40 1 43KB
Earth Works
Back Filling + Compaction
Excavation work in soft soil Excavation Work in Hard Soil
120 50
m3/day m3/day
In layer of 150 mm thickness with 95% MDD value
150
m2/day
Concrete Protection Works Bitumen Priming Works
Including surface preparation
200
m2/day
Bitustic works
Horizontal/Vertical surface
150
m2/day
Protection works (torch applied)
Horizontal/Vertical Surface
80
m2/day
75/100 mm thick Blinding works
120
m2/day
40/50 mm thick C/S Screed 75/100 mm thick screed with welded steel fabric
200
m2/day
120
m2/day
Up to 16 mm dia bars
200
kg
Above 16 mm dia bars
300
kg
200
kg
Up to 12 mm
300
kg
16 mm and Above
400
kg
With Ordinary(Ply wood) shutter "
8
m2/day m2/day
"
12
Concrete Blinding Works
Screed Works
Reinforcement Works Isolated/ Strap Footing
Column/Corewall/Staircase Slab with beam/Raft
Shuttering Footing Column/Core Wall/Staircase
6
Slab
m2/day
Concrete Pumping Works Placing with concrete Pump
60 40
Boom Placer
m3/hr m3/hr
Concrete Works Footings
Concrete Placing and Trowel Finishing
Staircase
"
60
m3/day
Slab
"
150
m3/day
Placing in line and level
400
m2/day
10/15/20 cm thick Block works
10
m2/day
15 mm thick Plaster Works with Acc.
12
m2/day
20 mm thick Plaster Works with Acc.
10
m2/day
Including Surface preparation works
150
m2/day
75
m2/day
First Coat
250
m2/day
Second Coat
350
m2/day
Placing Precast/Hollow Core Slab
Block works
Plaster Works
160
m3/day
Ordinary Painting Priming Works Putty Works Painting Works
Epoxy Paint
Gypsum Partition Works
False Ceiling
Tile Works
Marble/Granite Works
Surface Prep + Priming
50
m2/day
Painting
100
m2/day
Frame + Gypsum Partition Installation
120
m2/day
Frame + False Ceiling Fixing
30
m2/day
On Floor
15
m2/day
On Walls
12
m2/day
on Floor
20
m2/day
Excavator (bucket type) Rock breaker
1 Skilled, 4 Unskilled, 1 shovel,1 Roller compactor
1 skilled + 1 unskilled 1 skilled + 1 unskilled 1 skilled + 1 unskilled
1 Mason + 2 Helper
1 Mason + 2 Helper 1 Mason + 2 Helper
1 SF + 1 Helper 1 SF + 1 Helper 1 SF + 1 Helper 1 SF + 1 Helper 1 SF + 1 Helper
1 Carpenter + 1 Helper 1 Carpenter + 1 Helper 1 Carpenter + 1 Helper
1 Mason + 3 helper 1 Mason + 2 helper 2 Mason + 3 Helper
2 Rigger + 1 Mason + 2 Helper
1 mason + 1 Helper
1 Plaster Mason + 1 Helper 1 Plaster Mason + 1 Helper
1 Painter + 1 Helper 1 Painter + 1 Helper 1 painter 1 Painter
1 Painter + 1 Helper 1 Painter + 1 Helper
1 Mason + 1 Helper
1 Mason + 1 Helper
1 Mason + 1 Helper 1 Mason + 1 Helper
2 Mason + 1 Helper