.L 2M+6D.L
8hr 8hr 8hr
3 4 5
0.375 0.500 0.625
m3 m3 m3
1M+3D.L 1M+3D.L 1M+3D.L 1M+3D.L
8hr 8hr 8hr 8hr
7 9 5 7
0.875 1.125 0.625 0.875
m2 m2 m2 m2
Gang
5 5.2 Ridge cover 5.3 Valley cover 5.4 Gutter fixing 5.5 Joining eucalyptus truss up to 10m span on ground 6
Plastering & Pointing 7.1 1st cost plastering 7.2 2nd cost plastering 7.3 3rd cost plastering 7.4 Pointing on stone Wall 7.5 7.6 7.7 7.8
8
9 9.1 9.2 10 10.1 10.2 10.3 10.4 10.4
8hr 8hr 8hr
4pcs 10m2 10m2
2hr/pos 48min/m2 48min/m2
1C+2D.L
8hr
13m2
48min/m2
1W+2D.L 1W+2D.L 1W+2D.L
8hr 8hr 8hr
3pcs 4pcs 2pcs
2.66hr/pcs 2hr/pcs 4hr/pcs
1P+2D.L
8hr
35m2
14min/m2
1P+2D.L
8hr
10m2
48min/m2
1P+2D.L
8hr
14m2
34min/m2
1P+2D.L 1P+2D.L 1P+2D.L 1P+2D.L
8hr 8hr 8hr 8hr
8m2 14m2 12m2 20m2
4hr/m2 34min/m2 40min/m2 24min/m2
1M+2D.L 1M+2D.L 1M+2D.L 1M+2D.L 1C+2D.L 1M+2D.L 1M+2D.L 1M+2D.L 1M+2D.L 1M+2D.L 1M+2D.L 1M+2D.L
8hr 8hr 8hr 8hr 8hr 8hr 8hr 8hr 8hr 8hr 8hr 8hr
14m2 10m2 17m2 15m2 8m2 7m2 40ml 12ml 12ml 16ml 10ml 6ml
34min/m2 48min/m2 48min/m2 32min/m2 1hr/m2 1.14hrn/m2 12min/ml 40min/m2 40min/m2 30min/m2 48min/ml 1.33min/ml
1G+2D.L 1G+2D.L
8hr 8hr
50m2 20m2
10min/m2 24min/m2
1P + 1DL 1P + 1DL 1P + 1DL 1P + 1DL 1P + 1DL
8hr 8hr 8hr 8hr 8hr
30m2 25m2 20m2 20m2 20m2
16min/m2 19min/m2 24min/m2 24min/m2 24ming/m2
1p + ID1 1p + ID1 1p + ID1
8hr 8hr 8hr
25m2 25m2 25m2
19min/m2 19min/m2 19min/m2
Metal Work 6.1 Metal door fixing 6.2 Metal Window fixing 6.3 French Window fixing
7
1C+2D.L 1C+2D.L 1C+2D.L
Pointing on brick wall Pointing on Hollow block Pointing on dressed stone Rendering
Flooring Cement Screed Cement tile fixing Plastic tile fixing Par - quet flooring Wooden flooring Ceramic wall tile Plastic tile skirting Cement tile skirting Marble slate flooring Marble slate skirting Fixing pre-cast windows Fixing un pre-cat window sill Glazing Cutting Fixing
Painting a) Plastic paint Painting plastered wallSurface 3ocats Painting Rendered wallsurface Painting Abujedid wall Painting Hard board obi Painting Cheap boardceiling
b) Synthetic paint 10.6 Plastered wall surface in 3 coats 10.7 Wooden surface 10.8 Metal surface
11 Sanitary work 11.1 G.1. pipe laying inGround ½ - 11/4 Fixing – Bath tubeShower complete, 11.2 washBasin, water closest, bidetSink, urinal 12 2 12.2 .12.3 .12.4 .12.5 . 13 13.1
13.2 13.3 13.4 13.5
1P+2DL
8hr
120m2
4min/ml
1p+1DL
8hr
1pcs
8hr/pcs
1E+1DL 1E+1DL 1E+1DL 1E+1DL 1E+1DL
8hr 8hr 8hr 8hr 8hr
40ml 50ml 20pcs 10pcs 10pcs
12min/ml 10min/ml 24min/pcs 48min/pcs 8min/pcs
1m+3DL
8hr 8hr 8hr 8hr
30ml 20ml 10ml 30ml
16min/ml 24min/ml 48min/ml 16min/ml
1m+3DL
8hr
3pcs
4hr/pcs
1m+3DL
8hr
2pcs
4hr/pcs
1C+2DL
8hr
50m2
10min/m2
Electrical installation Fixing conduits Pulling wires Fixing switch & out-lets Fixing fittings Fitting distribution board
Site Work Drain laying 0.10 - 0.30m 0.40 - 0.60 m 0.80 - 1.00 m Curb Stone 0.60 x 0.60 x 0.60m manhole out of brick 0.60 x 0.60 x 0.60m manhole out of hollow block Fencing with Galv. Fencing net
1M +3 1DL
Item
Type of activity
Unit
1
5cm thick lean concrete (c-7)
m3
2
Concrete C-15
m3
3
C-25 concrete for footing
m3
4
C-25 concrete for column
m3
5
C-25 concrete for Grade beam
m3
6
C-25 Concrete for slab
m3
7
C-25 top beam and Lintel
m3
8
30 cm Ribbed slab
m2
9
Wooden form work (Footing)
m2
10 Wooden form work (Column)
m2
CREW FORMATION Labour Equipment 1 Forman 2 mason 1 mixer 45 D/L 1 Forman 1Mixer 2 mason 1 Vibrator 45 D/L 1 Forman 1 Mixer 2 mason 1 Vibrator 45 D/L 1 Forman 1 Mixer 2 mason 2 Vibrator 25 D/L 1Forman 1 Mixer 2 mason 2 Vibrator 45 D/L 1 Forman 1 Mixer 2 Mason 2 Vibrator 45 D/L 1 Forman 1 Mixer 2 Mason 2 Vibrator 45 D/L 1/6 Forman 1Mason 2 D/L 1/6 Forman 1 carpenter 1 Helper 1 D/L 1/6 Forman 1 carpenter 1 Helper 1 D/L
Hourly Output 2.25m3
2.25m3
2.25m3
0.75m3
1.75m3
2.50m3
1.50m3
2.00m2
0.60m2
0.50m2