39 2 967KB
EQUIPMENT PRODUCTIVITY Code
Work Item
Rate
EARTHWORKS
EP1.1.1 EP1.1.2
Clearing & Grubbing Clearing & Grubbing (Volume) Clearing & Grubbing (Area)
92.05 613.64
m3/hr m2/hr
EP1.2.1 EP1.2.2
Ground Dressing Dressing (t < 250mm) (Volume) Dressing (t < 250mm) (Area)
103.32 413.27
m3/hr m2/hr
EP1.3.1 EP1.3.2 EP1.3.3
Ground Leveling Leveling (t > 250mm) (Volume) Leveling (t >250mm) (Area) Leveling (t > 500mm) (Volume)
97.70 325.68 88.24
EP1.3.4
Leveling (t >500mm) (Area)
176.47
m3/hr m2/hr m3/hr m2/hr
EXCAVATION & BACKFILLING
EP2.1.1 EP2.1.2 EP2.1.3 EP2.1.4 EP2.1.5 EP2.1.6
Bulk Excavation Bulk Excavation (Cap=0.8m3, Normal Soil) Bulk Excavation (Cap=0.8m3, Hard Soil) Bulk Excavation (Cap=0.8m3, Rocky Soil) Bulk Excavation (Cap=1.0m3, Normal Soil)
55.86 33.27
m3/hr m3/hr m3/hr m3/hr
Bulk Excavation (Cap=1.0m3, Hard Soil) Bulk Excavation (Cap=1.0m3, Rocky Soil)
22.76 56.01 33.36 22.82
EP2.2.1 EP2.2.2 EP2.2.3 EP2.2.4
Foundation Excavation Foundation Excavation (Cap=0.8m3, Normal Soil) Foundation Excavation (Cap=0.8m3, Hard Soil) Foundation Excavation (Cap=0.8m3, Rocky Soil) Foundation Excavation (Cap=1.0m3, Normal Soil)
40.16 26.99 19.63 40.26
m3/hr m3/hr m3/hr m3/hr
EP2.2.5 EP2.2.6
Foundation Excavation (Cap=1.0m3, Hard Soil) Foundation Excavation (Cap=1.0m3, Rocky Soil)
27.05 19.68
m3/hr m3/hr
m3/hr
Trench Excavation (Cap=0.4m3, Hard Soil) Trench Excavation (Cap=0.4m3, Rocky Soil) Trench Excavation (Cap=0.5m3, Normal Soil)
33.30 21.10 16.32 33.41
Trench Excavation (Cap=0.5m3, Hard Soil) Trench Excavation (Cap=0.5m3, Rocky Soil)
21.17 16.37
m3/hr m3/hr
EP2.3.1 EP2.3.2 EP2.3.3 EP2.3.4 EP2.3.5 EP2.3.6
Trench Excavation Trench Excavation (Cap=0.4m3, Normal Soil)
m3/hr m3/hr
m3/hr m3/hr m3/hr
EP2.4.1 EP2.4.2
Foundation Backfilling Foundation Backfilling (Cap=0.8m3, Normal Soil) Foundation Backfilling (Cap=1.0m3, Normal Soil)
22.42 23.08
m3/hr m3/hr
EP2.5.1 EP2.5.2
Trench Backfilling Trench Backfilling (Cap=0.4m3, Normal Soil) Trench Backfilling (Cap=0.5m3, Normal Soil)
18.42 18.75
m3/hr m3/hr
47.01 235.06
m3/hr m2/hr
63.03
m3/hr
420.17
m2/hr
EP4.1.1
Soil Loading / Filling Load/Fill by Backhoe (Cap=0.8m3)
42.69
m3/hr
EP4.1.2 EP4.1.3 EP4.1.4
Load/Fill by Backhoe (Cap=1.0m3) Load/Fill by Loader (Cap=1.5m3) Load/Fill by Loader (Cap=2.4m3)
43.90 58.57 65.82
m3/hr m3/hr m3/hr
8.33 9.42 10.83
m3/hr m3/hr m3/hr m3/hr m3/hr
EMBANKMENT WORKS
EP3.1.1 EP3.1.2
Embankment Grading Embankment Grading (Volume) Embankment Grading (Area)
EP3.2.1
Embankment Compaction Embankment Compaction (Volume)
EP3.2.2
Embankment Compaction (Area) QUARRYING & EARTH HANDLING WORKS
EP4.2.1 EP4.2.2 EP4.2.3 EP4.2.4 EP4.2.5 EP4.2.6 EP4.2.7 EP4.2.8
EP4.3.1 EP4.3.2 EP4.3.3 EP4.3.4 EP4.3.5 EP4.3.6 EP4.3.7
Soil Hauling (loading by Backhoe) Hauling (AHD= 30km Cap=15m3) (load by backhoe) Hauling (AHD= 25km Cap=15m3) (load by backhoe) Hauling (AHD= 20km Cap=15m3) (load by backhoe) Hauling (AHD= 15km Cap=15m3) (load by backhoe) Hauling (AHD= 10km Cap=15m3) (load by backhoe) Hauling (AHD= 7km Cap=15m3) (load by backhoe) Hauling (AHD= 5km Cap=15m3) (load by backhoe) Hauling (Free Haul Cap=15m3) (load by backhoe) Soil Hauling (loading by Payloader) Hauling (AHD= 30km Cap=15m3) (load by payloader) Hauling (AHD= 25km Cap=15m3) (load by payloader) Hauling (AHD= 20km Cap=15m3) (load by payloader) Hauling (AHD= 15km Cap=15m3) (load by payloader) Hauling (AHD= 10km Cap=15m3) (load by payloader) Hauling (AHD= 7km Cap=15m3) (load by payloader) Hauling (AHD= 5km Cap=15m3) (load by payloader)
12.75 15.49 17.79 19.74 25.29
8.79 10.01 11.63 13.87 15.40 20.06 22.58
m3/hr m3/hr m3/hr
m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr
EP4.3.8
Hauling (Free Haul Cap=15m3) (load by payloader)
30.13
m3/hr
EP4.4.1
Rock Breaking Rock Breaking by Backhoe with Breaker
21.63
m3/hr
EP4.5.1 EP4.5.2
Rock Loading / Filling Rock Load/Fill by Loader (Cap=1.5m3) Rock Load/Fill by Loader (Cap=2.4m3)
43.93 49.37
m3/hr m3/hr
EP4.6.1
Rock Hauling (loading by Payloader) Hauling (AHD= 30km Cap=15m3) (load by payloader)
5.84
m3/hr
EP4.6.2 EP4.6.3 EP4.6.4 EP4.6.5 EP4.6.6 EP4.6.7
Hauling (AHD= 25km Cap=15m ) (load by payloader) Hauling (AHD= 20km Cap=15m3) (load by payloader) Hauling (AHD= 15km Cap=15m3) (load by payloader) Hauling (AHD= 10km Cap=15m3) (load by payloader) Hauling (AHD= 7km Cap=15m3) (load by payloader) Hauling (AHD= 5km Cap=15m3) (load by payloader)
6.70 7.88 9.55 11.89 14.46 16.60
m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr
EP4.7.1 EP4.7.2
Stone Loading Stone Load/Fill by Loader (Cap=1.5m3) Stone Load/Fill by Loader (Cap=2.4m3)
49.78 55.95
m3/hr m3/hr
EP4.8.1 EP4.8.2 EP4.8.3
Stone Hauling Stone Hauling AHD=30kms Stone Hauling AHD=25kms Stone Hauling AHD=20kms
6.61 7.60 8.93
EP4.8.4 EP4.8.5 EP4.8.6 EP4.8.7
Stone Hauling AHD=15kms Stone Hauling AHD=10kms Stone Hauling AHD=7kms Stone Hauling AHD=5kms
10.82 13.48 16.39 18.81
m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr
EP4.9.1 EP4.9.2
Boulder Loading / Filling Boulder Load/Fill by Loader (Cap=1.5m3) Boulder Load/Fill by Loader (Cap=2.4m3)
24.85 29.62
m3/hr m3/hr
EP4.10.1 EP4.10.2
Boulder Hauling Boulder Hauling AHD=30kms Boulder Hauling AHD=25kms
3.33 3.83
EP4.10.3 EP4.10.4 EP4.10.5 EP4.10.6 EP4.10.7
Boulder Hauling AHD=20kms Boulder Hauling AHD=15kms Boulder Hauling AHD=10kms Boulder Hauling AHD=7kms Boulder Hauling AHD=5kms
4.52 5.50 6.89 8.42 9.72
m3/hr m3/hr m3/hr m3/hr m3/hr
3
PAVEMENT BREAKING
m3/hr
m3/hr m3/hr
EP5.1.1 EP5.1.2
Asphalt Pavement Breaking Asphalt Breaking t=50mm (Area) Asphalt Breaking t=50mm (Volume)
23.40 1.17
EP5.1.3 EP5.1.4
Asphalt Breaking t>50mm (Area) Asphalt Breaking t>50mm (Volume)
22.20 1.66
EP5.2.1 EP5.2.2 EP5.2.3 EP5.2.4
Concrete Pavement Breaking Concrete Breaking t=150mm (Area) Concrete Breaking t=150mm (Volume) Concrete Breaking t=200mm (Area) Concrete Breaking t=200mm (Volume)
17.18 2.58 13.75 3.16
EP5.2.5 EP5.2.6
Concrete Breaking t=300mm (Area) Concrete Breaking t=300mm (Volume)
12.76 3.19
m3/hr m2/hr m3/hr m2/hr m3/hr
479.83 71.97
m2/hr m3/hr
m2/hr m3/hr m2/hr m3/hr
m2/hr
WATERING EP6.1.1 EP6.1.2
Watering (Area) Watering (Volume) PILEWORKS
EP7.1.1 EP7.1.2 EP7.1.3
Pile Driving Pile Driving (PC 400mmx400mm) Pile Driving (Steel H350mmx350mm) Pile Driving (Sheet Type 2)
2.54 3.21 5.71
lm/hr lm/hr lm/hr
EP7.2.1
Pile Extraction Pile Extraction (Sheet Type 2)
8.09
lm/hr
EP7.3.1 EP7.3.2 EP7.3.3
Pile Load / Unload Load/Unload (PC 400mmx400mm) Load/Unload (Steel H350mmx350mm) Load/Unload (Sheet Type 2)
36.00 36.61 43.86
lm/hr lm/hr lm/hr
PIPELAYING WORKS
EP8.1.1 EP8.1.2 EP8.1.3 EP8.1.4
Pipe Laying Pipe Laying 1600mmØ-2000mmØ by Crane Pipe Laying 1200mmØ - 1500mmØ by Crane Pipe Laying 600mmØ - 1000mmØ by Crane Pipe Laying 300mmØ - 500mmØ by Crane
5.45 5.54 5.63 5.71
lm/hr lm/hr lm/hr lm/hr
EP8.2.1 EP8.2.2 EP8.2.3 EP8.2.4
Pipe Loading / Unloading Pipe Load/Unload 1600mmØ-2000mmØ by Crane Pipe Load/Unload 1200mmØ - 1500mmØ by Crane Pipe Load/Unload 600mmØ - 1000mmØ by Crane Pipe Load/Unload 300mmØ - 500mmØ by Crane
7.50 7.66 7.83 8.00
lm/hr lm/hr lm/hr lm/hr
Pipe Hauling
EP8.3.1.1 EP8.3.1.2 EP8.3.1.3 EP8.3.1.4 EP8.3.2.1 EP8.3.2.2 EP8.3.2.3 EP8.3.2.4 EP8.3.3.1 EP8.3.3.2 EP8.3.3.3 EP8.3.3.4 EP8.3.4.1 EP8.3.4.2 EP8.3.4.3 EP8.3.4.4 EP8.3.5.1 EP8.3.5.2 EP8.3.5.3 EP8.3.5.4 EP8.3.6.1 EP8.3.6.2 EP8.3.6.3 EP8.3.6.4 EP8.3.7.1 EP8.3.7.2 EP8.3.7.3 EP8.3.7.4
AHD = 30kms Pipe Hauling 1600mmØ-2000mmØ AHD=30kms Pipe Hauling 1200mmØ - 1500mmØ AHD=30kms Pipe Hauling 600mmØ - 1000mmØ AHD=30kms Pipe Hauling 300mmØ - 500mmØ AHD=30kms AHD = 25kms Pipe Hauling 1600mmØ-2000mmØ AHD=25kms Pipe Hauling 1200mmØ - 1500mmØ AHD=25kms Pipe Hauling 600mmØ - 1000mmØ AHD=25kms Pipe Hauling 300mmØ - 500mmØ AHD=25kms AHD = 20kms Pipe Hauling 1600mmØ-2000mmØ AHD=20kms Pipe Hauling 1200mmØ - 1500mmØ AHD=20kms Pipe Hauling 600mmØ - 1000mmØ AHD=20kms Pipe Hauling 300mmØ - 500mmØ AHD=20kms AHD = 15kms Pipe Hauling 1600mmØ-2000mmØ AHD=15kms Pipe Hauling 1150mmØ - 1500mmØ AHD=15kms Pipe Hauling 600mmØ - 1000mmØ AHD=15kms Pipe Hauling 300mmØ - 500mmØ AHD=15kms AHD = 10kms Pipe Hauling 1600mmØ-2000mmØ AHD=10kms Pipe Hauling 1100mmØ - 1500mmØ AHD=10kms Pipe Hauling 600mmØ - 1000mmØ AHD=10kms Pipe Hauling 300mmØ - 500mmØ AHD=10kms AHD = 7kms Pipe Hauling 1600mmØ-2000mmØ AHD=7kms Pipe Hauling 1200mmØ - 1500mmØ AHD=7kms Pipe Hauling 600mmØ - 1000mmØ AHD=7kms Pipe Hauling 300mmØ - 500mmØ AHD=7kms AHD = 5kms Pipe Hauling 1600mmØ-2000mmØ AHD=5kms Pipe Hauling 1200mmØ - 1500mmØ AHD=5kms Pipe Hauling 600mmØ - 1000mmØ AHD=5kms Pipe Hauling 300mmØ - 500mmØ AHD=5kms
2.45 2.90 3.40 3.85
lm/hr lm/hr lm/hr lm/hr
2.58 3.01 3.47 3.87
lm/hr lm/hr lm/hr lm/hr
2.73 3.13 3.54 3.89
lm/hr lm/hr lm/hr lm/hr
2.89 3.25 3.61 3.91
lm/hr lm/hr lm/hr lm/hr
3.08 3.38 3.69 3.94
lm/hr lm/hr lm/hr lm/hr
3.20 3.47 3.73 3.95
lm/hr lm/hr lm/hr lm/hr
3.29 3.53 3.76 3.96
lm/hr lm/hr lm/hr lm/hr
5.56 23.65
m3/hr m3/hr
13.04 96.00
tons/hr sqm/hr bags/hr
CONCRETING EP9.1.1 EP9.2.1
Concreting (Crane & Bucket) Concreting (Truck Mounted Pump) MATERIALS HANDLING
EP10.1.1 EP10.1.2 EP10.1.3
Materials Loading / Unloading Rebar Load/Unload Formworks Load/Unload Cement Load/Unload
EP10.2.1.1 EP10.2.1.2 EP10.2.1.3
Materials Hauling AHD=30kms Rebar Hauling AHD=30kms Formworks Hauling AHD=30kms Cement Hauling AHD=30kms
4.20 30.86 45.92
kgs/hr sqm/hr bags/hr
EP10.2.2.1 EP10.2.2.2 EP10.2.2.3
Materials Hauling AHD=25kms Rebar Hauling AHD=25kms Formworks Hauling AHD=25kms Cement Hauling AHD=25kms
4.46 32.68 47.12
kgs/hr sqm/hr bags/hr
EP10.2.3.1 EP10.2.3.2 EP10.2.3.3
Materials Hauling AHD=20kms Rebar Hauling AHD=20kms Formworks Hauling AHD=20kms Cement Hauling AHD=20kms
4.74 34.73 48.39
kgs/hr sqm/hr bags/hr
EP10.2.4.1 EP10.2.4.2 EP10.2.4.3
Materials Hauling AHD=15kms Rebar Hauling AHD=15kms Formworks Hauling AHD=15kms Cement Hauling AHD=15kms
5.06 37.06 49.72
kgs/hr sqm/hr bags/hr
EP10.2.5.1 EP10.2.5.2 EP10.2.5.3
Materials Hauling AHD=10kms Rebar Hauling AHD=10kms Formworks Hauling AHD=10kms Cement Hauling AHD=10kms
5.43 38.38 51.14
kgs/hr sqm/hr bags/hr
EP10.2.6.1 EP10.2.6.2 EP10.2.6.3
Materials Hauling AHD=7kms Rebar Hauling AHD=7kms Formworks Hauling AHD=7kms Cement Hauling AHD=7kms
5.67 41.51 52.02
kgs/hr sqm/hr bags/hr
EP10.2.7.1 EP10.2.7.2 EP10.2.7.3
Materials Hauling AHD=5kms Rebar Hauling AHD=5kms Formworks Hauling AHD=5kms Cement Hauling AHD=5kms
5.85 42.80 52.63
tons/hr sqm/hr bags/hr
EP10.3.1
Water Hauling Water Hauling AHD=30kms
2.33
m3/hr
EP10.3.2 EP10.3.3 EP10.3.4
Water Hauling AHD=25kms Water Hauling AHD=20kms Water Hauling AHD=15kms
2.63 3.02 3.54
EP10.3.5 EP10.3.6 EP10.3.7
Water Hauling AHD=10kms Water Hauling AHD=7kms Water Hauling AHD=5kms
4.27 4.88 5.39
m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr
EP10.4.1 EP10.4.2 EP10.4.3
Fuel Hauling (by Fuel Truck) Water Hauling AHD=30kms Water Hauling AHD=25kms Water Hauling AHD=20kms
1.63 1.67 1.71
li/hr li/hr li/hr
EP10.4.4 EP10.4.5 EP10.4.6 EP10.4.7
Water Hauling AHD=15kms Water Hauling AHD=10kms Water Hauling AHD=7kms Water Hauling AHD=5kms
1.75 1.80 1.83 1.85
li/hr li/hr li/hr li/hr
EP10.5.1 EP10.5.2 EP10.5.3 EP10.5.4 EP10.5.5
Asphalt Hauling Asphalt Hauling AHD=30kms Asphalt Hauling AHD=25kms Asphalt Hauling AHD=20kms Asphalt Hauling AHD=15kms Asphalt Hauling AHD=10kms
4.05 4.48 5.02 5.70 6.52
m3/hr
EP10.5.6 EP10.5.7 EP10.5.8 EP10.5.9 EP10.5.10 EP10.5.11 EP10.5.12 EP10.5.13 EP10.5.14
Asphalt Hauling AHD=7kms Asphalt Hauling AHD=5kms Asphalt Hauling AHD=30kms Asphalt Hauling AHD=25kms Asphalt Hauling AHD=20kms Asphalt Hauling AHD=15kms Asphalt Hauling AHD=10kms Asphalt Hauling AHD=7kms Asphalt Hauling AHD=5kms
7.27 7.82 8.91 9.86 11.03 12.53 14.33 16.00 17.20
m3/hr m3/hr tons/hr tons/hr tons/hr tons/hr tons/hr tons/hr tons/hr
EP10.6.1 EP10.6.2 EP10.6.3
Piles Hauling PC Hauling Piles Steel Hauling Piles Steel Sheet Hauling Piles
17.55 17.90 21.91
lm/hr lm/hr lm/hr
9.76 42.44 11.08 41.04 11.73 39.11
m3/hr m2/hr m3/hr
39.06 355.14 45.98 278.64 52.24 237.47
tons/hr m2/hr tons/hr m2/hr tons/hr m2/hr
9.49 86.27
tons/hr m2/hr
m3/hr m3/hr m3/hr m3/hr
PAVING WORK
EP11.1.1 EP11.1.2 EP11.1.3 EP11.1.4 EP11.1.5 EP11.1.6
Concrete Paving Concrete Paving t=230mm (Volume) Concrete Paving t=230mm (Area) Concrete Paving t=270mm (Volume) Concrete Paving t=270mm (Area) Concrete Paving t=300mm (Volume) Concrete Paving t=300mm (Area)
EP11.2.1 EP11.2.2 EP11.2.3 EP11.2.4 EP11.2.5 EP11.2.6
Asphalt Paving Asphalt Paving t=50mm (Weight) Asphalt Paving t=50mm (Area) Asphalt Paving t=75mm (Weight) Asphalt Paving t=75mm (Area) Asphalt Paving t=100mm (Weight) Asphalt Paving t=100mm (Area)
EP11.3.1 EP11.3.2
Asphalt Compaction Asphalt Compaction t=50mm (Weight) Asphalt Compaction t=50mm (Area)
m2/hr m3/hr m2/hr
EP11.3.3 EP11.3.4 EP11.3.5 EP11.3.6
Asphalt Compaction t=75mm (Weight) Asphalt Compaction t=75mm (Area) Asphalt Compaction t=100mm (Weight) Asphalt Compaction t=100mm (Area)
EP11.4.1 EP11.4.2 EP11.4.3 EP11.4.4 EP11.4.5 EP11.4.6 EP11.4.7 EP11.4.8
Asphalt Spraying Prime Coat Application (Weight) Prime Coat Application (Area) Tack Coat Application (Weight) Tack Coat Application (Area) Asphalt Spraying (1L/sqm) (Weight) Asphalt Spraying (1L/sqm) (Area) Asphalt Spraying (2L/sqm) (Weight) Asphalt Spraying (2L/sqm) (Area)
EP12.1.1 EP12.1.2 EP12.1.3 EP12.1.4 EP12.1.5
BRIDGE WORK PC Girder Installation Type 1 PC Girder Installation Type 2 PC Girder Installation Type 3 PC Girder Installation Type 4 PC Girder Installation Type 5
12.58 76.26 15.35 69.78
tons/hr m2/hr tons/hr m2/hr
0.62 388.35 0.73 1,224.42 0.97 1,014.00 1.24 776.71
tons/hr m2/hr tons/hr m2/hr tons/hr m2/hr tons/hr m2/hr
1.71 2.10 3.72 6.00 7.74
lm/hr lm/hr lm/hr lm/hr lm/hr
5.31 5.71 6.19 6.74 7.36 7.87 8.22
tons/hr tons/hr tons/hr tons/hr tons/hr tons/hr tons/hr
PC Items Handling
EP13.1.1 EP13.1.2 EP13.1.3 EP13.1.4 EP13.1.5 EP13.1.6 EP13.1.7
PC Item (1-2 tons/pc) PC Item (1-2 tons/pc) Hauling AHD=30kms PC Item (1-2 tons/pc) Hauling AHD=25kms PC Item (1-2 tons/pc) Hauling AHD=20kms PC Item (1-2 tons/pc) Hauling AHD=15kms PC Item (1-2 tons/pc) Hauling AHD=10kms PC Item (1-2 tons/pc) Hauling AHD=70kms PC Item (1-2 tons/pc) Hauling AHD=5kms
655.23 327.615614357727
19800
4950
12,549.30
1568.66197183099
1,960.0
773.11
PRODUCTIVITY CALCULATIONS Clearing and Grubbing Trial Strip
Parameter Segment Length Segment Width Depth of Cut Area of Embankment Volume Equipment Specifications Parameter Forward Speed Reverse Speed Blade Width Blade Capacity Fuel Consumption
Quantity 50.00 5.00 0.15 250.00 37.50 Bulddozer D7 Quantity 1.35 1.35 3.70 3.50 27.00
Unit km/hr km/hr m m3 li/hr
Rate
Time Required hrs
Time-Motion Table Activity
First Pass (one side) Maneuver Push Earth to 50m Maneuver Reverse to 50m First Pass (other side) Maneuver Push Earth to 50m Maneuver Reverse to 50m 2nd Pass (one side) Maneuver Push Earth to 50m Maneuver Reverse to 50m 2nd Pass (other side) Maneuver Push Earth to 50m Maneuver Reverse to 50m Total Productivity
Unit m m m sm m3
1.35 1.35
1.35 1.35
1.35 1.35
1.35 1.35
Time Required minutes
0.01 0.04 0.01 0.04
0.83 2.22 0.83 2.22
0.01 0.04 0.01 0.04
0.83 2.22 0.83 2.22
0.01 0.04 0.01 0.04
0.83 2.22 0.83 2.22
0.01 0.04 0.01 0.04
0.83 2.22 0.83 2.22
0.41
24.44
92.05 m3/hr
Productivity
613.64 m2/hr
PRODUCTIVITY CALCULATIONS Dressing Trial Strip
Parameter Segment Length Segment Width Depth of Cut Area of Embankment Volume Equipment Specifications Parameter Forward Speed Reverse Speed Blade Width Blade Capacity Fuel Consumption
Quantity 50.00 5.00 0.25 250.00 62.50 Bulldozer D7 Quantity 0.81 0.81 3.70 3.50 27.00
Unit km/hr km/hr m m3 li/hr
Rate
Time Required hrs
Time-Motion Table Activity
First Pass (one side) Maneuver Push Earth to 50m Maneuver Reverse to 50m First Pass (other side) Maneuver Push Earth to 50m Maneuver Reverse to 50m 2nd Pass (one side) Maneuver Push Earth to 50m Maneuver Reverse to 50m 2nd Pass (other side) Maneuver Push Earth to 50m Maneuver Reverse to 50m Total Productivity
Unit m m m sm m3
0.81 0.81
0.81 0.81
0.81 0.81
0.81 0.81
Time Required minutes
0.01 0.06 0.01 0.06
0.83 3.70 0.83 3.70
0.01 0.06 0.01 0.06
0.83 3.70 0.83 3.70
0.01 0.06 0.01 0.06
0.83 3.70 0.83 3.70
0.01 0.06 0.01 0.06
0.83 3.70 0.83 3.70
0.60
36.30
103.32 m3/hr
Productivity
413.27 m2/hr
PRODUCTIVITY CALCULATIONS Ground Leveling Trial Strip
Parameter Segment Length Segment Width Thickness Area of Embankment Volume Equipment Specifications Parameter Forward Speed Reverse Speed Blade Width Blade Capacity Fuel Consumption
Quantity 50.00 5.00 0.30 250.00 75.00 Bulldozer D7 Quantity 1.04 0.96 3.70 3.50 27.00
Unit km/hr km/hr m m3 li/hr
Rate
Time Required hrs
Time-Motion Table Activity
First Pass (one side) Maneuver Push Earth to 50m Maneuver Reverse to 50m First Pass (other side) Maneuver Push Earth to 50m Maneuver Reverse to 50m 2nd Pass (one side) Maneuver Push Earth to 50m Maneuver Reverse to 50m 2nd Pass (other side) Maneuver Push Earth to 50m Maneuver Reverse to 50m 3rd Pass (one side) Maneuver Push Earth to 50m
Unit m m m sm m3
Time Required minutes
0.01 0.05 0.01 0.05
0.83 2.88 0.83 3.13
0.01 0.05 0.01 0.05
0.83 2.88 0.83 3.13
0.01 0.05 0.01 0.05
0.83 2.88 0.83 3.13
0.96
0.01 0.05 0.01 0.05
0.83 2.88 0.83 3.13
1.04
0.01 0.05
0.83 2.88
1.04 0.96
1.04 0.96
1.04 0.96
1.04
Maneuver Reverse to 50m 3rd Pass (other side) Maneuver Push Earth to 50m Maneuver Reverse to 50m Total
0.96
1.04 0.96
0.01 0.05
0.83 3.13
0.01 0.05 0.01 0.05
0.83 2.88 0.83 3.13
0.77
46.06
Productivity
97.70 m3/hr
Productivity
325.68 m2/hr
PRODUCTIVITY CALCULATIONS Ground Cutting Trial Strip
Parameter Segment Length Segment Width Depth of Cut Area of Embankment Volume Equipment Specifications Parameter Forward Speed Reverse Speed Blade Width Blade Capacity Fuel Consumption
Quantity 50.00 5.00 0.50 250.00 125.00 Bulldozer D7 Quantity 0.32 0.96 3.70 3.50 27.00
Unit km/hr km/hr m m3 li/hr
Rate
Time Required hrs
Time-Motion Table Activity
First Pass (one side) Maneuver Push Earth to 50m Maneuver Reverse to 50m First Pass (other side) Maneuver Push Earth to 50m Maneuver Reverse to 50m 2nd Pass (one side) Maneuver Push Earth to 50m Maneuver Reverse to 50m 2nd Pass (other side) Maneuver Push Earth to 50m Maneuver Reverse to 50m 3rd Pass (one side) Maneuver Push Earth to 50m
Unit m m m sm m3
Time Required minutes
0.01 0.16 0.01 0.05
0.83 9.38 0.83 3.13
0.01 0.16 0.01 0.05
0.83 9.38 0.83 3.13
0.01 0.16 0.01 0.05
0.83 9.38 0.83 3.13
0.96
0.01 0.16 0.01 0.05
0.83 9.38 0.83 3.13
0.32
0.01 0.16
0.83 9.38
0.32 0.96
0.32 0.96
0.32 0.96
0.32
Maneuver Reverse to 50m 3rd Pass (other side) Maneuver Push Earth to 50m Maneuver Reverse to 50m Total
0.96
0.32 0.96
0.01 0.05
0.83 3.13
0.01 0.16 0.01 0.05
0.83 9.38 0.83 3.13
1.42
85.00
Productivity
88.24 m3/hr
Productivity
176.47 m2/hr
PRODUCTIVITY CALCULATIONS Embankment Grading Trial Strip
Parameter Segment Length Segment Width Thickness Area of Embankment Volume Equipment Specifications Parameter Forward Speed (Loaded) Reverse Speed (Empty) Blade Width Blade Capacity Fuel Consumption
Quantity 50.00 7.50 0.20 375.00 75.00 Grader 125HP Quantity 6.12 6.48 3.70 1.33 16.00
Unit km/hr km/hr m m3 li/hr
Rate
Time Required hrs
Time-Motion Table Activity
First Pass (one side) Maneuver Push Earth to 50m Maneuver Reverse to 50m First Pass (other side) Maneuver Push Earth to 50m Maneuver Reverse to 50m 2nd Pass (one side) Maneuver Push Earth to 50m Maneuver Reverse to 50m 2nd Pass (other side) Maneuver Push Earth to 50m Maneuver Reverse to 50m 3rd Pass (one side) Maneuver Push Earth to 50m Maneuver Reverse to 50m 3rd Pass (other side) Maneuver
Unit m m m m2 m3
6.12 6.48
6.12 6.48
6.12 6.48
6.12 6.48
6.12 6.48
Time Required minutes
0.13 0.01 0.13 0.01
7.50 0.49 7.50 0.46
0.13 0.01 0.13 0.01
7.50 0.49 7.50 0.46
0.13 0.01 0.13 0.01
7.50 0.49 7.50 0.46
0.13 0.01 0.13 0.01
7.50 0.49 7.50 0.46
0.13 0.01 0.13 0.01
7.50 0.49 7.50 0.46
0.13
7.50
Push Earth to 50m Maneuver Reverse to 50m Total
6.12 6.48
0.01 0.13 0.01
0.49 7.50 0.46
1.60
95.72
Productivity
47.01 m3/hr
Productivity
235.06 m2/hr
PRODUCTIVITY CALCULATIONS Compaction Trial Strip
Parameter Segment Length Segment Width Thickness Area of Embankment Volume Equipment Specifications Parameter Forward Speed Reverse Speed Drum Width Fuel Consumption
Quantity 50.00 5.00 0.15 250.00 37.50 Road Roller 10T Quantity 1.88 1.88 1.65 12.00
Unit km/hr km/hr m li/hr
Rate
Time Required hrs
Time-Motion Table Activity
1st Pass Maneuver Compact to 50m Maneuver Compact to 50m (Return) Maneuver Compact to 50m Maneuver Compact to 50m (Return) 2nd Pass Maneuver Compact to 50m Maneuver Compact to 50m (Return) Maneuver Compact to 50m Maneuver Compact to 50m (Return) 3rd Pass Maneuver Compact to 50m Maneuver Compact to 50m (Return) Maneuver
Unit m m m sm m3
1.88 1.88 1.88 1.88
1.88 1.88 1.88 1.88
1.88 1.88
Time Required minutes
0.03 0.03 0.03 0.03 0.01 0.03 0.03 0.03
2.00 1.60 2.00 1.60 0.50 1.60 2.00 1.60
0.01 0.03 0.03 0.03 0.01 0.03 0.03 0.03
0.50 1.60 2.00 1.60 0.50 1.60 2.00 1.60
0.01 0.03 0.03 0.03 0.01
0.50 1.60 2.00 1.60 0.50
Compact to 50m Maneuver Compact to 50m (Return) Total
1.88 1.88
0.03 0.03 0.03
1.60 2.00 1.60
0.60
35.70
Productivity
63.03 m3/hr
Productivity
420.17 m2/hr
PRODUCTIVITY CALCULATIONS Embankment Watering Trial Strip
Parameter Segment Length Segment Width Layer Thickness Area of Embankment Volume Distance from Water Source Equipment Specifications Parameter Travel Speed (Loaded) Travel Speed (Empty) Watering Speed (Loaded) Tank Capacity Water Loading Rate Spray Rate Sprayer Width Fuel Consumption
Quantity 200.00 7.50 0.15 1,500.00 225.00 25.00 Water Truck Quantity 40.00 60.00 2.50 4,000.00 3,000.00 3,600.00 3.00 16.00
Unit km/hr km/hr km/hr li li/hr li/hr m li/hr
Rate
Time Required hrs
Time-Motion Table Activity
Load & Haul Water Load Water Haul Water First Pass (one side) Maneuver Spray Water Maneuver Spray Water First Pass (other side) Maneuver Spray Water Maneuver Spray Water 2nd Pass (one side) Maneuver Spray Water Maneuver Spray Water 2nd Pass (other side)
Unit m m m sm m3 km
40.00
2.50 2.50
2.50 2.50
2.50 2.50
Time Required minutes
1.33 0.63
80.00 37.50
0.01 0.08 0.01 0.08
0.83 4.80 0.83 4.80
0.01 0.08 0.01 0.08
0.83 4.80 0.83 4.80
0.01 0.08 0.01 0.08
0.83 4.80 0.83 4.80
Maneuver Spray Water Maneuver Spray Water
2.50
0.01 0.08 0.01 0.08
0.83 4.80 0.83 4.80
60.00
0.42
25.00
3.13
187.57
2.50
Return to Base Travel to Base Total Productivity
71.97 m3/hr
Productivity
479.83 m2/hr
Water Dispensed (li)
-
288.00 288.00 288.00 288.00
288.00 288.00
288.00 288.00
2,304.00 1.54
PRODUCTIVITY CALCULATIONS Bulk Excavation Trial Excavation Area Parameter Segment Length Segment Width Depth of Cut Area of Excavation Maximum Volume
BACKHOE
(Excavation & Stockpiling)
Quantity 15.00 5.00 1.00 75.00 75.00
Unit m m m sm m3
Cap = 0.80 cu.m.
NORMAL SOIL Equipment Specifications Parameter Forward Speed Reverse Speed Bucket Capacity Fuel Consumption Productivity Rates Parameter Cut-Swing-Unload-Swing Area Covered / Position Volume / Position Excavation Duration / Position Number of Positions Total Excavation Duration
Backhoe Quantity
2.63 2.63 0.80 16.00
Quantity 45.00 30.00 30.00 0.47 2.50 1.17
Cap = 0.80 cu.m. Unit km/hr km/hr m3 li/hr
Unit secs m2 m3 hrs positions hrs
Excluding Travel
Time-Motion Table Activity
Maneuver Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing
Rate
Manuever & Wait 0.17 -
Time Required (hours) Cut-Swing Load-Swing 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing
-
0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing
-
0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 -
Total Productivity
HARD SOIL
-
Equipment Specifications Parameter Forward Speed Reverse Speed Bucket Capacity Fuel Consumption Productivity Rates Parameter Cut-Swing-Unload-Swing Area Covered / Position Volume / Position Excavation Duration / Position Number of Positions Total Excavation Duration
Backhoe Quantity
2.63 2.63 0.80 16.00
Quantity 80.00 30.00 30.00 0.83 2.50 2.08
Cap = 0.80 cu.m. Unit km/hr km/hr m3 li/hr
Unit secs m2 m3 hrs positions hrs
Excluding Travel
Time-Motion Table Activity
Maneuver Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing
Rate
Manuever & Wait 0.17 -
Time Required (hours) Cut-Swing Load-Swing 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing
-
0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing
-
0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 -
-
-
Total Productivity
ROCKY SOIL Equipment Specifications Parameter Forward Speed Reverse Speed Bucket Capacity Fuel Consumption Productivity Rates Parameter Cut-Swing-Unload-Swing Area Covered / Position Volume / Position Excavation Duration / Position Number of Positions Total Excavation Duration
Backhoe Quantity
2.63 2.63 0.80 16.00
Quantity 120.00 30.00 30.00 1.25 2.50 3.13
Cap = 0.80 cu.m. Unit km/hr km/hr m3 li/hr
Unit secs m2 m3 hrs positions hrs
Excluding Travel
Time-Motion Table Activity
Maneuver Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing
Rate
Manuever & Wait 0.17 -
Time Required (hours) Cut-Swing Load-Swing 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing
-
0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 -
-
-
-
-
Total Productivity
BACKHOE
Cap = 1.00 cu.m.
NORMAL SOIL Equipment Specifications Parameter Forward Speed Reverse Speed Bucket Capacity Fuel Consumption Productivity Rates Parameter Cut-Swing-Unload-Swing Area Covered / Position Volume / Position Excavation Duration / Position Number of Positions Total Excavation Duration
Backhoe Quantity
2.63 2.63 1.00 16.00
Quantity 45.00 30.00 30.00 0.38 2.50 0.94
Cap = 1.00 cu.m. Unit km/hr km/hr m3 li/hr
Unit secs m2 m3 hrs positions hrs
Excluding Travel
Time-Motion Table Activity
Maneuver Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing
Rate
Manuever & Wait 0.17 -
Time Required (hours) Cut-Swing Load-Swing 0.01 0.01 0.01 0.01 0.01 0.01 0.01
Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing
-
0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing
-
0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 -
-
-
-
-
Total Productivity
HARD SOIL Equipment Specifications Parameter Forward Speed Reverse Speed Bucket Capacity Fuel Consumption Productivity Rates Parameter Cut-Swing-Unload-Swing Area Covered / Position Volume / Position Excavation Duration / Position Number of Positions Total Excavation Duration
Backhoe Quantity
2.63 2.63 1.00 16.00
Quantity 80.00 30.00 30.00 0.67 2.50 1.67
Cap = 1.00 cu.m. Unit km/hr km/hr m3 li/hr
Unit secs m2 m3 hrs positions hrs
Excluding Travel
Time-Motion Table Activity
Maneuver Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing
Rate
Manuever & Wait 0.17 -
Time Required (hours) Cut-Swing Load-Swing 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing
-
0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing
-
0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 -
Total Productivity
ROCKY SOIL Equipment Specifications Parameter Forward Speed Reverse Speed Bucket Capacity Fuel Consumption
Backhoe Quantity
2.63 2.63 1.00 16.00
Cap = 1.00 cu.m. Unit km/hr km/hr m3 li/hr
-
Productivity Rates Parameter Cut-Swing-Unload-Swing Area Covered / Position Volume / Position Excavation Duration / Position Number of Positions Total Excavation Duration
Quantity 120.00 30.00 30.00 1.00 2.50 2.50
Unit secs m2 m3 hrs positions hrs
Excluding Travel
Time-Motion Table Activity
Maneuver Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position
Rate
Manuever & Wait 0.17 -
Time Required (hours) Cut-Swing Load-Swing 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 -
Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing
-
0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing
-
0.03 0.03 0.03 -
Total Productivity
-
Case Description Case Description 15.00 Cut-Swing-Unload-Swing 25.00 Transfer Position 30.00 35.00 Maneuver
Time Required (hours) Transfer Position
Stockpile Volume Time Required (minutes)
Total
-
0.17 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
10.00 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75
Position
Cycle
30.00 cu.m. Volume (m
Position Running Total
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80
0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 8.80 9.60 10.40 11.20 12.00
0.00 -
0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.00 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.14 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80
12.80 13.60 14.40 15.20 16.00 16.80 17.60 18.40 19.20 20.00 20.80 21.60 22.40 23.20 24.00 24.80 25.60 26.40 27.20 28.00 28.80 29.60 30.40 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 8.80 9.60 10.40 11.20 12.00 12.80 13.60 14.40 15.20 16.00 16.80 17.60 18.40 19.20 20.00 20.80 21.60 22.40 23.20 24.00
0.00 -
0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.00 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 -
0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.14 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 -
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 -
24.80 25.60 26.40 27.20 28.00 28.80 29.60 30.40 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 8.80 9.60 10.40 11.20 12.00 12.80 13.60 14.40 -
-
1.35 55.86 m3/hr
-
-
25.75 75.2 m3
-
Time Required (hours) Transfer Position
Stockpile Volume Time Required (minutes)
Total
-
0.17 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
10.00 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33
Position
Cycle
30.00 cu.m. Volume (m
Position Running Total
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80
0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 8.80 9.60 10.40 11.20 12.00 12.80 13.60 14.40 15.20 16.00 16.80 17.60 18.40 19.20 20.00 20.80 21.60 22.40 23.20 24.00 24.80
0.00 0.00 -
0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.00 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.00 0.02 0.02 0.02 0.02 0.02 0.02 0.02
1.33 1.33 1.33 1.33 1.33 1.33 1.33 0.14 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 0.14 1.33 1.33 1.33 1.33 1.33 1.33 1.33
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80
25.60 26.40 27.20 28.00 28.80 29.60 30.40 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 8.80 9.60 10.40 11.20 12.00 12.80 13.60 14.40 15.20 16.00 16.80 17.60 18.40 19.20 20.00 20.80 21.60 22.40 23.20 24.00 24.80 25.60 26.40 27.20 28.00 28.80 29.60 30.40 0.80 1.60 2.40 3.20 4.00 4.80 5.60
-
0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 -
1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 -
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 -
6.40 7.20 8.00 8.80 9.60 10.40 11.20 12.00 12.80 13.60 14.40 -
-
2.26 33.27 m3/hr
-
-
38.00 75.2 m3
-
Time Required (hours) Transfer Position
Stockpile Volume Time Required (minutes)
Total
0.00 -
0.17 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.00 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
10.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 0.14 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00
Position
Cycle
30.00 cu.m. Volume (m
Position Running Total
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80
0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 8.80 9.60 10.40 11.20 12.00 12.80 13.60 14.40 15.20 16.00 16.80 17.60 18.40 19.20 20.00 20.80 21.60 22.40 23.20 24.00 24.80 25.60 26.40 27.20 28.00 28.80 29.60 30.40 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40
0.00 -
0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.00 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 -
2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 0.14 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 -
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 -
7.20 8.00 8.80 9.60 10.40 11.20 12.00 12.80 13.60 14.40 15.20 16.00 16.80 17.60 18.40 19.20 20.00 20.80 21.60 22.40 23.20 24.00 24.80 25.60 26.40 27.20 28.00 28.80 29.60 30.40 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 8.80 9.60 10.40 11.20 12.00 12.80 13.60 14.40 -
-
-
-
-
-
-
-
-
3.30
-
52.00
22.76 m3/hr
Time Required (hours) Transfer Position -
75.2 m3
Stockpile Volume Time Required (minutes)
Total
0.17 0.01 0.01 0.01 0.01 0.01 0.01 0.01
-
10.00 0.75 0.75 0.75 0.75 0.75 0.75 0.75
Position
Cycle
30.00 cu.m. Volume (m
Position Running Total
1.00 0.80 0.80 0.80 0.80 0.80 0.80
1.00 1.80 2.60 3.40 4.20 5.00 5.80
0.00 -
0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.00 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.14 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80
6.60 7.40 8.20 9.00 9.80 10.60 11.40 12.20 13.00 13.80 14.60 15.40 16.20 17.00 17.80 18.60 19.40 20.20 21.00 21.80 22.60 23.40 24.20 25.00 25.80 26.60 27.40 28.20 29.00 29.80 30.60 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 8.80 9.60 10.40 11.20 12.00 12.80 13.60 14.40 15.20 16.00 16.80 17.60
0.00 -
0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.00 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 -
0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.14 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 -
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 -
18.40 19.20 20.00 20.80 21.60 22.40 23.20 24.00 24.80 25.60 26.40 27.20 28.00 28.80 29.60 30.40 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 8.80 9.60 10.40 11.20 12.00 12.80 13.60 14.40 -
-
-
-
-
-
-
-
-
1.35
-
25.75
56.01 m3/hr
Time Required (hours) Transfer Position -
75.4 m3
Stockpile Volume Time Required (minutes)
Total
0.17 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
-
10.00 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33
Position
Cycle
30.00 cu.m. Volume (m
Position Running Total
1.00 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80
1.00 1.80 2.60 3.40 4.20 5.00 5.80 6.60 7.40 8.20 9.00 9.80 10.60 11.40 12.20 13.00 13.80 14.60 15.40 16.20 17.00 17.80 18.60
0.00 -
0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.00 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 0.14 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80
19.40 20.20 21.00 21.80 22.60 23.40 24.20 25.00 25.80 26.60 27.40 28.20 29.00 29.80 30.60 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 8.80 9.60 10.40 11.20 12.00 12.80 13.60 14.40 15.20 16.00 16.80 17.60 18.40 19.20 20.00 20.80 21.60 22.40 23.20 24.00 24.80 25.60 26.40 27.20 28.00 28.80 29.60 30.40
0.00 -
0.00 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 -
0.14 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 -
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 -
0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 8.80 9.60 10.40 11.20 12.00 12.80 13.60 14.40 -
-
2.26 33.36 m3/hr
-
-
38.00 75.4 m3
-
Time Required (hours) Transfer Position
Stockpile Volume Time Required (minutes)
Total
0.00
0.17 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.00
10.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 0.14
Position
Cycle
30.00 cu.m. Volume (m
Position Running Total
1.00 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 -
1.00 1.80 2.60 3.40 4.20 5.00 5.80 6.60 7.40 8.20 9.00 9.80 10.60 11.40 12.20 13.00 13.80 14.60 15.40 16.20 17.00 17.80 18.60 19.40 20.20 21.00 21.80 22.60 23.40 24.20 25.00 25.80 26.60 27.40 28.20 29.00 29.80 30.60 -
0.00 -
0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.00 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 0.14 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80
0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 8.80 9.60 10.40 11.20 12.00 12.80 13.60 14.40 15.20 16.00 16.80 17.60 18.40 19.20 20.00 20.80 21.60 22.40 23.20 24.00 24.80 25.60 26.40 27.20 28.00 28.80 29.60 30.40 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 8.80 9.60 10.40 11.20 12.00
-
0.03 0.03 0.03 -
2.00 2.00 2.00 -
0.80 0.80 0.80 -
12.80 13.60 14.40 -
-
3.30 22.82 m3/hr
-
-
52.00 75.4 m3
-
Stockpile
75.00 cu.m.
Volume (m3) Cycle
Stockpile Running Total
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80
0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 8.80 9.60 10.40 11.20 12.00
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80
12.80 13.60 14.40 15.20 16.00 16.80 17.60 18.40 19.20 20.00 20.80 21.60 22.40 23.20 24.00 24.80 25.60 26.40 27.20 28.00 28.80 29.60 30.40 30.40 31.20 32.00 32.80 33.60 34.40 35.20 36.00 36.80 37.60 38.40 39.20 40.00 40.80 41.60 42.40 43.20 44.00 44.80 45.60 46.40 47.20 48.00 48.80 49.60 50.40 51.20 52.00 52.80 53.60 54.40
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 -
55.20 56.00 56.80 57.60 58.40 59.20 60.00 60.80 60.80 61.60 62.40 63.20 64.00 64.80 65.60 66.40 67.20 68.00 68.80 69.60 70.40 71.20 72.00 72.80 73.60 74.40 75.20 -
-
75.2 m3
-
Stockpile
75.00 cu.m.
Volume (m ) 3
Cycle
Stockpile Running Total
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80
0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 8.80 9.60 10.40 11.20 12.00 12.80 13.60 14.40 15.20 16.00 16.80 17.60 18.40 19.20 20.00 20.80 21.60 22.40 23.20 24.00 24.80
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80
25.60 26.40 27.20 28.00 28.80 29.60 30.40 30.40 31.20 32.00 32.80 33.60 34.40 35.20 36.00 36.80 37.60 38.40 39.20 40.00 40.80 41.60 42.40 43.20 44.00 44.80 45.60 46.40 47.20 48.00 48.80 49.60 50.40 51.20 52.00 52.80 53.60 54.40 55.20 56.00 56.80 57.60 58.40 59.20 60.00 60.80 60.80 61.60 62.40 63.20 64.00 64.80 65.60 66.40
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 -
67.20 68.00 68.80 69.60 70.40 71.20 72.00 72.80 73.60 74.40 75.20 -
-
75.2 m3
-
Stockpile
75.00 cu.m.
Volume (m ) 3
Cycle
Stockpile Running Total
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80
0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 8.80 9.60 10.40 11.20 12.00 12.80 13.60 14.40 15.20 16.00 16.80 17.60 18.40 19.20 20.00 20.80 21.60 22.40 23.20 24.00 24.80 25.60 26.40 27.20 28.00 28.80 29.60 30.40 30.40 31.20 32.00 32.80 33.60 34.40 35.20 36.00 36.80
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 -
37.60 38.40 39.20 40.00 40.80 41.60 42.40 43.20 44.00 44.80 45.60 46.40 47.20 48.00 48.80 49.60 50.40 51.20 52.00 52.80 53.60 54.40 55.20 56.00 56.80 57.60 58.40 59.20 60.00 60.80 60.80 61.60 62.40 63.20 64.00 64.80 65.60 66.40 67.20 68.00 68.80 69.60 70.40 71.20 72.00 72.80 73.60 74.40 75.20 -
-
-
-
-
75.2 m3
Stockpile
75.00 cu.m.
Volume (m ) 3
Cycle
Stockpile Running Total
1.00 0.80 0.80 0.80 0.80 0.80 0.80
1.00 1.80 2.60 3.40 4.20 5.00 5.80
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80
6.60 7.40 8.20 9.00 9.80 10.60 11.40 12.20 13.00 13.80 14.60 15.40 16.20 17.00 17.80 18.60 19.40 20.20 21.00 21.80 22.60 23.40 24.20 25.00 25.80 26.60 27.40 28.20 29.00 29.80 30.60 30.60 31.40 32.20 33.00 33.80 34.60 35.40 36.20 37.00 37.80 38.60 39.40 40.20 41.00 41.80 42.60 43.40 44.20 45.00 45.80 46.60 47.40 48.20
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 -
49.00 49.80 50.60 51.40 52.20 53.00 53.80 54.60 55.40 56.20 57.00 57.80 58.60 59.40 60.20 61.00 61.00 61.80 62.60 63.40 64.20 65.00 65.80 66.60 67.40 68.20 69.00 69.80 70.60 71.40 72.20 73.00 73.80 74.60 75.40 -
-
-
-
-
75.4 m3
Stockpile
75.00 cu.m.
Volume (m3) Cycle
Stockpile Running Total
1.00 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80
1.00 1.80 2.60 3.40 4.20 5.00 5.80 6.60 7.40 8.20 9.00 9.80 10.60 11.40 12.20 13.00 13.80 14.60 15.40 16.20 17.00 17.80 18.60
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80
19.40 20.20 21.00 21.80 22.60 23.40 24.20 25.00 25.80 26.60 27.40 28.20 29.00 29.80 30.60 30.60 31.40 32.20 33.00 33.80 34.60 35.40 36.20 37.00 37.80 38.60 39.40 40.20 41.00 41.80 42.60 43.40 44.20 45.00 45.80 46.60 47.40 48.20 49.00 49.80 50.60 51.40 52.20 53.00 53.80 54.60 55.40 56.20 57.00 57.80 58.60 59.40 60.20 61.00
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 -
61.00 61.80 62.60 63.40 64.20 65.00 65.80 66.60 67.40 68.20 69.00 69.80 70.60 71.40 72.20 73.00 73.80 74.60 75.40 -
-
75.4 m3
-
Stockpile
75.00 cu.m.
Volume (m ) 3
Cycle
Stockpile Running Total
1.00 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 -
1.00 1.80 2.60 3.40 4.20 5.00 5.80 6.60 7.40 8.20 9.00 9.80 10.60 11.40 12.20 13.00 13.80 14.60 15.40 16.20 17.00 17.80 18.60 19.40 20.20 21.00 21.80 22.60 23.40 24.20 25.00 25.80 26.60 27.40 28.20 29.00 29.80 30.60 30.60
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80
31.40 32.20 33.00 33.80 34.60 35.40 36.20 37.00 37.80 38.60 39.40 40.20 41.00 41.80 42.60 43.40 44.20 45.00 45.80 46.60 47.40 48.20 49.00 49.80 50.60 51.40 52.20 53.00 53.80 54.60 55.40 56.20 57.00 57.80 58.60 59.40 60.20 61.00 61.00 61.80 62.60 63.40 64.20 65.00 65.80 66.60 67.40 68.20 69.00 69.80 70.60 71.40 72.20 73.00
0.80 0.80 0.80 -
73.80 74.60 75.40 -
-
75.4 m3
-
PRODUCTIVITY CALCULATIONS Foundation Excavation Trial Excavation Area Parameter Segment Length Segment Width Depth of Excavation Area of Excavation Maximum Volume
BACKHOE
Excavation & Stockpiling
Quantity 26.00 8.00 2.00 40.00 80.00
Unit m m m sm m3
Remarks
10 Footings
Cap = 0.80 cu.m.
NORMAL SOIL Equipment Specifications Parameter Forward Speed Reverse Speed Bucket Capacity Fuel Consumption Productivity Rates Parameter Cut-Swing-Unload-Swing Area Covered / Position Volume / Position Excavation Duration / Position Number of Positions Total Excavation Duration
Backhoe Quantity
2.63 2.63 0.80 16.00
Quantity 60.00 4.00 8.00 0.17 10.00 1.67
Cap = 0.80 cu.m. Unit km/hr km/hr m3 li/hr
Unit secs m2 m3 hrs positions hrs
Excluding Travel
Time-Motion Table Activity
Maneuver Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing
Rate
Manuever & Wait 0.17 -
Time Required (hours) Cut-Swing Load-Swing 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing
-
0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing
-
0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 -
Total Productivity
-
HARD SOIL Equipment Specifications Parameter Forward Speed Reverse Speed Bucket Capacity Fuel Consumption Productivity Rates Parameter Cut-Swing-Unload-Swing Area Covered / Position Volume / Position Excavation Duration / Position Number of Positions Total Excavation Duration
Backhoe Quantity
2.63 2.63 0.80 16.00
Quantity 95.00 4.00 8.00 0.26 10.00 2.64
Cap = 0.80 cu.m. Unit km/hr km/hr m3 li/hr
Unit secs m2 m3 hrs positions hrs
Excluding Travel
Time-Motion Table Activity
Maneuver Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing
Rate
Manuever & Wait 0.17 -
Time Required (hours) Cut-Swing Load-Swing 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing
-
0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing
-
0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 -
Total Productivity
ROCKY SOIL Equipment Specifications Parameter Forward Speed Reverse Speed Bucket Capacity Fuel Consumption Productivity Rates Parameter Cut-Swing-Unload-Swing Area Covered / Position Volume / Position Excavation Duration / Position Number of Positions
Backhoe Quantity
2.63 2.63 0.80 16.00
Quantity 135.00 4.00 8.00 0.38 10.00
Cap = 0.80 cu.m. Unit km/hr km/hr m3 li/hr
Unit secs m2 m3 hrs positions
-
Total Excavation Duration
3.75
hrs
Excluding Travel
Time-Motion Table Activity
Maneuver Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing
Rate
Manuever & Wait 0.17 -
Time Required (hours) Cut-Swing Load-Swing 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04
Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing
-
0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04
Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing
-
0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 -
-
-
Total Productivity
BACKHOE
Cap = 1.00 cu.m.
NORMAL SOIL Equipment Specifications Parameter Forward Speed Reverse Speed Bucket Capacity Fuel Consumption Productivity Rates Parameter Cut-Swing-Unload-Swing Area Covered / Position Volume / Position Excavation Duration / Position Number of Positions Total Excavation Duration
Backhoe Quantity
2.63 2.63 1.00 16.00
Quantity 60.00 4.00 8.00 0.13 10.00 1.33
Cap = 1.00 cu.m. Unit km/hr km/hr m3 li/hr
Unit secs m2 m3 hrs positions hrs
Excluding Travel
Time-Motion Table Activity
Maneuver Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing
Rate
Manuever & Wait 0.17 -
Time Required (hours) Cut-Swing Load-Swing 0.02 0.02 0.02 0.02 0.02 0.02
Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing
-
0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing
-
0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 -
-
-
-
-
Total Productivity
HARD SOIL Equipment Specifications Parameter Forward Speed Reverse Speed Bucket Capacity Fuel Consumption Productivity Rates Parameter Cut-Swing-Unload-Swing Area Covered / Position Volume / Position Excavation Duration / Position Number of Positions Total Excavation Duration
Backhoe Quantity
2.63 2.63 1.00 16.00
Quantity 95.00 4.00 8.00 0.21 10.00 2.11
Cap = 1.00 cu.m. Unit km/hr km/hr m3 li/hr
Unit secs m2 m3 hrs positions hrs
Excluding Travel
Time-Motion Table Activity
Maneuver Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position
Rate
Manuever & Wait 0.17 -
Time Required (hours) Cut-Swing Load-Swing 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 -
Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing
-
0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing
-
0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 -
Total Productivity
ROCKY SOIL Equipment Specifications Parameter Forward Speed Reverse Speed Bucket Capacity Fuel Consumption
Backhoe Quantity
2.63 2.63 1.00 16.00
Cap = 1.00 cu.m. Unit km/hr km/hr m3 li/hr
-
Productivity Rates Parameter Cut-Swing-Unload-Swing Area Covered / Position Volume / Position Excavation Duration / Position Number of Positions Total Excavation Duration
Quantity 135.00 4.00 8.00 0.30 10.00 3.00
Unit secs m2 m3 hrs positions hrs
Excluding Travel
Time-Motion Table Activity
Maneuver Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing
Rate
Manuever & Wait 0.17 -
Time Required (hours) Cut-Swing Load-Swing 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04
Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing
-
0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04
Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing
-
0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 -
Total Productivity
-
Case Description Case Description 15.00 Cut-Swing-Unload-Swing 25.00 Transfer Position 30.00 35.00 Maneuver
Remarks
Length: 2.00 m
Time Required (hours) Transfer Position
Width: 2.00 m
Stockpile Volume Time Required (minutes)
Total
0.02 -
0.17 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
10.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.06 1.00 1.00 1.00
Position
Cycle
8.00 cu.m. Volume (m
Position Running Total
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80
0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 0.80 1.60 2.40
0.02 0.02 0.02 0.02 0.02 -
0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.06 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.06 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.06 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.06 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.06 1.00 1.00
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80
3.20 4.00 4.80 5.60 6.40 7.20 8.00 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 0.80 1.60
0.02 0.02 0.02 -
0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 -
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.06 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.06 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.06 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 -
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 -
2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 -
-
1.99 40.16 m3/hr
-
-
31.06 80 m3
-
Time Required (hours) Transfer Position
Stockpile Volume Time Required (minutes)
Total
0.02 0.02 -
0.17 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.02 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.02 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
10.00 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.06 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.06 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58
Position
Cycle
8.00 cu.m. Volume (m
Position Running Total
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80
0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40
0.02 0.02 0.02 0.02 0.02 -
0.03 0.03 0.02 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.02 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.02 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.02 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.02 0.03 0.03 0.03 0.03 0.03 0.03 0.03
1.58 1.58 1.06 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.06 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.06 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.06 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.06 1.58 1.58 1.58 1.58 1.58 1.58 1.58
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80
7.20 8.00 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 0.80 1.60 2.40 3.20 4.00 4.80 5.60
0.02 0.02 -
0.03 0.03 0.03 0.02 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.02 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 -
1.58 1.58 1.58 1.06 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.06 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 -
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 -
6.40 7.20 8.00 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 -
-
2.96 26.99 m3/hr
-
-
42.73 80 m3
-
Time Required (hours) Transfer Position
Stockpile Volume Time Required (minutes)
Total
0.02 0.02 0.02 0.02 -
0.17 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.02 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.02 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.02 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.02 0.04 0.04
10.00 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 1.06 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 1.06 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 1.06 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 1.06 2.25 2.25
Position
Cycle
8.00 cu.m. Volume (m
Position Running Total
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80
0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 0.80 1.60
0.02 0.02 0.02 0.02 0.02 -
0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.02 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.02 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.02 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.02 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.02 0.04
2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 1.06 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 1.06 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 1.06 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 1.06 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 1.06 2.25
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80
2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 0.80
-
0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 -
2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 -
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 -
1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 -
-
-
-
4.08
-
56.06
19.63 m3/hr
Time Required (hours) Transfer Position -
80 m3
Stockpile Volume Time Required (minutes)
Total
0.17 0.02 0.02 0.02 0.02 0.02 0.02
-
10.00 1.00 1.00 1.00 1.00 1.00 1.00
Position
Cycle
8.00 cu.m. Volume (m
Position Running Total
1.00 0.80 0.80 0.80 0.80 0.80
1.00 1.80 2.60 3.40 4.20 5.00
0.02 0.02 0.02 0.02 0.02 -
0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
1.00 1.00 1.00 1.00 1.06 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.06 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.06 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.06 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.06 1.00 1.00 1.00 1.00 1.00
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80
5.80 6.60 7.40 8.20 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 0.80 1.60 2.40 3.20 4.00
0.02 0.02 0.02 0.02 -
0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 -
1.00 1.00 1.00 1.00 1.00 1.06 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.06 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.06 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.06 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 -
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 -
4.80 5.60 6.40 7.20 8.00 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 -
-
-
-
-
-
-
-
-
1.99
-
31.06
40.26 m3/hr
Time Required (hours) Transfer Position 0.02 0.02
80.2 m3
Stockpile Volume Time Required (minutes)
Total
0.17 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.02 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.02
-
10.00 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.06 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.06
Position
Cycle
8.00 cu.m. Volume (m
Position Running Total
1.00 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 -
1.00 1.80 2.60 3.40 4.20 5.00 5.80 6.60 7.40 8.20 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 -
0.02 0.02 0.02 0.02 -
0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.02 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.02 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.02 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.02 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.06 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.06 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.06 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.06 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80
0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00
0.02 0.02 0.02 -
0.02 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.02 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.02 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 -
1.06 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.06 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.06 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 -
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 -
0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 -
-
2.96 27.05 m3/hr
-
-
42.73 80.2 m3
-
Time Required (hours) Transfer Position
Stockpile Volume Time Required (minutes)
Total
0.02 0.02 0.02 -
0.17 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.02 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.02 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.02 0.04 0.04 0.04 0.04 0.04
10.00 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 1.06 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 1.06 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 1.06 2.25 2.25 2.25 2.25 2.25
Position
Cycle
8.00 cu.m. Volume (m
Position Running Total
1.00 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80
1.00 1.80 2.60 3.40 4.20 5.00 5.80 6.60 7.40 8.20 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 0.80 1.60 2.40 3.20 4.00
0.02 0.02 0.02 0.02 0.02 -
0.04 0.04 0.04 0.04 0.04 0.02 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.02 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.02 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.02 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.02 0.04 0.04 0.04 0.04
2.25 2.25 2.25 2.25 2.25 1.06 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 1.06 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 1.06 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 1.06 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 1.06 2.25 2.25 2.25 2.25
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80
4.80 5.60 6.40 7.20 8.00 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 0.80 1.60 2.40 3.20
0.02 -
0.04 0.04 0.04 0.04 0.04 0.04 0.02 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 -
2.25 2.25 2.25 2.25 2.25 2.25 1.06 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 -
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 -
4.00 4.80 5.60 6.40 7.20 8.00 0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 -
-
4.08 19.68 m3/hr
-
-
56.06 80.2 m3
-
Description wing-Unload-Swing er Position
uver
Stockpile
80.00 cu.m.
Volume (m3) Cycle
Stockpile Running Total
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80
0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 8.00 8.80 9.60 10.40
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80
11.20 12.00 12.80 13.60 14.40 15.20 16.00 16.00 16.80 17.60 18.40 19.20 20.00 20.80 21.60 22.40 23.20 24.00 24.00 24.80 25.60 26.40 27.20 28.00 28.80 29.60 30.40 31.20 32.00 32.00 32.80 33.60 34.40 35.20 36.00 36.80 37.60 38.40 39.20 40.00 40.00 40.80 41.60 42.40 43.20 44.00 44.80 45.60 46.40 47.20 48.00 48.00 48.80 49.60
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 -
50.40 51.20 52.00 52.80 53.60 54.40 55.20 56.00 56.00 56.80 57.60 58.40 59.20 60.00 60.80 61.60 62.40 63.20 64.00 64.00 64.80 65.60 66.40 67.20 68.00 68.80 69.60 70.40 71.20 72.00 72.00 72.80 73.60 74.40 75.20 76.00 76.80 77.60 78.40 79.20 80.00 -
-
80 m3
-
Stockpile
80.00 cu.m.
Volume (m ) 3
Cycle
Stockpile Running Total
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80
0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 8.00 8.80 9.60 10.40 11.20 12.00 12.80 13.60 14.40 15.20 16.00 16.00 16.80 17.60 18.40 19.20 20.00 20.80 21.60 22.40
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80
23.20 24.00 24.00 24.80 25.60 26.40 27.20 28.00 28.80 29.60 30.40 31.20 32.00 32.00 32.80 33.60 34.40 35.20 36.00 36.80 37.60 38.40 39.20 40.00 40.00 40.80 41.60 42.40 43.20 44.00 44.80 45.60 46.40 47.20 48.00 48.00 48.80 49.60 50.40 51.20 52.00 52.80 53.60 54.40 55.20 56.00 56.00 56.80 57.60 58.40 59.20 60.00 60.80 61.60
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 -
62.40 63.20 64.00 64.00 64.80 65.60 66.40 67.20 68.00 68.80 69.60 70.40 71.20 72.00 72.00 72.80 73.60 74.40 75.20 76.00 76.80 77.60 78.40 79.20 80.00 -
-
80 m3
-
Stockpile
80.00 cu.m.
Volume (m ) 3
Cycle
Stockpile Running Total
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80
0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 8.00 8.80 9.60 10.40 11.20 12.00 12.80 13.60 14.40 15.20 16.00 16.00 16.80 17.60 18.40 19.20 20.00 20.80 21.60 22.40 23.20 24.00 24.00 24.80 25.60 26.40 27.20 28.00 28.80 29.60 30.40 31.20 32.00 32.00 32.80 33.60
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80
34.40 35.20 36.00 36.80 37.60 38.40 39.20 40.00 40.00 40.80 41.60 42.40 43.20 44.00 44.80 45.60 46.40 47.20 48.00 48.00 48.80 49.60 50.40 51.20 52.00 52.80 53.60 54.40 55.20 56.00 56.00 56.80 57.60 58.40 59.20 60.00 60.80 61.60 62.40 63.20 64.00 64.00 64.80 65.60 66.40 67.20 68.00 68.80 69.60 70.40 71.20 72.00 72.00 72.80
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 -
73.60 74.40 75.20 76.00 76.80 77.60 78.40 79.20 80.00 -
-
-
80 m3
Stockpile
80.00 cu.m.
Volume (m ) 3
Cycle
Stockpile Running Total
1.00 0.80 0.80 0.80 0.80 0.80
1.00 1.80 2.60 3.40 4.20 5.00
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80
5.80 6.60 7.40 8.20 8.20 9.00 9.80 10.60 11.40 12.20 13.00 13.80 14.60 15.40 16.20 16.20 17.00 17.80 18.60 19.40 20.20 21.00 21.80 22.60 23.40 24.20 24.20 25.00 25.80 26.60 27.40 28.20 29.00 29.80 30.60 31.40 32.20 32.20 33.00 33.80 34.60 35.40 36.20 37.00 37.80 38.60 39.40 40.20 40.20 41.00 41.80 42.60 43.40 44.20
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 -
45.00 45.80 46.60 47.40 48.20 48.20 49.00 49.80 50.60 51.40 52.20 53.00 53.80 54.60 55.40 56.20 56.20 57.00 57.80 58.60 59.40 60.20 61.00 61.80 62.60 63.40 64.20 64.20 65.00 65.80 66.60 67.40 68.20 69.00 69.80 70.60 71.40 72.20 72.20 73.00 73.80 74.60 75.40 76.20 77.00 77.80 78.60 79.40 80.20 -
-
-
-
-
80.2 m3
Stockpile
80.00 cu.m.
Volume (m ) 3
Cycle
Stockpile Running Total
1.00 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 -
1.00 1.80 2.60 3.40 4.20 5.00 5.80 6.60 7.40 8.20 8.20 9.00 9.80 10.60 11.40 12.20 13.00 13.80 14.60 15.40 16.20 16.20
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80
17.00 17.80 18.60 19.40 20.20 21.00 21.80 22.60 23.40 24.20 24.20 25.00 25.80 26.60 27.40 28.20 29.00 29.80 30.60 31.40 32.20 32.20 33.00 33.80 34.60 35.40 36.20 37.00 37.80 38.60 39.40 40.20 40.20 41.00 41.80 42.60 43.40 44.20 45.00 45.80 46.60 47.40 48.20 48.20 49.00 49.80 50.60 51.40 52.20 53.00 53.80 54.60 55.40 56.20
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 -
56.20 57.00 57.80 58.60 59.40 60.20 61.00 61.80 62.60 63.40 64.20 64.20 65.00 65.80 66.60 67.40 68.20 69.00 69.80 70.60 71.40 72.20 72.20 73.00 73.80 74.60 75.40 76.20 77.00 77.80 78.60 79.40 80.20 -
-
80.2 m3
-
Stockpile
80.00 cu.m.
Volume (m3) Cycle
Stockpile Running Total
1.00 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80
1.00 1.80 2.60 3.40 4.20 5.00 5.80 6.60 7.40 8.20 8.20 9.00 9.80 10.60 11.40 12.20 13.00 13.80 14.60 15.40 16.20 16.20 17.00 17.80 18.60 19.40 20.20 21.00 21.80 22.60 23.40 24.20 24.20 25.00 25.80 26.60 27.40 28.20
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80
29.00 29.80 30.60 31.40 32.20 32.20 33.00 33.80 34.60 35.40 36.20 37.00 37.80 38.60 39.40 40.20 40.20 41.00 41.80 42.60 43.40 44.20 45.00 45.80 46.60 47.40 48.20 48.20 49.00 49.80 50.60 51.40 52.20 53.00 53.80 54.60 55.40 56.20 56.20 57.00 57.80 58.60 59.40 60.20 61.00 61.80 62.60 63.40 64.20 64.20 65.00 65.80 66.60 67.40
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 -
68.20 69.00 69.80 70.60 71.40 72.20 72.20 73.00 73.80 74.60 75.40 76.20 77.00 77.80 78.60 79.40 80.20 -
-
80.2 m3
-
PRODUCTIVITY CALCULATIONS Bulk Excavation Trial Excavation Area Parameter Segment Length Segment Width Depth of Cut Area of Excavation Maximum Volume
BACKHOE
(Excavation & Stockpiling)
Quantity 15.00 2.00 1.00 30.00 30.00
Unit m m m sm m3
Cap = 0.80 cu.m.
NORMAL SOIL Equipment Specifications Parameter Forward Speed Reverse Speed Bucket Capacity Fuel Consumption Productivity Rates Parameter Cut-Swing-Unload-Swing Area Covered / Position Volume / Position Excavation Duration / Position Number of Positions Total Excavation Duration
Backhoe Quantity
2.63 2.63 0.40 14.00
Quantity 35.00 4.00 4.00 0.10 8.00 0.78
Cap = 0.40 cu.m. Unit km/hr km/hr m3 li/hr
Unit secs m2 m3 hrs positions hrs
Excluding Travel
Time-Motion Table Activity
Maneuver Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing
Rate
Manuever & Wait 0.17 -
Time Required (hours) Cut-Swing Load-Swing 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing
-
0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing
-
0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 -
Total Productivity
HARD SOIL
-
Equipment Specifications Parameter Forward Speed Reverse Speed Bucket Capacity Fuel Consumption Productivity Rates Parameter Cut-Swing-Unload-Swing Area Covered / Position Volume / Position Excavation Duration / Position Number of Positions Total Excavation Duration
Backhoe Quantity
2.63 2.63 0.40 14.00
Quantity 60.00 4.00 4.00 0.17 8.00 1.33
Cap = 0.40 cu.m. Unit km/hr km/hr m3 li/hr
Unit secs m2 m3 hrs positions hrs
Excluding Travel
Time-Motion Table Activity
Maneuver Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing
Rate
Manuever & Wait 0.17 -
Time Required (hours) Cut-Swing Load-Swing 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing
-
0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 -
-
-
-
-
Total Productivity
ROCKY SOIL Equipment Specifications Parameter Forward Speed Reverse Speed Bucket Capacity Fuel Consumption Productivity Rates Parameter Cut-Swing-Unload-Swing Area Covered / Position Volume / Position Excavation Duration / Position Number of Positions Total Excavation Duration
Backhoe Quantity
2.63 2.63 0.40 14.00
Quantity 80.00 4.00 4.00 0.22 8.00 1.78
Cap = 0.40 cu.m. Unit km/hr km/hr m3 li/hr
Unit secs m2 m3 hrs positions hrs
Excluding Travel
Time-Motion Table Activity
Maneuver Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing
Rate
Manuever & Wait 0.17 -
Time Required (hours) Cut-Swing Load-Swing 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing
-
0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 -
-
-
-
-
Total Productivity
BACKHOE
Cap = 0.50 cu.m.
NORMAL SOIL Equipment Specifications Parameter Forward Speed Reverse Speed Bucket Capacity Fuel Consumption Productivity Rates Parameter Cut-Swing-Unload-Swing Area Covered / Position Volume / Position Excavation Duration / Position Number of Positions Total Excavation Duration
Backhoe Quantity
2.63 2.63 0.50 14.00
Quantity 35.00 4.00 4.00 0.08 8.00 0.62
Cap = 0.50 cu.m. Unit km/hr km/hr m3 li/hr
Unit secs m2 m3 hrs positions hrs
Excluding Travel
Time-Motion Table Activity
Maneuver Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing
Rate
Manuever & Wait 0.17 -
Time Required (hours) Cut-Swing Load-Swing 0.01 0.01 0.01 0.01 0.01 0.01 0.01
Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing
-
0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing
-
0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 -
-
-
-
-
Total Productivity
HARD SOIL Equipment Specifications Parameter Forward Speed Reverse Speed Bucket Capacity Fuel Consumption Productivity Rates Parameter Cut-Swing-Unload-Swing Area Covered / Position Volume / Position Excavation Duration / Position Number of Positions Total Excavation Duration
Backhoe Quantity
2.63 2.63 0.50 14.00
Quantity 60.00 4.00 4.00 0.13 8.00 1.07
Cap = 0.50 cu.m. Unit km/hr km/hr m3 li/hr
Unit secs m2 m3 hrs positions hrs
Excluding Travel
Time-Motion Table Activity
Maneuver Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing
Rate
Manuever & Wait 0.17 -
Time Required (hours) Cut-Swing Load-Swing 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position
-
0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 -
Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing
-
0.02 0.02 0.02 0.02 0.02 -
Total Productivity
ROCKY SOIL Equipment Specifications Parameter Forward Speed Reverse Speed Bucket Capacity Fuel Consumption
Backhoe Quantity
2.63 2.63 0.50 14.00
Cap = 0.50 cu.m. Unit km/hr km/hr m3 li/hr
-
Productivity Rates Parameter Cut-Swing-Unload-Swing Area Covered / Position Volume / Position Excavation Duration / Position Number of Positions Total Excavation Duration
Quantity 80.00 4.00 4.00 0.18 8.00 1.42
Unit secs m2 m3 hrs positions hrs
Excluding Travel
Time-Motion Table Activity
Maneuver Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing
Rate
Manuever & Wait 0.17 -
Time Required (hours) Cut-Swing Load-Swing 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Transfer Position Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing Cut-Swing-Unload-Swing
-
0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 -
-
-
Total Productivity
-
Case Description Case Description 15.00 Cut-Swing-Unload-Swing 25.00 Transfer Position 30.00 35.00 Maneuver
Time Required (hours) Transfer Position
Stockpile Volume Time Required (minutes)
Total
0.00 -
0.17 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.00 0.01 0.01 0.01 0.01
10.00 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.04 0.58 0.58 0.58 0.58
Position
Cycle
4.00 cu.m. Volume (m
Position Running Total
0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40
0.40 0.80 1.20 1.60 2.00 2.40 2.80 3.20 3.60 4.00 0.40 0.80 1.20 1.60
0.00 0.00 0.00 0.00 0.00 -
0.01 0.01 0.01 0.01 0.01 0.01 0.00 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.00 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.00 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.00 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.00 0.01 0.01 0.01
0.58 0.58 0.58 0.58 0.58 0.58 0.04 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.04 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.04 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.04 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.04 0.58 0.58 0.58
0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40
2.00 2.40 2.80 3.20 3.60 4.00 0.40 0.80 1.20 1.60 2.00 2.40 2.80 3.20 3.60 4.00 0.40 0.80 1.20 1.60 2.00 2.40 2.80 3.20 3.60 4.00 0.40 0.80 1.20 1.60 2.00 2.40 2.80 3.20 3.60 4.00 0.40 0.80 1.20 1.60 2.00 2.40 2.80 3.20 3.60 4.00 0.40 0.80 1.20
0.00 -
0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.00 0.01 0.01 0.01 0.01 0.01 -
0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.04 0.58 0.58 0.58 0.58 0.58 -
0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 -
1.60 2.00 2.40 2.80 3.20 3.60 4.00 0.40 0.80 1.20 1.60 2.00 -
-
0.90 33.30 m3/hr
-
-
21.71 30 m3
-
Time Required (hours) Transfer Position
Stockpile Volume Time Required (minutes)
Total
0.00 0.00 -
0.17 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.00 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.00 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
10.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.04 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.04 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
Position
Cycle
4.00 cu.m. Volume (m
Position Running Total
0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40
0.40 0.80 1.20 1.60 2.00 2.40 2.80 3.20 3.60 4.00 0.40 0.80 1.20 1.60 2.00 2.40 2.80 3.20 3.60 4.00 0.40 0.80 1.20 1.60 2.00 2.40 2.80 3.20 3.60
0.00 0.00 0.00 0.00 0.00 -
0.02 0.00 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.00 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.00 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.00 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.00 0.02 0.02 0.02 0.02 0.02 -
1.00 0.04 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.04 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.04 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.04 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.04 1.00 1.00 1.00 1.00 1.00 -
0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 -
4.00 0.40 0.80 1.20 1.60 2.00 2.40 2.80 3.20 3.60 4.00 0.40 0.80 1.20 1.60 2.00 2.40 2.80 3.20 3.60 4.00 0.40 0.80 1.20 1.60 2.00 2.40 2.80 3.20 3.60 4.00 0.40 0.80 1.20 1.60 2.00 2.40 2.80 3.20 3.60 4.00 0.40 0.80 1.20 1.60 2.00 -
-
-
-
-
-
-
1.42 21.10 m3/hr
-
-
30.04 30 m3
-
Time Required (hours) Transfer Position
Stockpile Volume Time Required (minutes)
Total
0.00 0.00 0.00 0.00 -
0.17 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.00 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.00 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.00 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.00 0.02 0.02 0.02
10.00 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 0.04 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 0.04 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 0.04 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 0.04 1.33 1.33 1.33
Position
Cycle
4.00 cu.m. Volume (m
Position Running Total
0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40
0.40 0.80 1.20 1.60 2.00 2.40 2.80 3.20 3.60 4.00 0.40 0.80 1.20 1.60 2.00 2.40 2.80 3.20 3.60 4.00 0.40 0.80 1.20 1.60 2.00 2.40 2.80 3.20 3.60 4.00 0.40 0.80 1.20 1.60 2.00 2.40 2.80 3.20 3.60 4.00 0.40 0.80 1.20
0.00 0.00 0.00 -
0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.00 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.00 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.00 0.02 0.02 0.02 0.02 0.02 -
1.33 1.33 1.33 1.33 1.33 1.33 1.33 0.04 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 0.04 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 0.04 1.33 1.33 1.33 1.33 1.33 -
0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 -
1.60 2.00 2.40 2.80 3.20 3.60 4.00 0.40 0.80 1.20 1.60 2.00 2.40 2.80 3.20 3.60 4.00 0.40 0.80 1.20 1.60 2.00 2.40 2.80 3.20 3.60 4.00 0.40 0.80 1.20 1.60 2.00 -
-
-
-
-
-
-
-
-
1.84
-
36.71
16.32 m3/hr
Time Required (hours) Transfer Position -
30 m3
Stockpile Volume Time Required (minutes)
Total
0.17 0.01 0.01 0.01 0.01 0.01 0.01 0.01
-
10.00 0.58 0.58 0.58 0.58 0.58 0.58 0.58
Position
Cycle
4.00 cu.m. Volume (m
Position Running Total
0.50 0.40 0.40 0.40 0.40 0.40 0.40
0.50 0.90 1.30 1.70 2.10 2.50 2.90
0.00 0.00 0.00 0.00 0.00 -
0.01 0.01 0.01 0.00 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.00 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.00 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.00 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.00 0.01 0.01 0.01 0.01 0.01 0.01
0.58 0.58 0.58 0.04 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.04 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.04 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.04 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.04 0.58 0.58 0.58 0.58 0.58 0.58
0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40
3.30 3.70 4.10 0.40 0.80 1.20 1.60 2.00 2.40 2.80 3.20 3.60 4.00 0.40 0.80 1.20 1.60 2.00 2.40 2.80 3.20 3.60 4.00 0.40 0.80 1.20 1.60 2.00 2.40 2.80 3.20 3.60 4.00 0.40 0.80 1.20 1.60 2.00 2.40 2.80 3.20 3.60 4.00 0.40 0.80 1.20 1.60 2.00 2.40
0.00 0.00 -
0.01 0.01 0.01 0.01 0.00 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.00 0.01 0.01 0.01 0.01 0.01 -
0.58 0.58 0.58 0.58 0.04 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.04 0.58 0.58 0.58 0.58 0.58 -
0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 -
2.80 3.20 3.60 4.00 0.40 0.80 1.20 1.60 2.00 2.40 2.80 3.20 3.60 4.00 0.40 0.80 1.20 1.60 2.00 -
-
-
-
-
-
-
-
-
0.90
-
21.71
33.41 m3/hr
Time Required (hours) Transfer Position 0.00 0.00 -
30.1 m3
Stockpile Volume Time Required (minutes)
Total
0.17 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.00 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.00 0.02
-
10.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.04 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.04 1.00
Position
Cycle
4.00 cu.m. Volume (m
Position Running Total
0.50 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40
0.50 0.90 1.30 1.70 2.10 2.50 2.90 3.30 3.70 4.10 0.40 0.80 1.20 1.60 2.00 2.40 2.80 3.20 3.60 4.00 0.40
0.00 0.00 0.00 0.00 0.00
0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.00 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.00 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.00 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.00 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.00
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.04 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.04 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.04 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.04 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.04
0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 -
0.80 1.20 1.60 2.00 2.40 2.80 3.20 3.60 4.00 0.40 0.80 1.20 1.60 2.00 2.40 2.80 3.20 3.60 4.00 0.40 0.80 1.20 1.60 2.00 2.40 2.80 3.20 3.60 4.00 0.40 0.80 1.20 1.60 2.00 2.40 2.80 3.20 3.60 4.00 0.40 0.80 1.20 1.60 2.00 2.40 2.80 3.20 3.60 4.00 -
-
0.02 0.02 0.02 0.02 0.02 -
1.00 1.00 1.00 1.00 1.00 -
0.40 0.40 0.40 0.40 0.40 -
0.40 0.80 1.20 1.60 2.00 -
-
1.42 21.17 m3/hr
-
-
30.04 30.1 m3
-
Time Required (hours) Transfer Position
Stockpile Volume Time Required (minutes)
Total
0.00 0.00 0.00 -
0.17 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.00 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.00 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.00 0.02 0.02 0.02 0.02 0.02 0.02
10.00 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 0.04 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 0.04 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 0.04 1.33 1.33 1.33 1.33 1.33 1.33
Position
Cycle
4.00 cu.m. Volume (m
Position Running Total
0.50 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40
0.50 0.90 1.30 1.70 2.10 2.50 2.90 3.30 3.70 4.10 0.40 0.80 1.20 1.60 2.00 2.40 2.80 3.20 3.60 4.00 0.40 0.80 1.20 1.60 2.00 2.40 2.80 3.20 3.60 4.00 0.40 0.80 1.20 1.60 2.00 2.40
0.00 0.00 0.00 0.00 -
0.02 0.02 0.02 0.02 0.00 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.00 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.00 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.00 0.02 0.02 0.02 0.02 0.02 -
1.33 1.33 1.33 1.33 0.04 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 0.04 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 0.04 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 0.04 1.33 1.33 1.33 1.33 1.33 -
0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 -
2.80 3.20 3.60 4.00 0.40 0.80 1.20 1.60 2.00 2.40 2.80 3.20 3.60 4.00 0.40 0.80 1.20 1.60 2.00 2.40 2.80 3.20 3.60 4.00 0.40 0.80 1.20 1.60 2.00 2.40 2.80 3.20 3.60 4.00 0.40 0.80 1.20 1.60 2.00 -
-
-
-
-
-
-
1.84 16.37 m3/hr
-
-
36.71 30.1 m3
-
Stockpile
30.00 cu.m.
Volume (m3) Cycle
Stockpile Running Total
0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40
0.40 0.80 1.20 1.60 2.00 2.40 2.80 3.20 3.60 4.00 4.00 4.40 4.80 5.20 5.60
0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40
6.00 6.40 6.80 7.20 7.60 8.00 8.00 8.40 8.80 9.20 9.60 10.00 10.40 10.80 11.20 11.60 12.00 12.00 12.40 12.80 13.20 13.60 14.00 14.40 14.80 15.20 15.60 16.00 16.00 16.40 16.80 17.20 17.60 18.00 18.40 18.80 19.20 19.60 20.00 20.00 20.40 20.80 21.20 21.60 22.00 22.40 22.80 23.20 23.60 24.00 24.00 24.40 24.80 25.20
0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 -
25.60 26.00 26.40 26.80 27.20 27.60 28.00 28.00 28.40 28.80 29.20 29.60 30.00 -
-
30 m3
-
Stockpile
30.00 cu.m.
Volume (m ) 3
Cycle
Stockpile Running Total
0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40
0.40 0.80 1.20 1.60 2.00 2.40 2.80 3.20 3.60 4.00 4.00 4.40 4.80 5.20 5.60 6.00 6.40 6.80 7.20 7.60 8.00 8.00 8.40 8.80 9.20 9.60 10.00 10.40 10.80 11.20 11.60
0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 -
12.00 12.00 12.40 12.80 13.20 13.60 14.00 14.40 14.80 15.20 15.60 16.00 16.00 16.40 16.80 17.20 17.60 18.00 18.40 18.80 19.20 19.60 20.00 20.00 20.40 20.80 21.20 21.60 22.00 22.40 22.80 23.20 23.60 24.00 24.00 24.40 24.80 25.20 25.60 26.00 26.40 26.80 27.20 27.60 28.00 28.00 28.40 28.80 29.20 29.60 30.00 -
-
-
-
30 m3
-
Stockpile
30.00 cu.m.
Volume (m ) 3
Cycle
Stockpile Running Total
0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40
0.40 0.80 1.20 1.60 2.00 2.40 2.80 3.20 3.60 4.00 4.00 4.40 4.80 5.20 5.60 6.00 6.40 6.80 7.20 7.60 8.00 8.00 8.40 8.80 9.20 9.60 10.00 10.40 10.80 11.20 11.60 12.00 12.00 12.40 12.80 13.20 13.60 14.00 14.40 14.80 15.20 15.60 16.00 16.00 16.40 16.80 17.20
0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 -
17.60 18.00 18.40 18.80 19.20 19.60 20.00 20.00 20.40 20.80 21.20 21.60 22.00 22.40 22.80 23.20 23.60 24.00 24.00 24.40 24.80 25.20 25.60 26.00 26.40 26.80 27.20 27.60 28.00 28.00 28.40 28.80 29.20 29.60 30.00 -
-
-
-
-
30 m3
Stockpile
30.00 cu.m.
Volume (m ) 3
Cycle
Stockpile Running Total
0.50 0.40 0.40 0.40 0.40 0.40 0.40
0.50 0.90 1.30 1.70 2.10 2.50 2.90
0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40
3.30 3.70 4.10 4.10 4.50 4.90 5.30 5.70 6.10 6.50 6.90 7.30 7.70 8.10 8.10 8.50 8.90 9.30 9.70 10.10 10.50 10.90 11.30 11.70 12.10 12.10 12.50 12.90 13.30 13.70 14.10 14.50 14.90 15.30 15.70 16.10 16.10 16.50 16.90 17.30 17.70 18.10 18.50 18.90 19.30 19.70 20.10 20.10 20.50 20.90 21.30 21.70 22.10 22.50
0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 -
22.90 23.30 23.70 24.10 24.10 24.50 24.90 25.30 25.70 26.10 26.50 26.90 27.30 27.70 28.10 28.10 28.50 28.90 29.30 29.70 30.10 -
-
-
-
-
30.1 m3
Stockpile
30.00 cu.m.
Volume (m3) Cycle
Stockpile Running Total
0.50 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40
0.50 0.90 1.30 1.70 2.10 2.50 2.90 3.30 3.70 4.10 4.10 4.50 4.90 5.30 5.70 6.10 6.50 6.90 7.30 7.70 8.10 8.10 8.50
0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 -
8.90 9.30 9.70 10.10 10.50 10.90 11.30 11.70 12.10 12.10 12.50 12.90 13.30 13.70 14.10 14.50 14.90 15.30 15.70 16.10 16.10 16.50 16.90 17.30 17.70 18.10 18.50 18.90 19.30 19.70 20.10 20.10 20.50 20.90 21.30 21.70 22.10 22.50 22.90 23.30 23.70 24.10 24.10 24.50 24.90 25.30 25.70 26.10 26.50 26.90 27.30 27.70 28.10 28.10
0.40 0.40 0.40 0.40 0.40 -
28.50 28.90 29.30 29.70 30.10 -
-
30.1 m3
-
Stockpile
30.00 cu.m.
Volume (m ) 3
Cycle
Stockpile Running Total
0.50 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40
0.50 0.90 1.30 1.70 2.10 2.50 2.90 3.30 3.70 4.10 4.10 4.50 4.90 5.30 5.70 6.10 6.50 6.90 7.30 7.70 8.10 8.10 8.50 8.90 9.30 9.70 10.10 10.50 10.90 11.30 11.70 12.10 12.10 12.50 12.90 13.30 13.70 14.10 14.50
0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 -
14.90 15.30 15.70 16.10 16.10 16.50 16.90 17.30 17.70 18.10 18.50 18.90 19.30 19.70 20.10 20.10 20.50 20.90 21.30 21.70 22.10 22.50 22.90 23.30 23.70 24.10 24.10 24.50 24.90 25.30 25.70 26.10 26.50 26.90 27.30 27.70 28.10 28.10 28.50 28.90 29.30 29.70 30.10 -
-
-
-
30.1 m3
-
PRODUCTIVITY CALCULATIONS Trench Backfilling - Backhoe Trial Strip
Parameter Segment Length Segment Width Thickness Area of Embankment Volume Equipment Specifications Parameter Forward Speed Reverse Speed Bucket Capacity Swing Bucket Cycle Lower - Load Bucket Cycle Swing / Unload Bucket Cycle Fuel Consumption
Quantity 50.00 5.00 0.25 250.00 62.50 Backhoe Excavation Quantity
2.63 2.63 0.40 8.00 13.00 8.00 16.00
Time-Motion Table Activity
Maneuver & Waiting Time Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty
Rate
Unit m m m sm m3 Cap = 0.40 cu.m. Vol = 5.00 cu.m. Unit km/hr km/hr m3 secs secs secs li/hr
Time Required hrs
0.167 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 -
0.73 0.73
Excavation Volume Time Required minutes
10.00 0.48 0.48 0.48 0.48 0.48 0.48 0.48 0.48 0.48 0.48 0.48 0.48 0.48 -
Total
0.27
Productivity
18.42 m3/hr
Equipment Specifications Parameter Forward Speed Reverse Speed Bucket Capacity Swing Bucket Cycle Lower - Load Bucket Cycle Swing / Unload Bucket Cycle Fuel Consumption
Backhoe Quantity
2.63 2.63 0.50 10.00 16.00 10.00 16.00
Time-Motion Table Activity
Maneuver & Waiting Time Dig-Swing-Unload-Swing Dig-Swing-Unload-Swing Dig-Swing-Unload-Swing Dig-Swing-Unload-Swing Dig-Swing-Unload-Swing Dig-Swing-Unload-Swing Dig-Swing-Unload-Swing Dig-Swing-Unload-Swing Dig-Swing-Unload-Swing Dig-Swing-Unload-Swing
Total Productivity
16.28
Rate
Cap = 0.50 cu.m. Unit km/hr km/hr m3 secs secs secs li/hr
Time Required hrs
0.73 0.73
Excavation Volume Time Required minutes
0.167 0.010 0.010 0.010 0.010 0.010 0.010 0.010 0.010 0.010 0.010 -
10.00 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 -
0.27
16.00
18.75 m3/hr
m/s m/s
Excavation Volume = Volume (m3)
0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 -
5.00 cu.m. Running Volume (m3)
0.40 0.80 1.20 1.60 2.00 2.40 2.80 3.20 3.60 4.00 4.40 4.80 5.20 5.20 5.20 5.20 5.20 5.20 5.20 5.20 5.20
m/s m/s
Excavation Volume = Volume (m3)
0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 -
5.00 cu.m. Running Volume (m3)
0.50 1.00 1.50 2.00 2.50 3.00 3.50 4.00 4.50 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00
PRODUCTIVITY CALCULATIONS Foundation Backfilling - Backhoe Trial Strip
Parameter Segment Length Segment Width Thickness Area of Embankment Volume Equipment Specifications Parameter Forward Speed Reverse Speed Bucket Capacity Swing Bucket Cycle Lower - Load Bucket Cycle Swing / Unload Bucket Cycle Fuel Consumption
Quantity 50.00 5.00 0.25 250.00 62.50 Backhoe Excavation Quantity
2.63 2.63 0.80 8.00 13.00 8.00 16.00
Time-Motion Table Activity
Maneuver & Waiting Time Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty
Rate
Unit m m m sm m3 Cap = 0.80 cu.m. Vol = 5.00 cu.m. Unit km/hr km/hr m3 secs secs secs li/hr
Time Required hrs
0.167 0.008 0.008 0.008 0.008 0.008 0.008 0.008 -
0.73 0.73
Excavation Volume Time Required minutes
10.00 0.48 0.48 0.48 0.48 0.48 0.48 0.48 -
Total
0.22
Productivity
22.42 m3/hr
Equipment Specifications Parameter Forward Speed Reverse Speed Bucket Capacity Swing Bucket Cycle Lower - Load Bucket Cycle Swing / Unload Bucket Cycle Fuel Consumption
Backhoe Quantity
2.63 2.63 1.00 10.00 16.00 10.00 16.00
Time-Motion Table Activity
Maneuver & Waiting Time Dig-Swing-Unload-Swing Dig-Swing-Unload-Swing Dig-Swing-Unload-Swing Dig-Swing-Unload-Swing Dig-Swing-Unload-Swing
Total Productivity
13.38
Rate
Cap = 1.00 cu.m. Unit km/hr km/hr m3 secs secs secs li/hr
Time Required hrs
0.73 0.73
Excavation Volume Time Required minutes
0.167 0.010 0.010 0.010 0.010 0.010 -
10.00 0.60 0.60 0.60 0.60 0.60 -
0.22
13.00
23.08 m3/hr
m/s m/s
Excavation Volume = Volume (m3)
0.80 0.80 0.80 0.80 0.80 0.80 0.80 -
5.00 cu.m. Running Volume (m3)
0.80 1.60 2.40 3.20 4.00 4.80 5.60 5.60 5.60 5.60 5.60 5.60 5.60 5.60 5.60 5.60 5.60 5.60 5.60 5.60 5.60
m/s m/s
Excavation Volume = Volume (m3)
1.00 1.00 1.00 1.00 1.00 -
5.00 cu.m. Running Volume (m3)
1.00 2.00 3.00 4.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00
PRODUCTIVITY CALCULATIONS Loading from Stockpile - Loader Trial Strip
Parameter Segment Length Segment Width Thickness Area of Embankment Volume Equipment Specifications Parameter Forward Speed Reverse Speed Bucket Capacity Dig - Raise Cycle Reverse-Forward Cycle Dump - Lower Empty Cycle Fuel Consumption
Quantity 50.00 5.00 0.25 250.00 62.50 Loader 100HP Dump Truck Quantity 6.40 7.70 1.50 16.40 10.30 5.50 15.00
Cap = 1.50 cu.m. ### Unit km/hr km/hr m3 secs secs secs li/hr
Rate
Time Required hrs
Time-Motion Table Activity
Maneuver & Waiting Time Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty
Unit m m m sm m3
0.167 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 -
1.78 2.14
Dump Truck Capacity Time Required minutes
10.00 0.54 0.54 0.54 0.54 0.54 0.54 0.54 0.54 0.54 0.54 -
Total
0.26
Productivity
58.57 m3/hr
Equipment Specifications Parameter Forward Speed Reverse Speed Bucket Capacity Dig - Raise Cycle Reverse-Forward Cycle Dump - Lower Empty Cycle Fuel Consumption
Loader 117HP Quantity 7.10 7.80 2.40 16.60 9.69 5.20 19.00
Time-Motion Table Activity
Maneuver & Waiting Time Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty
Total Productivity
15.37
Rate
Cap = 2.40 cu.m. Unit km/hr km/hr m3 secs secs secs li/hr
Time Required hrs
1.97 2.17
Dump Truck Capacity Time Required minutes
0.167 0.009 0.009 0.009 0.009 0.009 0.009 0.009 -
10.00 0.52 0.52 0.52 0.52 0.52 0.52 0.52 -
0.23
13.67
65.82 m3/hr
m/s m/s
Dump Truck Capacity = Volume (m3)
1.50 1.50 1.50 1.50 1.50 1.50 1.50 1.50 1.50 1.50 -
15.00 cu.m. Running Volume (m3)
1.50 3.00 4.50 6.00 7.50 9.00 10.50 12.00 13.50 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00
m/s m/s
Dump Truck Capacity = Volume (m3)
2.40 2.40 2.40 2.40 2.40 2.40 2.40 -
15.00 cu.m. Running Volume (m3)
2.40 4.80 7.20 9.60 12.00 14.40 16.80 16.80 16.80 16.80 16.80 16.80 16.80 16.80 16.80 16.80 16.80 16.80 16.80 16.80 16.80
PRODUCTIVITY CALCULATIONS Loading from Stockpile - Backhoe Trial Strip
Parameter Segment Length Segment Width Thickness Area of Embankment Volume Equipment Specifications Parameter Forward Speed Reverse Speed Bucket Capacity Swing Bucket Cycle Lower - Load Bucket Cycle Swing / Unload Bucket Cycle Fuel Consumption
Quantity 50.00 5.00 0.25 250.00 62.50 Backhoe Dump Truck Quantity 2.63 2.63 0.80 10.00 15.00 10.00 16.00
Cap = 0.80 cu.m. ### Unit km/hr km/hr m3 secs secs secs li/hr
Rate
Time Required hrs
Time-Motion Table Activity
Maneuver & Waiting Time Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty
Unit m m m sm m3
0.167 0.010 0.010 0.010 0.010 0.010 0.010 0.010 0.010 0.010 0.010 0.010 0.010 0.010 0.010 0.010 0.010 0.010 0.010 0.010 -
0.73 0.73
Dump Truck Capacity Time Required minutes
10.00 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 -
Total
0.35
Productivity
42.69 m3/hr
Equipment Specifications Parameter Forward Speed Reverse Speed Bucket Capacity Swing Bucket Cycle Lower - Load Bucket Cycle Swing / Unload Bucket Cycle Fuel Consumption
Backhoe Quantity
2.63 2.63 1.00 12.00 18.00 12.00 16.00
Time-Motion Table Activity
Maneuver & Waiting Time Dig-Swing-Unload-Swing Dig-Swing-Unload-Swing Dig-Swing-Unload-Swing Dig-Swing-Unload-Swing Dig-Swing-Unload-Swing Dig-Swing-Unload-Swing Dig-Swing-Unload-Swing Dig-Swing-Unload-Swing Dig-Swing-Unload-Swing Dig-Swing-Unload-Swing Dig-Swing-Unload-Swing Dig-Swing-Unload-Swing Dig-Swing-Unload-Swing Dig-Swing-Unload-Swing Dig-Swing-Unload-Swing
Total Productivity
21.08
Rate
Cap = 1.00 cu.m. Unit km/hr km/hr m3 secs secs secs li/hr
Time Required hrs
0.73 0.73
Dump Truck Capacity Time Required minutes
0.167 0.012 0.012 0.012 0.012 0.012 0.012 0.012 0.012 0.012 0.012 0.012 0.012 0.012 0.012 0.012 -
10.00 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70 -
0.34
20.50
43.90 m3/hr
m/s m/s
Dump Truck Capacity = Volume (m3)
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 -
15.00 cu.m. Running Volume (m3)
0.80 1.60 2.40 3.20 4.00 4.80 5.60 6.40 7.20 8.00 8.80 9.60 10.40 11.20 12.00 12.80 13.60 14.40 15.20 15.20 15.20
m/s m/s
Dump Truck Capacity = Volume (m3)
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 -
15.00 cu.m. Running Volume (m3)
1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 12.00 13.00 14.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00
PRODUCTIVITY CALCULATIONS Soil Hauling by Dump Truck
Equipment Specifications Parameter Loaded Speed Empty Speed Load Capacity Fuel Consumption
Dump Truck Quantity 40.00 60.00 15.00 15.00
Unit km/hr km/hr m3 li/hr
###
LOADING BY BACKHOE AHD = Time-Motion Table Activity
5.000 km(s) Time Required hrs
Rate
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Dump Travel (Empty)
40.00
60.00
Total Productivity
AHD= 5.000 km(s)
AHD = Time-Motion Table Activity
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Dump Travel (Empty)
0.08 0.35 0.13 0.08 0.03 0.08
5.00 21.08 7.50 5.00 2.00 5.00
0.76
45.58
19.74 m3/hr
7.000 km(s) Time Required hrs
Rate
40.00
60.00
Total Productivity
Time Required minutes
AHD= 7.000 km(s)
Time Required minutes
0.08 0.35 0.18 0.08 0.03 0.12
5.00 21.08 10.50 5.00 2.00 7.00
0.84
50.58
17.79 m3/hr
AHD = Time-Motion Table Activity
10.000 km(s) Time Required hrs
Rate
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Dump Travel (Empty)
40.00
60.00
Total Productivity
AHD= 10.000 km(s)
AHD = Time-Motion Table Activity
40.00
60.00
AHD= 15.000 km(s)
Activity
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Dump Travel (Empty)
5.00 21.08 15.00 5.00 2.00 10.00
0.97
58.08
15.49 m3/hr
Time Required hrs
Rate
Total
AHD = Time-Motion Table
0.08 0.35 0.25 0.08 0.03 0.17
15.000 km(s)
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Dump Travel (Empty)
Productivity
Time Required minutes
Time Required minutes
0.08 0.35 0.38 0.08 0.03 0.25
5.00 21.08 22.50 5.00 2.00 15.00
1.18
70.58
12.75 m3/hr
20.000 km(s) Time Required hrs
Rate
40.00
60.00
0.08 0.35 0.50 0.08 0.03 0.33
Time Required minutes
5.00 21.08 30.00 5.00 2.00 20.00
Total Productivity
1.38 AHD= 20.000 km(s)
AHD = Time-Motion Table Activity
Time Required hrs
Rate
40.00
60.00
Total AHD= 25.000 km(s)
AHD = Time-Motion Table Activity
Time Required minutes
0.08 0.35 0.63 0.08 0.03 0.42
5.00 21.08 37.50 5.00 2.00 25.00
1.59
95.58
9.42 m3/hr
30.000 km(s) Time Required hrs
Rate
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Dump Travel (Empty)
40.00
60.00
Total Productivity
10.83 m3/hr
25.000 km(s)
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Dump Travel (Empty)
Productivity
83.08
AHD= 30.000 km(s)
Time Required minutes
0.08 0.35 0.75 0.08 0.03 0.50
5.00 21.08 45.00 5.00 2.00 30.00
1.80
108.08
8.33 m3/hr
LOADING BY WHEEL LOADER AHD = Time-Motion Table Activity
Maneuver & Wait
5.000 km(s)
Rate
Time Required hrs
0.08
Time Required minutes
5.00
Wait While Loading Travel (Loaded) Maneuver & Wait Dump Travel (Empty)
40.00
60.00
Total Productivity
AHD= 5.000 km(s)
AHD = Time-Motion Table Activity
40.00
60.00
AHD= 7.000 km(s)
Activity
Rate
40.00
60.00
AHD= 10.000 km(s)
Activity
22.58 m3/hr
Time Required minutes
0.08 0.26 0.18 0.08 0.03 0.12
5.00 15.37 10.50 5.00 2.00 7.00
0.75
44.87
20.06 m3/hr
Time Required hrs
Total
AHD = Time-Motion Table
39.87
10.000 km(s)
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Dump Travel (Empty)
Productivity
0.66
Time Required hrs
Rate
Total
AHD = Time-Motion Table
15.37 7.50 5.00 2.00 5.00
7.000 km(s)
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Dump Travel (Empty)
Productivity
0.26 0.13 0.08 0.03 0.08
Time Required minutes
0.08 0.26 0.35 0.08 0.03 0.17
5.00 15.37 21.08 5.00 2.00 10.00
0.97
58.45
15.40 m3/hr
15.000 km(s)
Rate
Time Required
Time Required
Activity
Rate
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Dump Travel (Empty)
hrs
40.00
60.00
Total Productivity
AHD= 15.000 km(s)
AHD = Time-Motion Table Activity
Rate
40.00
60.00
AHD= 20.000 km(s)
Activity
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Dump Travel (Empty)
1.08
64.87
13.87 m3/hr
Time Required minutes
0.08 0.26 0.50 0.08 0.03 0.33
5.00 15.37 30.00 5.00 2.00 20.00
1.29
77.37
11.63 m3/hr
25.000 km(s) Time Required hrs
Rate
40.00
60.00
Total Productivity
5.00 15.37 22.50 5.00 2.00 15.00
Time Required hrs
Total
AHD = Time-Motion Table
0.08 0.26 0.38 0.08 0.03 0.25
20.000 km(s)
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Dump Travel (Empty)
Productivity
minutes
AHD= 25.000 km(s)
Time Required minutes
0.08 0.26 0.63 0.08 0.03 0.42
5.00 15.37 37.50 5.00 2.00 25.00
1.50
89.87
10.01 m3/hr
AHD = Time-Motion Table
30.000 km(s)
Activity
Time Required hrs
Rate
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Dump Travel (Empty)
40.00
60.00
Total Productivity
AHD= 30.000 km(s)
Time Required minutes
0.08 0.26 0.75 0.08 0.03 0.50
5.00 15.37 45.00 5.00 2.00 30.00
1.71
102.37
8.79 m3/hr
FREE HAUL - LOADING BY BACKHOE AHD = Time-Motion Table Activity
1.000 km(s) Time Required hrs
Rate
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Dump Travel (Empty)
40.00
60.00
Total Productivity
AHD= 1.000 km(s)
Time Required minutes
0.08 0.35 0.03 0.08 0.03 0.02
5.00 21.08 1.50 5.00 2.00 1.00
0.59
35.58
25.29 m3/hr
FREE HAUL - LOADING BY WHEEL LOADER AHD = Time-Motion Table Activity
Maneuver & Wait Wait While Loading
1.000 km(s)
Rate
Time Required hrs
0.08 0.26
Time Required minutes
5.00 15.37
Travel (Loaded) Maneuver & Wait Dump Travel (Empty)
40.00
60.00
Total Productivity
AHD= 1.000 km(s)
0.03 0.08 0.03 0.02
1.50 5.00 2.00 1.00
0.50
29.87
30.13 m3/hr
PRODUCTIVITY CALCULATIONS Quarrying Related Productivities Ground Cutting (Excavation & Stockpiling)
Bulldozer D7 Backhoe Backhoe Soil Hauling by Dump Truck Dump Truck Speed Loaded 40.00 AHD= Speed Empty 60.00 AHD= Time to Dump 0.03 AHD= AHD= AHD= AHD= AHD= Trial Strip Parameter Quantity Unit Length 12.50 m Width 10.00 m Cut Depth 0.50 m Area 125.00 sm Volume 62.50 m3 AHD 10.00 km(s)
88.24 m3/hr 55.86 m3/hr 56.01 m3/hr
Cap = 0.80 cu.m. Cap = 1.00 cu.m. Cap = 15.00 cu.m.
19.74 17.79 15.49 12.75 10.83 9.42 8.33
5.000 km(s) 7.000 km(s) 10.000 km(s) 15.000 km(s) 20.000 km(s) 25.000 km(s) 30.000 km(s)
Bulldozer Productivity : Work Item Clearing/Pushing Clearing/Pushing Clearing/Pushing Clearing/Pushing
Backhoe 88.24 m3/hr
Volume
Time Needed
Time Elapsed
0.36 0.18 0.18 0.18
0.36 0.54 0.71 0.89
31.500 cu m 15.750 cu m 15.750 cu m 15.750 cu m
Productivity : Work Item Wait Dig/Swing/Load Dig/Swing/Load Dig/Swing/Load Dig/Swing/Load Wait Dig/Swing/Load
78.750 cu m Dumptruck 2 Productivity : Work Item Wait Wait Wait (Loading) Haul & Dump
15.000 cu m
Time Needed
Time Elapsed
0.36 0.28 0.28 0.45
0.36 0.64 0.92 1.37 1.37
Wait Wait Wait Wait (Loading) Haul & Dump
2.02
Quarry Productivity
Total Time Elapsed Legend:
Dumptruck 1 56.01 m3/hr
Volume
Time Needed
15.750 cu m
0.36 0.28 0.28 0.28 0.28 (0.39) 0.28
78.750 cu m
44.67
15.750 cu m 15.750 cu m 15.750 cu m 15.750 cu m
Time Elapsed 0.36 0.64 0.92 1.20 1.48 1.09 1.76
Productivity : Work Item Wait Wait (Loading) Haul & Dump Wait Wait (Loading) Haul & Dump Return
AHD= 10.00 km(s)
Volume
15.49 m3/hr
15.000 cu m
Activities OVERLAPPED by LATER Activities of other Equipment. Second Load Carry Over to SUMMARY SHEET
Time Elapsed
0.36 0.28 0.45
0.36 0.64 1.09 1.09 1.48 1.76 1.97 2.02
0.39 0.28 0.21 0.05
15.000 cu m
Dumptruck 4
Time Needed
Time Elapsed
Productivity : Work Item
0.36 0.28 0.28 0.28 0.45
0.36 0.64 0.92 1.20 1.65 1.65
Wait Wait Wait Wait Wait (Loading) Haul & Dump
AHD= 10.00 km(s)
Volume
15.49 m3/hr
Time Needed
15.000 cu m
Dumptruck 3 Productivity : Work Item
AHD= 10.00 km(s)
Volume
m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr
15.49 m3/hr
38.93 m3/hr
AHD= 10.00 km(s)
Volume
15.000 cu m
Time Elapsed
0.36 0.28 0.28 0.28 0.28 0.45
0.36 0.64 0.92 1.20 1.48 1.93 1.93
Quarry Productivity Bull Dozer Productivity Backhoe Productivity Dump Truck
15.49 m3/hr
Time Needed
311.41 m3/day 88.24 m3/hr 38.93 m3/hr 38.93 m3/hr
PRODUCTIVITY CALCULATIONS Pavement Breaking Pavement Breaking
Asphalt
Trial Strip
Parameter Segment Length Segment Width Pavement Thickness Area of Embankment Volume Equipment Specifications Parameter Forward Speed Reverse Speed Bucket Capacity Fuel Consumption
Thickness = 50.00 mm
Quantity 50.00 3.00 0.05 150.00 7.50
Unit m m m sm m3
Backhoe w/ Breaker Quantity 2.63 2.63 0.80 16.00
Unit km/hr km/hr m3 li/hr
Productivity Rates - Breaking Breaker Penetration Rate Duration per Breaking Stroke Swing-Lower/Raise-Swing Cycle Area Covered / Penetration Direct Area Breaking Rate Area Covered / Position Duration per Position Number of Positions Total Duration (Breaking)
6.00 21.60 0.002 35.00 0.80 345.60 18.75 0.06 8.00 0.51
mm/sec m/hr hrs secs m2 m2/hr m2 hrs positions hrs
Excluding Travel
0.28 35.00 28.80 18.75 0.94 0.03 8.00 0.26
m3 secs m3/hr m2 m3 hrs positions hrs
Excluding Travel
Productivity Rates - Scraping & Loading Volume / Digging Stroke Swing-Scrape-Swing-Load Cycle Scraping - Loading Rate Area Covered / Position Volume Covered / Position Duration per Position Number of Positions Total Duration (Scraping & Loading) Time-Motion Table Activity
Breaking
Rate
Time Required hrs
Time Required minutes
Fix Breaker, Maneuver, Wait Moving Forward, Positioning Breaking Fix Bucket, Maneuver, Wait
1.25 0.82 0.51 1.25
75.00 49.14 30.71 75.00
Scraping & Loading Debris Manuever, Wait Moving Forward, Positioning Scraping & Loading Debris Manuever, Wait
0.75 0.82 0.26 0.75
45.00 49.14 15.63 45.00
6.41
384.62
Total Productivity
1.17 m3/hr
Productivity
23.40 m2/hr
Pavement Breaking
Asphalt
Trial Strip
Parameter Segment Length Width Pavement Thickness Area of Embankment Volume Equipment Specifications Parameter Forward Speed Reverse Speed Bucket Capacity Fuel Consumption
Thickness = 75.00 mm
Quantity 50.00 3.00 0.08 150.00 11.25
Unit m m m sm m3
Backhoe w/ Breaker Quantity 2.63 2.63 0.80 16.00
Unit km/hr km/hr m3 li/hr
Productivity Rates - Breaking Breaker Penetration Rate Duration per Breaking Stroke Swing-Lower/Raise-Swing Cycle Area Covered / Penetration Direct Area Breaking Rate Area Covered / Position Duration per Position Number of Positions Total Duration (Breaking) Productivity Rates - Scraping & Loading Volume / Digging Stroke
6.00 21.60 0.003 35.00 0.80 230.40 18.75 0.09 8.00 0.73
0.28
mm/sec m/hr hrs secs m2 m2/hr m2 hrs positions hrs
m3
Excluding Travel
Swing-Scrape-Swing-Load Cycle Scraping - Loading Rate Area Covered / Position Volume Covered / Position Duration per Position Number of Positions Total Duration (Scraping & Loading)
35.00 28.80 18.75 1.41 0.05 8.00 0.39
Time-Motion Table Activity
secs m3/hr m2 m3 hrs positions hrs
Time Required hrs
Rate
Excluding Travel
Time Required minutes
Breaking Change Attach., Maneuver, Wait Moving Forward, Positioning Breaking Change Attach., Maneuver, Wait
1.25 0.82 0.73 1.25
75.00 49.14 43.73 75.00
Scraping & Loading Debris Manuever, Wait Moving Forward, Positioning
0.75 0.82
45.00 49.14
6.76
405.45
Total Productivity
1.66 m3/hr
Productivity
22.20 m2/hr
Pavement Breaking Trial Strip
Parameter Segment Length Width Pavement Thickness Area of Embankment Volume Equipment Specifications Parameter Forward Speed Reverse Speed Bucket Capacity Fuel Consumption Productivity Rates - Breaking Breaker Penetration Rate
Concrete
Thickness = 150.00 mm
Quantity 50.00 3.00 0.15 150.00 22.50
Unit m m m sm m3
Backhoe w/ Breaker Quantity 2.63 2.63 0.80 16.00
Unit km/hr km/hr m3 li/hr
3.50 12.60
mm/sec m/hr
Duration per Breaking Stroke Swing-Lower/Raise-Swing Cycle Area Covered / Penetration Direct Area Breaking Rate Area Covered / Position Duration per Position Number of Positions Total Duration (Breaking)
0.012 35.00 0.80 67.20 18.75 0.29 8.00 2.31
hrs secs m2 m2/hr m2 hrs positions hrs
Excluding Travel
Productivity Rates - Scraping & Loading Volume / Digging Stroke Swing-Scrape-Swing-Load Cycle Scraping - Loading Rate Area Covered / Position Volume Covered / Position Duration per Position Number of Positions Total Duration (Scraping & Loading)
0.28 35.00 28.80 18.75 2.81 0.10 8.00 0.78
m3 secs m3/hr m2 m3 hrs positions hrs
Excluding Travel
Time-Motion Table Activity
Rate
Time Required hrs
Time Required minutes
Breaking Fix Breaker, Maneuver, Wait Moving Forward, Positioning Breaking Fix Bucket, Maneuver, Wait
1.25 0.82 2.31 1.25
75.00 49.14 138.60 75.00
Scraping & Loading Debris Manuever, Wait Moving Forward, Positioning Scraping & Loading Debris Manuever, Wait
0.75 0.82 0.78 0.75
45.00 49.14 46.88 45.00
8.73
523.76
Total Productivity
2.58 m3/hr
Productivity
17.18 m2/hr
Pavement Breaking Trial Strip
Parameter Segment Length Width
Concrete
Quantity 50.00 3.00
Thickness = 230.00 mm
Unit m m
Pavement Thickness Area of Embankment Volume Equipment Specifications Parameter Forward Speed Reverse Speed Bucket Capacity Fuel Consumption
0.23 150.00 34.50
m sm m3
Backhoe w/ Breaker Quantity 2.63 2.63 0.80 16.00
Productivity Rates - Breaking Breaker Penetration Rate
Unit km/hr km/hr m3 li/hr
Duration per Breaking Stroke Swing-Lower/Raise-Swing Cycle Area Covered / Penetration Direct Area Breaking Rate Area Covered / Position Duration per Position Number of Positions Total Duration (Breaking)
3.00 10.80 0.021 35.00 0.80 37.57 18.75 0.51 8.00 4.07
mm/sec m/hr hrs secs m2 m2/hr m2 hrs positions hrs
Excluding Travel
Productivity Rates - Scraping & Loading Volume / Digging Stroke Swing-Scrape-Swing-Load Cycle Scraping - Loading Rate Area Covered / Position Volume Covered / Position Duration per Position Number of Positions Total Duration (Scraping & Loading)
0.28 35.00 28.80 18.75 4.31 0.15 8.00 1.20
m3 secs m3/hr m2 m3 hrs positions hrs
Excluding Travel
Time-Motion Table Activity
Rate
Time Required hrs
Time Required minutes
Breaking Fix Breaker, Maneuver, Wait Moving Forward, Positioning Breaking Fix Bucket, Maneuver, Wait
1.25 0.82 4.07 1.25
75.00 49.14 244.25 75.00
Scraping & Loading Debris Manuever, Wait Moving Forward, Positioning Scraping & Loading Debris Manuever, Wait
0.75 0.82 1.20 0.75
45.00 49.14 71.88 45.00
Total
10.91
654.41
Productivity
3.16 m3/hr
Productivity
13.75 m2/hr
Pavement Breaking
Concrete
Trial Strip
Parameter Segment Length Width Pavement Thickness Area of Embankment Volume Equipment Specifications Parameter Forward Speed Reverse Speed Bucket Capacity Fuel Consumption
Thickness = 250.00 mm
Quantity 50.00 3.00 0.25 150.00 37.50
Unit m m m sm m3
Backhoe w/ Breaker Quantity 2.63 2.63 0.80 16.00
Unit km/hr km/hr m3 li/hr
Productivity Rates - Breaking Breaker Penetration Rate Duration per Breaking Stroke Swing-Lower/Raise-Swing Cycle Area Covered / Penetration Direct Area Breaking Rate Area Covered / Position Duration per Position Number of Positions Total Duration (Breaking)
2.75 9.90 0.025 35.00 0.80 31.68 18.75 0.60 8.00 4.81
mm/sec m/hr hrs secs m2 m2/hr m2 hrs positions hrs
Excluding Travel
Productivity Rates - Scraping & Loading Volume / Digging Stroke Swing-Scrape-Swing-Load Cycle Scraping - Loading Rate Area Covered / Position Volume Covered / Position Duration per Position Number of Positions Total Duration (Scraping & Loading)
0.28 35.00 28.80 18.75 4.69 0.16 8.00 1.30
m3 secs m3/hr m2 m3 hrs positions hrs
Excluding Travel
Time-Motion Table Activity
Rate
Time Required
Time Required
Activity
Rate
hrs
minutes
Breaking Fix Breaker, Maneuver, Wait Moving Forward, Positioning Breaking Fix Bucket, Maneuver, Wait
1.25 0.82 4.81 1.25
75.00 49.14 288.76 75.00
Scraping & Loading Debris Manuever, Wait Moving Forward, Positioning Scraping & Loading Debris Manuever, Wait
0.75 0.82 1.30 0.75
45.00 49.14 78.13 45.00
11.75
705.17
Total Productivity
3.19 m3/hr
Productivity
12.76 m2/hr
PRODUCTIVITY CALCULATIONS Pile Driving Works Pile Driving - PC Piles Trial Pile Set Parameter Pile Dimension 1 Pile Dimension 2 Pile Length Quantity of Piles Total Pile Length Equipment Specifications Parameter Forward Speed Reverse Speed Lifting Capacity Fuel Consumption Pile Penetration Rate
Quantity 400.00 400.00 12.00 10.00 120.00
Remarks
Crane 40.00 Tons w/ Vibratory Hammer Quantity Unit Remarks 2.00 km/hr 2.00 km/hr 40.00 tons 27.00 li/hr 3.00 lm/hr
Time-Motion Table Activity
Unit mm mm m nos m
Time Required hrs
Rate
Time Required minutes
Equipment Set-up Setting-Up of Rig
1.50
90.00
Pile Driving - Pile No. 1 Maneuver to Position Pick-Up Pile Drive Pile Release Pile
0.25 0.25 4.00 0.08
15.00 15.00 240.00 5.00
0.25 0.25 4.00 0.08
15.00 15.00 240.00 5.00
0.25 0.25 4.00 0.08
15.00 15.00 240.00 5.00
0.25
15.00
Pile Driving - Pile No. 2 Maneuver to Position Pick-Up Pile Drive Pile Release Pile Pile Driving - Pile No. 3 Maneuver to Position Pick-Up Pile Drive Pile Release Pile Pile Driving - Pile No. 4 Maneuver to Position
3.00
3.00
3.00
Pick-Up Pile Drive Pile Release Pile
3.00
Pile Driving - Pile No. 5 Maneuver to Position Pick-Up Pile Drive Pile Release Pile Pile Driving - Pile No. 6 Maneuver to Position Pick-Up Pile Drive Pile Release Pile Pile Driving - Pile No. 7 Maneuver to Position Pick-Up Pile Drive Pile Release Pile Pile Driving - Pile No. 8 Maneuver to Position Pick-Up Pile Drive Pile Release Pile Pile Driving - Pile No. 9 Maneuver to Position Pick-Up Pile Drive Pile Release Pile Pile Driving - Pile No. 10 Maneuver to Position Pick-Up Pile Drive Pile Release Pile
3.00
3.00
3.00
3.00
3.00
3.00
Total Productivity
0.25 4.00 0.08
15.00 240.00 5.00
0.25 0.25 4.00 0.08
15.00 15.00 240.00 5.00
0.25 0.25 4.00 0.08
15.00 15.00 240.00 5.00
0.25 0.25 4.00 0.08
15.00 15.00 240.00 5.00
0.25 0.25 4.00 0.08
15.00 15.00 240.00 5.00
0.25 0.25 4.00 0.08
15.00 15.00 240.00 5.00
0.25 0.25 4.00 0.08
15.00 15.00 240.00 5.00
47.33
2,840.00
2.54 lm/hr
Pile Driving - H Piles Trial Pile Set Parameter Pile Dimension 1
Quantity 350.00
Unit mm
Remarks
Pile Dimension 2 Pile Length Quantity of Piles Total Pile Length Equipment Specifications Parameter Forward Speed Reverse Speed Lifting Capacity Fuel Consumption Pile Penetration Rate
350.00 12.00 10.00 120.00
Crane 40.00 Tons w/ Vibratory Hammer Quantity Unit Remarks 2.00 km/hr 2.00 km/hr 40.00 tons 27.00 li/hr 4.00 lm/hr
Time-Motion Table Activity
mm m nos m
Time Required hrs
Rate
Time Required minutes
Equipment Set-up Setting-Up of Rig
1.50
90.00
Pile Driving - Pile No. 1 Maneuver to Position Pick-Up Pile Drive Pile Release Pile
0.25 0.25 3.00 0.08
15.00 15.00 180.00 5.00
0.25 0.25 3.00 0.08
15.00 15.00 180.00 5.00
0.25 0.25 3.00 0.08
15.00 15.00 180.00 5.00
0.25 0.25 3.00 0.08
15.00 15.00 180.00 5.00
0.25 0.25 3.00 0.08
15.00 15.00 180.00 5.00
Pile Driving - Pile No. 2 Maneuver to Position Pick-Up Pile Drive Pile Release Pile Pile Driving - Pile No. 3 Maneuver to Position Pick-Up Pile Drive Pile Release Pile Pile Driving - Pile No. 4 Maneuver to Position Pick-Up Pile Drive Pile Release Pile Pile Driving - Pile No. 5 Maneuver to Position Pick-Up Pile Drive Pile Release Pile
4.00
4.00
4.00
4.00
4.00
Pile Driving - Pile No. 6 Maneuver to Position Pick-Up Pile Drive Pile Release Pile Pile Driving - Pile No. 7 Maneuver to Position Pick-Up Pile Drive Pile Release Pile Pile Driving - Pile No. 8 Maneuver to Position Pick-Up Pile Drive Pile Release Pile Pile Driving - Pile No. 9 Maneuver to Position Pick-Up Pile Drive Pile Release Pile Pile Driving - Pile No. 10 Maneuver to Position Pick-Up Pile Drive Pile Release Pile
4.00
4.00
4.00
4.00
4.00
Total Productivity
0.25 0.25 3.00 0.08
15.00 15.00 180.00 5.00
0.25 0.25 3.00 0.08
15.00 15.00 180.00 5.00
0.25 0.25 3.00 0.08
15.00 15.00 180.00 5.00
0.25 0.25 3.00 0.08
15.00 15.00 180.00 5.00
0.25 0.25 3.00 0.08
15.00 15.00 180.00 5.00
37.33
2,240.00
3.21 lm/hr
Pile Driving - Sheet Piles Trial Pile Set Parameter Pile Dimension 1 Pile Dimension 2 Pile Length Quantity of Piles Total Pile Length Equipment Specifications Parameter Forward Speed Reverse Speed
Quantity 100.00 400.00 12.00 10.00 120.00
Unit mm mm m nos m
Remarks
Crane 40.00 Tons w/ Vibratory Hammer Quantity Unit Remarks 2.00 km/hr 2.00 km/hr
Lifting Capacity Fuel Consumption Pile Penetration Rate
40.00 27.00 8.00
Time-Motion Table Activity
tons li/hr lm/hr
Time Required hrs
Rate
Time Required minutes
Equipment Set-up Setting-Up of Pile Driver
1.00
60.00
Pile Driving - Pile No. 1 Maneuver to Position Pick-Up Pile Drive Pile Release Pile
0.25 0.17 1.50 0.08
15.00 10.00 90.00 5.00
0.25 0.17 1.50 0.08
15.00 10.00 90.00 5.00
0.25 0.17 1.50 0.08
15.00 10.00 90.00 5.00
0.25 0.17 1.50 0.08
15.00 10.00 90.00 5.00
0.25 0.17 1.50 0.08
15.00 10.00 90.00 5.00
0.25 0.17 1.50 0.08
15.00 10.00 90.00 5.00
0.25
15.00
Pile Driving - Pile No. 2 Maneuver to Position Pick-Up Pile Drive Pile Release Pile Pile Driving - Pile No. 3 Maneuver to Position Pick-Up Pile Drive Pile Release Pile Pile Driving - Pile No. 4 Maneuver to Position Pick-Up Pile Drive Pile Release Pile Pile Driving - Pile No. 5 Maneuver to Position Pick-Up Pile Drive Pile Release Pile Pile Driving - Pile No. 6 Maneuver to Position Pick-Up Pile Drive Pile Release Pile Pile Driving - Pile No. 7 Maneuver to Position
8.00
8.00
8.00
8.00
8.00
8.00
Pick-Up Pile Drive Pile Release Pile
8.00
Pile Driving - Pile No. 8 Maneuver to Position Pick-Up Pile Drive Pile Release Pile
8.00
Pile Driving - Pile No. 9 Maneuver to Position Pick-Up Pile Drive Pile Release Pile
8.00
Pile Driving - Pile No. 10 Maneuver to Position Pick-Up Pile Drive Pile Release Pile
8.00
Total Productivity
0.17 1.50 0.08
10.00 90.00 5.00
0.25 0.17 1.50 0.08
15.00 10.00 90.00 5.00
0.25 0.17 1.50 0.08
15.00 10.00 90.00 5.00
0.25 0.17 1.50 0.08
15.00 10.00 90.00 5.00
21.00
1,260.00
5.71 lm/hr
Pile Extraction - Sheet Piles Trial Pile Set Parameter Pile Dimension 1 Pile Dimension 2 Pile Length Quantity of Piles Total Pile Length Equipment Specifications Parameter Forward Speed Reverse Speed Lifting Capacity Fuel Consumption Pile Extraction Rate
Quantity 100.00 400.00 12.00 10.00 120.00
Remarks
Crane 40.00 Tons w/ Vibratory Hammer Quantity Unit Remarks 2.00 km/hr 2.00 km/hr 40.00 tons 27.00 li/hr 12.00 lm/hr
Time-Motion Table Activity
Unit mm mm m nos m
Rate
Time Required hrs
Time Required minutes
Equipment Set-up Setting-Up of Pile Driver Pile Driving - Pile No. 1 Maneuver to Position Drive Pile Lay Pile to Ground Pile Driving - Pile No. 2 Maneuver to Position Drive Pile Lay Pile to Ground Pile Driving - Pile No. 3 Maneuver to Position Drive Pile Lay Pile to Ground Pile Driving - Pile No. 4 Maneuver to Position Drive Pile Lay Pile to Ground Pile Driving - Pile No. 5 Maneuver to Position Drive Pile Lay Pile to Ground Pile Driving - Pile No. 6 Maneuver to Position Drive Pile Lay Pile to Ground Pile Driving - Pile No. 7 Maneuver to Position Drive Pile Lay Pile to Ground Pile Driving - Pile No. 8 Maneuver to Position Drive Pile Lay Pile to Ground Pile Driving - Pile No. 9 Maneuver to Position Drive Pile Lay Pile to Ground Pile Driving - Pile No. 10 Maneuver to Position
1.50
90.00
12.00
0.25 1.00 0.08
15.00 60.00 5.00
12.00
0.25 1.00 0.08
15.00 60.00 5.00
12.00
0.25 1.00 0.08
15.00 60.00 5.00
12.00
0.25 1.00 0.08
15.00 60.00 5.00
12.00
0.25 1.00 0.08
15.00 60.00 5.00
12.00
0.25 1.00 0.08
15.00 60.00 5.00
12.00
0.25 1.00 0.08
15.00 60.00 5.00
12.00
0.25 1.00 0.08
15.00 60.00 5.00
12.00
0.25 1.00 0.08
15.00 60.00 5.00
0.25
15.00
Drive Pile Lay Pile to Ground
12.00
Total Productivity
1.00 0.08
60.00 5.00
14.83
890.00
8.09 lm/hr
Pile Loading / Unloading - PC Piles Trial Pile Set Parameter Pile Dimension 1 Pile Dimension 2 Pile Length Pile Weight Quantity of Piles Total Pile Length Total Pile Weight Equipment Specifications Parameter Forward Speed Reverse Speed Lifting Capacity Fuel Consumption Swing-Hoist Up-Swing-Hoist Down
Quantity 400.00 400.00 12.00 4,608.00 5.00 60.00 23,040.00
Unit mm mm m kgs nos m kgs
Remarks
Crane 40.00 Tons Quantity 2.00 2.00 40.00 27.00 120.00
Unit km/hr km/hr tons li/hr secs
Remarks
Rate
Time Required hrs
Time Required minutes
Time-Motion Table Activity
Pile No. 1 Maneuver to Position Rig Pile Swing-Hoist Up-Swing-Hoist Down Unrig Pile Pile No. 2 Maneuver to Position Rig Pile Swing-Hoist Up-Swing-Hoist Down Unrig Pile Pile No. 3 Maneuver to Position Rig Pile Swing-Hoist Up-Swing-Hoist Down Unrig Pile
0.03
0.03
0.03
0.15 0.10 0.03 0.05
9.00 6.00 2.00 3.00
0.15 0.10 0.03 0.05
9.00 6.00 2.00 3.00
0.15 0.10 0.03 0.05
9.00 6.00 2.00 3.00
Pile No. 4 Maneuver to Position Rig Pile Swing-Hoist Up-Swing-Hoist Down Unrig Pile
0.03
Pile No. 5 Maneuver to Position Rig Pile Swing-Hoist Up-Swing-Hoist Down Unrig Pile
0.03
Total Productivity
0.15 0.10 0.03 0.05
9.00 6.00 2.00 3.00
0.15 0.10 0.03 0.05
9.00 6.00 2.00 3.00
1.67
100.00
36.00 lm/hr
Pile Loading / Unloading - Steel Piles Trial Pile Set Parameter Pile Dimension 1 Pile Dimension 2 Pile Length Pile Weight Quantity of Piles Total Pile Length Total Pile Weight Equipment Specifications Parameter Forward Speed Reverse Speed Lifting Capacity Fuel Consumption Swing-Hoist Up-Swing-Hoist Down
Quantity 350.00 350.00 12.00 1,980.00 5.00 60.00 9,900.00
Unit mm mm m kgs nos m kgs
Remarks
Crane 40.00 Tons Quantity 2.00 2.00 40.00 27.00 100.00
Unit km/hr km/hr tons li/hr secs
Remarks
Rate
Time Required hrs
Time Required minutes
Time-Motion Table Activity
Pile No. 1 Maneuver to Position Rig Pile Swing-Hoist Up-Swing-Hoist Down Unrig Pile
0.03
0.15 0.10 0.03 0.05
9.00 6.00 1.67 3.00
Pile No. 2 Maneuver to Position Rig Pile Swing-Hoist Up-Swing-Hoist Down Unrig Pile
0.03
Pile No. 3 Maneuver to Position Rig Pile Swing-Hoist Up-Swing-Hoist Down Unrig Pile
0.03
Pile No. 4 Maneuver to Position Rig Pile Swing-Hoist Up-Swing-Hoist Down Unrig Pile
0.03
Pile No. 5 Maneuver to Position Rig Pile Swing-Hoist Up-Swing-Hoist Down Unrig Pile
0.03
Total Productivity
0.15 0.10 0.03 0.05
9.00 6.00 1.67 3.00
0.15 0.10 0.03 0.05
9.00 6.00 1.67 3.00
0.15 0.10 0.03 0.05
9.00 6.00 1.67 3.00
0.15 0.10 0.03 0.05
9.00 6.00 1.67 3.00
1.64
98.33
36.61 lm/hr
Pile Loading / Unloading - Sheet Piles Trial Pile Set Parameter Pile Dimension 1 Pile Dimension 2 Pile Length Pile Weight Quantity of Piles Total Pile Length Total Pile Weight Equipment Specifications Parameter Forward Speed Reverse Speed Lifting Capacity Fuel Consumption Swing-Hoist Up-Swing-Hoist Down
Quantity 400.00 100.00 12.00 50.00 5.00 60.00 250.00 Crane 40.00 Tons Quantity 2.00 2.00 40.00 27.00 85.00
Unit mm mm m kgs nos m kgs
Remarks
Unit km/hr km/hr tons li/hr secs
Remarks
Time-Motion Table Activity
Pile No. 1 Maneuver to Position Rig Pile Swing-Hoist Up-Swing-Hoist Down Unrig Pile Pile No. 2 Maneuver to Position Rig Pile Swing-Hoist Up-Swing-Hoist Down Unrig Pile Pile No. 3 Maneuver to Position Rig Pile Swing-Hoist Up-Swing-Hoist Down Unrig Pile Pile No. 4 Maneuver to Position Rig Pile Swing-Hoist Up-Swing-Hoist Down Unrig Pile Pile No. 5 Maneuver to Position Rig Pile Swing-Hoist Up-Swing-Hoist Down Unrig Pile
Time Required hrs
Rate
0.02
0.02
0.02
0.02
0.02
Total Productivity
0.15 0.05 0.02 0.05
9.00 3.00 1.42 3.00
0.15 0.05 0.02 0.05
9.00 3.00 1.42 3.00
0.15 0.05 0.02 0.05
9.00 3.00 1.42 3.00
0.15 0.05 0.02 0.05
9.00 3.00 1.42 3.00
0.15 0.05 0.02 0.05
9.00 3.00 1.42 3.00
1.37
82.08
43.86 lm/hr
PILES HAULING
PC PILES Equipment Specifications Parameter Loaded Speed Empty Speed
Time Required minutes
Trailer Truck Quantity 25.00 40.00
Cap = 40,000.00 kgs.
Unit km/hr km/hr
Load Capacity (Weight) Load Capacity (lm) Fuel Consumption AHD = Time-Motion Table Activity
Maneuver & Wait Wait While Loading Travel (Loaded) Wait While Unloading Travel (Empty)
40,000.00 104.00 15.00
kgs. lm li/hr
1.000 km(s)
Rate
Time Required hrs
36.00 lm/hr 25.00 36.00 lm/hr 40.00
Total Productivity
Time Required minutes
0.08 2.89 0.04 2.89 0.03
5.00 173.33 2.40 173.33 1.50
5.93
355.57
17.55 lm/hr
AHD= 1.000 km(s)
STEEL PILES Equipment Specifications Parameter Loaded Speed Empty Speed Load Capacity (Weight) Load Capacity (lm) Fuel Consumption
Cargo Truck Quantity 25.00 40.00 20,000.00 121.00 15.00
AHD = Time-Motion Table
1.000 km(s)
Activity
Maneuver & Wait Wait While Loading Travel (Loaded) Wait While Unloading Travel (Empty)
Rate
36.61 lm/hr 25.00 36.61 lm/hr 40.00
Total Productivity
STEEL SHEET PILES
AHD= 1.000 km(s)
Cap = 20,000.00 kgs.
Unit km/hr km/hr kgs. lm li/hr
Time Required hrs
Time Required minutes
0.08 3.31 0.04 3.31 0.03
5.00 198.31 2.40 198.31 1.50
6.76
405.51
17.90 lm/hr
Equipment Specifications Parameter Loaded Speed Empty Speed Load Capacity (Weight) Load Capacity (lm) Fuel Consumption
Cargo Truck Quantity 25.00 40.00 20,000.00 4,800.00 15.00
AHD = Time-Motion Table
1.000 km(s)
Activity
Maneuver & Wait Wait While Loading Travel (Loaded) Wait While Unloading Travel (Empty)
Rate
43.86 lm/hr 25.00 43.86 lm/hr 40.00
Total Productivity
AHD= 1.000 km(s)
Cap = 20,000.00 kgs.
Unit km/hr km/hr kgs. lm li/hr
Time Required hrs
Time Required minutes
0.08 109.44 0.04 109.44 0.03
5.00 6,566.67 2.40 6,566.67 1.50
219.04
13,142.23
21.91 lm/hr
19800 7795.276 974.4094 243.6024
123.75
PRODUCTIVITY CALCULATIONS Pipe Laying Works RC Pipe Laying Trial Pipe Set Parameter Pipe Diameter Pipe Length Pipe Weight Quantity of Pipes Total Pipe Length Total Pipe Weight Equipment Specifications Parameter Forward Speed Reverse Speed Lifting Capacity Fuel Consumption Swing-Hoist Up-Swing-Hoist Down
1600Ø mm
Quantity
Unit m m kgs no(s) m kgs
Remarks
Crane 25.00 Tons Quantity 2.00 2.00 25.00 27.00 120.00
Unit km/hr km/hr tons li/hr secs
Remarks
Rate
Time Required hrs
Time Required minutes
Equipment Set-up / Waiting Set-up / Waiting / Maneuvering Pipe Laying 1 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Align Pipe Unrig Pipe
120.00
Pipe Laying 2 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Align Pipe Unrig Pipe
120.00
Pipe Laying 3 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Align Pipe Unrig Pipe
120.00
Pipe Laying 4
2000Ø mm
2.00 1.00 785.40 10.00 10.00 7,853.98
Time-Motion Table Activity
to
0.33
20.00
0.03 0.03 0.05 0.03
2.00 2.00 3.00 2.00
0.03 0.03 0.05 0.03
2.00 2.00 3.00 2.00
0.03 0.03 0.05 0.03
2.00 2.00 3.00 2.00
Rig Pipe Swing-Hoist Up-Swing-Hoist Down Align Pipe Unrig Pipe
120.00
Pipe Laying 5 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Align Pipe Unrig Pipe
120.00
Pipe Laying 6 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Align Pipe Unrig Pipe
120.00
Pipe Laying 7 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Align Pipe Unrig Pipe
120.00
Pipe Laying 8 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Align Pipe Unrig Pipe
120.00
Pipe Laying 9 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Align Pipe Unrig Pipe
120.00
Pipe Laying 10 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Align Pipe Unrig Pipe
120.00
Total Productivity
RC Pipe Laying Trial Pipe Set Parameter
0.03 0.03 0.05 0.03
2.00 2.00 3.00 2.00
0.03 0.03 0.05 0.03
2.00 2.00 3.00 2.00
0.03 0.03 0.05 0.03
2.00 2.00 3.00 2.00
0.03 0.03 0.05 0.03
2.00 2.00 3.00 2.00
0.03 0.03 0.05 0.03
2.00 2.00 3.00 2.00
0.03 0.03 0.05 0.03
2.00 2.00 3.00 2.00
0.03 0.03 0.05 0.03
2.00 2.00 3.00 2.00
1.83
110.00
5.45 lm/hr
1200Ø mm
Quantity
to
Unit
1500Ø mm
Remarks
Pipe Diameter Pipe Length Pipe Weight Quantity of Pipes Total Pipe Length Total Pipe Weight Equipment Specifications Parameter Forward Speed Reverse Speed Lifting Capacity Fuel Consumption Swing-Hoist Up-Swing-Hoist Down
1.50 1.00 441.79 10.00 10.00 4,417.86
m m kgs no(s) m kgs
Crane 25.00 Tons Quantity 2.00 2.00 25.00 27.00 110.00
Unit km/hr km/hr tons li/hr secs
Remarks
Rate
Time Required hrs
Time Required minutes
Time-Motion Table Activity
Equipment Set-up / Waiting Set-up / Waiting / Maneuvering
0.33
20.00
Pipe Laying 1 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Align Pipe Unrig Pipe
0.03 0.03 0.05 0.03
2.00 1.83 3.00 2.00
0.03 0.03 0.05 0.03
2.00 1.83 3.00 2.00
0.03 0.03 0.05 0.03
2.00 1.83 3.00 2.00
0.03 0.03 0.05 0.03
2.00 1.83 3.00 2.00
0.03 0.03
2.00 1.83
110.00
Pipe Laying 2 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Align Pipe Unrig Pipe
110.00
Pipe Laying 3 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Align Pipe Unrig Pipe
110.00
Pipe Laying 4 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Align Pipe Unrig Pipe
110.00
Pipe Laying 5 Rig Pipe Swing-Hoist Up-Swing-Hoist Down
110.00
Align Pipe Unrig Pipe Pipe Laying 6 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Align Pipe Unrig Pipe
110.00
Pipe Laying 7 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Align Pipe Unrig Pipe
110.00
Pipe Laying 8 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Align Pipe Unrig Pipe
110.00
Pipe Laying 9 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Align Pipe Unrig Pipe
110.00
Pipe Laying 10 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Align Pipe Unrig Pipe
110.00
Total Productivity
RC Pipe Laying Trial Pipe Set Parameter Pipe Diameter Pipe Length Pipe Weight Quantity of Pipes Total Pipe Length Total Pipe Weight Equipment Specifications
0.05 0.03
3.00 2.00
0.03 0.03 0.05 0.03
2.00 1.83 3.00 2.00
0.03 0.03 0.05 0.03
2.00 1.83 3.00 2.00
0.03 0.03 0.05 0.03
2.00 1.83 3.00 2.00
0.03 0.03 0.05 0.03
2.00 1.83 3.00 2.00
0.03 0.03 0.05 0.03
2.00 1.83 3.00 2.00
1.81
108.33
5.54 lm/hr
600Ø mm
Quantity
1.00 1.00 196.35 10.00 10.00 1,963.50
Crane 25.00 Tons
to
Unit m m kgs no(s) m kgs
1000Ø mm
Remarks
Parameter Forward Speed Reverse Speed Lifting Capacity Fuel Consumption Swing-Hoist Up-Swing-Hoist Down
Quantity
2.00 2.00 25.00 27.00 100.00
Time-Motion Table Activity
Rate
Equipment Set-up / Waiting Set-up / Waiting / Maneuvering Pipe Laying 1 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Align Pipe Unrig Pipe
100.00
Pipe Laying 2 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Align Pipe Unrig Pipe
100.00
Pipe Laying 3 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Align Pipe Unrig Pipe
100.00
Pipe Laying 4 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Align Pipe Unrig Pipe
100.00
Pipe Laying 5 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Align Pipe Unrig Pipe
100.00
Pipe Laying 6 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Align Pipe Unrig Pipe
100.00
Unit km/hr km/hr tons li/hr secs
Remarks
Time Required hrs
Time Required minutes
0.33
20.00
0.03 0.03 0.05 0.03
2.00 1.67 3.00 2.00
0.03 0.03 0.05 0.03
2.00 1.67 3.00 2.00
0.03 0.03 0.05 0.03
2.00 1.67 3.00 2.00
0.03 0.03 0.05 0.03
2.00 1.67 3.00 2.00
0.03 0.03 0.05 0.03
2.00 1.67 3.00 2.00
0.03 0.03 0.05 0.03
2.00 1.67 3.00 2.00
Pipe Laying 7 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Align Pipe Unrig Pipe
100.00
Pipe Laying 8 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Align Pipe Unrig Pipe
100.00
Pipe Laying 9 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Align Pipe Unrig Pipe
100.00
Pipe Laying 10 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Align Pipe Unrig Pipe
100.00
Total Productivity
RC Pipe Laying Trial Pipe Set Parameter Pipe Diameter Pipe Length Pipe Weight Quantity of Pipes Total Pipe Length Total Pipe Weight Equipment Specifications Parameter Forward Speed Reverse Speed Lifting Capacity Fuel Consumption Swing-Hoist Up-Swing-Hoist Down Time-Motion Table
0.03 0.03 0.05 0.03
2.00 1.67 3.00 2.00
0.03 0.03 0.05 0.03
2.00 1.67 3.00 2.00
0.03 0.03 0.05 0.03
2.00 1.67 3.00 2.00
0.03 0.03 0.05 0.03
2.00 1.67 3.00 2.00
1.78
106.67
5.63 lm/hr
300Ø mm
Quantity
to
500Ø mm
0.50 1.00 49.09 10.00 10.00 490.87
Unit m m kgs no(s) m kgs
Remarks
Crane 25.00 Tons Quantity 2.00 2.00 25.00 27.00 90.00
Unit km/hr km/hr tons li/hr secs
Remarks
Activity
Time Required hrs
Rate
Time Required minutes
Equipment Set-up / Waiting Set-up / Waiting / Maneuvering
0.33
20.00
Pipe Laying 1 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Align Pipe Unrig Pipe
90.00
0.03 0.03 0.05 0.03
2.00 1.50 3.00 2.00
Pipe Laying 2 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Align Pipe Unrig Pipe
90.00
0.03 0.03 0.05 0.03
2.00 1.50 3.00 2.00
Pipe Laying 3 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Align Pipe Unrig Pipe
90.00
0.03 0.03 0.05 0.03
2.00 1.50 3.00 2.00
Pipe Laying 4 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Align Pipe Unrig Pipe
90.00
0.03 0.03 0.05 0.03
2.00 1.50 3.00 2.00
Pipe Laying 5 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Align Pipe Unrig Pipe
90.00
0.03 0.03 0.05 0.03
2.00 1.50 3.00 2.00
Pipe Laying 6 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Align Pipe Unrig Pipe
90.00
0.03 0.03 0.05 0.03
2.00 1.50 3.00 2.00
Pipe Laying 7 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Align Pipe Unrig Pipe
90.00
0.03 0.03 0.05 0.03
2.00 1.50 3.00 2.00
Pipe Laying 8
Rig Pipe Swing-Hoist Up-Swing-Hoist Down Align Pipe Unrig Pipe
90.00
Pipe Laying 9 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Align Pipe Unrig Pipe
90.00
Pipe Laying 10 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Align Pipe Unrig Pipe
90.00
Total Productivity
0.03 0.03 0.05 0.03
2.00 1.50 3.00 2.00
0.03 0.03 0.05 0.03
2.00 1.50 3.00 2.00
0.03 0.03 0.05 0.03
2.00 1.50 3.00 2.00
1.75
105.00
5.71 lm/hr
RC Pipe Loading / Unloading Trial Pipe Set Parameter Pipe Diameter Pipe Length Pipe Weight Quantity of Pipes Total Pipe Length Total Pipe Weight Equipment Specifications Parameter Forward Speed Reverse Speed Lifting Capacity Fuel Consumption Swing-Hoist Up-Swing-Hoist Down
1600Ø mm
Quantity
Equipment Set-up / Waiting Set-up / Waiting / Maneuvering Pipe Loading / Unloading 1
2000Ø mm
2.00 1.00 785.40 10.00 10.00 7,853.98
Unit m m kgs no(s) m kgs
Remarks
Crane 25.00 Tons Quantity 2.00 2.00 25.00 27.00 120.00
Unit km/hr km/hr tons li/hr secs
Remarks
Rate
Time Required hrs
Time Required minutes
Time-Motion Table Activity
to
0.33
20.00
Rig Pipe Swing-Hoist Up-Swing-Hoist Down Unrig Pipe Pipe Loading / Unloading 2 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Unrig Pipe Pipe Loading / Unloading 3 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Unrig Pipe Pipe Loading / Unloading 4 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Unrig Pipe Pipe Loading / Unloading 5 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Unrig Pipe Pipe Loading / Unloading 6 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Unrig Pipe Pipe Loading / Unloading 7 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Unrig Pipe Pipe Loading / Unloading 8 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Unrig Pipe Pipe Loading / Unloading 9 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Unrig Pipe Pipe Loading / Unloading 10 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Unrig Pipe Total
120.00
0.03 0.03 0.03
2.00 2.00 2.00
120.00
0.03 0.03 0.03
2.00 2.00 2.00
120.00
0.03 0.03 0.03
2.00 2.00 2.00
120.00
0.03 0.03 0.03
2.00 2.00 2.00
120.00
0.03 0.03 0.03
2.00 2.00 2.00
120.00
0.03 0.03 0.03
2.00 2.00 2.00
120.00
0.03 0.03 0.03
2.00 2.00 2.00
120.00
0.03 0.03 0.03
2.00 2.00 2.00
120.00
0.03 0.03 0.03
2.00 2.00 2.00
120.00
0.03 0.03 0.03
2.00 2.00 2.00
1.33
80.00
Productivity
7.50 lm/hr
RC Pipe Loading / Unloading Trial Pipe Set Parameter Pipe Diameter Pipe Length Pipe Weight Quantity of Pipes Total Pipe Length Total Pipe Weight Equipment Specifications Parameter Forward Speed Reverse Speed Lifting Capacity Fuel Consumption Swing-Hoist Up-Swing-Hoist Down
1200Ø mm
Quantity
Unit m m kgs no(s) m kgs
Remarks
Crane 25.00 Tons Quantity 2.00 2.00 25.00 27.00 110.00
Unit km/hr km/hr tons li/hr secs
Remarks
Rate
Time Required hrs
Time Required minutes
Equipment Set-up / Waiting Set-up / Waiting / Maneuvering Pipe Loading / Unloading 1 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Unrig Pipe Pipe Loading / Unloading 2 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Unrig Pipe Pipe Loading / Unloading 3 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Unrig Pipe Pipe Loading / Unloading 4 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Unrig Pipe
1500Ø mm
1.50 1.00 441.79 10.00 10.00 4,417.86
Time-Motion Table Activity
to
0.33
20.00
110.00
0.03 0.03 0.03
2.00 1.83 2.00
110.00
0.03 0.03 0.03
2.00 1.83 2.00
110.00
0.03 0.03 0.03
2.00 1.83 2.00
110.00
0.03 0.03 0.03
2.00 1.83 2.00
Pipe Loading / Unloading 5 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Unrig Pipe Pipe Loading / Unloading 6 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Unrig Pipe Pipe Loading / Unloading 7 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Unrig Pipe Pipe Loading / Unloading 8 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Unrig Pipe Pipe Loading / Unloading 9 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Unrig Pipe Pipe Loading / Unloading 10 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Unrig Pipe
110.00
0.03 0.03 0.03
2.00 1.83 2.00
110.00
0.03 0.03 0.03
2.00 1.83 2.00
110.00
0.03 0.03 0.03
2.00 1.83 2.00
110.00
0.03 0.03 0.03
2.00 1.83 2.00
110.00
0.03 0.03 0.03
2.00 1.83 2.00
110.00
0.03 0.03 0.03
2.00 1.83 2.00
1.31
78.33
Total Productivity
RC Pipe Loading / Unloading Trial Pipe Set Parameter Pipe Diameter Pipe Length Pipe Weight Quantity of Pipes Total Pipe Length Total Pipe Weight Equipment Specifications Parameter Forward Speed
7.66 lm/hr
600Ø mm
Quantity
to
1000Ø mm
1.00 1.00 196.35 10.00 10.00 1,963.50
Unit m m kgs no(s) m kgs
Remarks
Crane 25.00 Tons Quantity 2.00
Unit km/hr
Remarks
Reverse Speed Lifting Capacity Fuel Consumption Swing-Hoist Up-Swing-Hoist Down
2.00 25.00 27.00 100.00
Time-Motion Table Activity
Rate
Equipment Set-up / Waiting Set-up / Waiting / Maneuvering Pipe Loading / Unloading 1 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Unrig Pipe Pipe Loading / Unloading 2 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Unrig Pipe Pipe Loading / Unloading 3 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Unrig Pipe Pipe Loading / Unloading 4 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Unrig Pipe Pipe Loading / Unloading 5 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Unrig Pipe Pipe Loading / Unloading 6 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Unrig Pipe Pipe Loading / Unloading 7 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Unrig Pipe Pipe Loading / Unloading 8 Rig Pipe
km/hr tons li/hr secs
Time Required hrs
Time Required minutes
0.33
20.00
100.00
0.03 0.03 0.03
2.00 1.67 2.00
100.00
0.03 0.03 0.03
2.00 1.67 2.00
100.00
0.03 0.03 0.03
2.00 1.67 2.00
100.00
0.03 0.03 0.03
2.00 1.67 2.00
100.00
0.03 0.03 0.03
2.00 1.67 2.00
100.00
0.03 0.03 0.03
2.00 1.67 2.00
100.00
0.03 0.03 0.03
2.00 1.67 2.00
0.03
2.00
Swing-Hoist Up-Swing-Hoist Down Unrig Pipe Pipe Loading / Unloading 9 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Unrig Pipe Pipe Loading / Unloading 10 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Unrig Pipe
100.00
0.03 0.03
1.67 2.00
100.00
0.03 0.03 0.03
2.00 1.67 2.00
100.00
0.03 0.03 0.03
2.00 1.67 2.00
1.28
76.67
Total Productivity
7.83 lm/hr
RC Pipe Loading / Unloading Trial Pipe Set Parameter Pipe Diameter Pipe Length Pipe Weight Quantity of Pipes Total Pipe Length Total Pipe Weight Equipment Specifications Parameter Forward Speed Reverse Speed Lifting Capacity Fuel Consumption Swing-Hoist Up-Swing-Hoist Down
300Ø mm
Quantity
500Ø mm
0.50 1.00 49.09 10.00 10.00 490.87
Unit m m kgs no(s) m kgs
Remarks
Crane 25.00 Tons Quantity 2.00 2.00 25.00 27.00 90.00
Unit km/hr km/hr tons li/hr secs
Remarks
Rate
Time Required hrs
Time Required minutes
Time-Motion Table Activity
to
Equipment Set-up / Waiting Set-up / Waiting / Maneuvering
0.33
20.00
Pipe Loading / Unloading 1 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Unrig Pipe
0.03 0.03 0.03
2.00 1.50 2.00
90.00
Pipe Loading / Unloading 2 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Unrig Pipe Pipe Loading / Unloading 3 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Unrig Pipe Pipe Loading / Unloading 4 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Unrig Pipe Pipe Loading / Unloading 5 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Unrig Pipe Pipe Loading / Unloading 6 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Unrig Pipe Pipe Loading / Unloading 7 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Unrig Pipe Pipe Loading / Unloading 8 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Unrig Pipe Pipe Loading / Unloading 9 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Unrig Pipe Pipe Loading / Unloading 10 Rig Pipe Swing-Hoist Up-Swing-Hoist Down Unrig Pipe Total Productivity
90.00
0.03 0.03 0.03
2.00 1.50 2.00
90.00
0.03 0.03 0.03
2.00 1.50 2.00
90.00
0.03 0.03 0.03
2.00 1.50 2.00
90.00
0.03 0.03 0.03
2.00 1.50 2.00
90.00
0.03 0.03 0.03
2.00 1.50 2.00
90.00
0.03 0.03 0.03
2.00 1.50 2.00
90.00
0.03 0.03 0.03
2.00 1.50 2.00
90.00
0.03 0.03 0.03
2.00 1.50 2.00
90.00
0.03 0.03 0.03
2.00 1.50 2.00
1.25
75.00
8.00 lm/hr
RC Pipe Hauling
Trial Pipe Set Parameter Pipe Diameter Pipe Length Pipe Weight Pipe Volume (Cube Volume) Quantity of Pipes Total Pipe Length Total Pipe Weight Total Pipe Volume Hauling Distance Equipment Specifications Parameter Speed (Loaded) Speed (Empty) Load Capacity Fuel Consumption Loading Bay Width Loading Bay Length Loading Bay Height Loading Bay Volume Capacity (number of Pipes)
1600Ø mm to Hauling Distance: 30.00 km(s)
Quantity
Activity
Waiting / Maneuvering Loading of Pipes Travel (Loaded) Unloading of Pipes Travel (Empty)
Unit m m kgs m3 no(s) m kgs m3 km
Remarks
Unit km/hr km/hr tons li/hr m m m m3 pcs
Remarks
Time Required hrs
Time Required minutes
2.00 1.00 785.40 4.00 10.00 10.00 7,853.98 40.00 30.00
Truck with Liting Boom Quantity 40.00 60.00 20.00 10.00 3.00 6.00 2.00 36.00 10.00
Time-Motion Table Rate
7.50 40.00 7.50 60.00
Total Productivity
RC Pipe Hauling
Trial Pipe Set Parameter Pipe Diameter Pipe Length
2000Ø mm
0.17 1.33 0.75 1.33 0.50
10.00 80.00 45.00 80.00 30.00
4.08
245.00
2.45 lm/hr
1200Ø mm to Hauling Distance: 30.00 km(s)
Quantity
1.50 1.00
Unit m m
1500Ø mm
Remarks
Pipe Weight Pipe Volume (Cube Volume) Quantity of Pipes Total Pipe Length Total Pipe Weight Total Pipe Volume Hauling Distance Equipment Specifications Parameter Speed (Loaded) Speed (Empty) Load Capacity Fuel Consumption Loading Bay Width Loading Bay Length Loading Bay Height Loading Bay Volume Capacity (number of Pipes)
441.79 2.25 17.00 17.00 7,510.37 38.25 30.00 Truck with Liting Boom Quantity 40.00 60.00 20.00 10.00 3.00 6.00 2.00 36.00 17.00
Time-Motion Table Activity
Waiting / Maneuvering Loading of Pipes Travel (Loaded) Unloading of Pipes Travel (Empty)
kgs m3 no(s) m kgs m3 km
Rate
Unit km/hr km/hr tons li/hr m m m m3 pcs
Remarks
Time Required hrs
Time Required minutes
7.66 40.00 7.66 60.00
Total Productivity
RC Pipe Hauling
Trial Pipe Set Parameter Pipe Diameter Pipe Length Pipe Weight Pipe Volume (Cube Volume) Quantity of Pipes Total Pipe Length Total Pipe Weight Total Pipe Volume Hauling Distance
0.17 2.22 0.75 2.22 0.50
10.00 133.17 45.00 133.17 30.00
5.86
351.33
2.90 lm/hr
600Ø mm to Hauling Distance: 30.00 km(s)
Quantity
1.00 1.00 196.35 1.00 37.00 37.00 7,264.93 37.00 30.00
Unit m m kgs m3 no(s) m kgs m3 km
1000Ø mm
Remarks
Equipment Specifications Parameter Speed (Loaded) Speed (Empty) Load Capacity Fuel Consumption Loading Bay Width Loading Bay Length Loading Bay Height Loading Bay Volume Capacity (number of Pipes)
Truck with Liting Boom Quantity 40.00 60.00 20.00 10.00 3.00 6.00 2.00 36.00 37.00
Time-Motion Table Activity
Waiting / Maneuvering Loading of Pipes Travel (Loaded) Unloading of Pipes Travel (Empty)
Rate
Unit km/hr km/hr tons li/hr m m m m3 pcs
Remarks
Time Required hrs
Time Required minutes
7.83 40.00 7.83 60.00
Total Productivity
RC Pipe Hauling
Trial Pipe Set Parameter Pipe Diameter Pipe Length Pipe Weight Pipe Volume (Cube Volume) Quantity of Pipes Total Pipe Length Total Pipe Weight Total Pipe Volume Hauling Distance Equipment Specifications Parameter Speed (Loaded) Speed (Empty) Load Capacity Fuel Consumption
0.17 4.73 0.75 4.73 0.50
10.00 283.67 45.00 283.67 30.00
10.87
652.33
3.40 lm/hr
300Ø mm to Hauling Distance: 30.00 km(s)
Quantity
0.50 1.00 49.09 0.25 145.00 145.00 7,117.67 36.25 30.00
Truck with Liting Boom Quantity 40.00 60.00 20.00 10.00
500Ø mm
Unit m m kgs m3 no(s) m kgs m3 km
Remarks
Unit km/hr km/hr tons li/hr
Remarks
Loading Bay Width Loading Bay Length Loading Bay Height Loading Bay Volume Capacity (number of Pipes)
3.00 6.00 2.00 36.00 145.00
Time-Motion Table Activity
Waiting / Maneuvering Loading of Pipes Travel (Loaded) Unloading of Pipes Travel (Empty)
m m m m3 pcs
Time Required hrs
Rate
8.00 40.00 8.00 60.00
Total Productivity
RC Pipe Hauling
Trial Pipe Set Parameter Pipe Diameter Pipe Length Pipe Weight Pipe Volume (Cube Volume) Quantity of Pipes Total Pipe Length Total Pipe Weight Total Pipe Volume Hauling Distance Equipment Specifications Parameter Speed (Loaded) Speed (Empty) Load Capacity Fuel Consumption Loading Bay Width Loading Bay Length Loading Bay Height Loading Bay Volume Capacity (number of Pipes) Time-Motion Table
Time Required minutes
0.17 18.13 0.75 18.13 0.50
10.00 1,087.50 45.00 1,087.50 30.00
37.67
2,260.00
3.85 lm/hr
1600Ø mm to Hauling Distance: 25.00 km(s)
Quantity
2.00 1.00 785.40 4.00 10.00 10.00 7,853.98 40.00 25.00
Truck with Liting Boom Quantity 40.00 60.00 20.00 10.00 3.00 6.00 2.00 36.00 10.00
2000Ø mm
Unit m m kgs m3 no(s) m kgs m3 km
Remarks
Unit km/hr km/hr tons li/hr m m m m3 pcs
Remarks
Activity
Time Required hrs
Rate
Waiting / Maneuvering Loading of Pipes Travel (Loaded) Unloading of Pipes Travel (Empty)
7.50 40.00 7.50 60.00
Total Productivity
Time Required minutes
0.17 1.33 0.63 1.33 0.42
10.00 80.00 37.50 80.00 25.00
3.88
232.50
2.58 lm/hr
RC Pipe Hauling
Trial Pipe Set Parameter Pipe Diameter Pipe Length Pipe Weight Pipe Volume (Cube Volume) Quantity of Pipes Total Pipe Length Total Pipe Weight Total Pipe Volume Hauling Distance Equipment Specifications Parameter Speed (Loaded) Speed (Empty) Load Capacity Fuel Consumption Loading Bay Width Loading Bay Length Loading Bay Height Loading Bay Volume Capacity (number of Pipes)
1200Ø mm to Hauling Distance: 25.00 km(s)
Quantity
Activity
Waiting / Maneuvering Loading of Pipes Travel (Loaded)
Unit m m kgs m3 no(s) m kgs m3 km
Remarks
Unit km/hr km/hr tons li/hr m m m m3 pcs
Remarks
Time Required hrs
Time Required minutes
1.50 1.00 441.79 2.25 17.00 17.00 7,510.37 38.25 25.00
Truck with Liting Boom Quantity 40.00 60.00 20.00 10.00 3.00 6.00 2.00 36.00 17.00
Time-Motion Table Rate
7.66 40.00
1500Ø mm
0.17 2.22 0.63
10.00 133.17 37.50
Unloading of Pipes Travel (Empty)
7.66 60.00
Total Productivity
133.17 25.00
5.65
338.83
3.01 lm/hr
RC Pipe Hauling
Trial Pipe Set Parameter Pipe Diameter Pipe Length Pipe Weight Pipe Volume (Cube Volume) Quantity of Pipes Total Pipe Length Total Pipe Weight Total Pipe Volume Hauling Distance Equipment Specifications Parameter Speed (Loaded) Speed (Empty) Load Capacity Fuel Consumption Loading Bay Width Loading Bay Length Loading Bay Height Loading Bay Volume Capacity (number of Pipes)
600Ø mm to Hauling Distance: 25.00 km(s)
Quantity
Activity
Waiting / Maneuvering Loading of Pipes Travel (Loaded) Unloading of Pipes Travel (Empty) Total
Remarks
Unit km/hr km/hr tons li/hr m m m m3 pcs
Remarks
Time Required hrs
Time Required minutes
Truck with Liting Boom Quantity 40.00 60.00 20.00 10.00 3.00 6.00 2.00 36.00 37.00
Rate
7.83 40.00 7.83 60.00
1000Ø mm
Unit m m kgs m3 no(s) m kgs m3 km
1.00 1.00 196.35 1.00 37.00 37.00 7,264.93 37.00 25.00
Time-Motion Table
Productivity
2.22 0.42
0.17 4.73 0.63 4.73 0.42
10.00 283.67 37.50 283.67 25.00
10.66
639.83
3.47 lm/hr
RC Pipe Hauling
Trial Pipe Set Parameter Pipe Diameter Pipe Length Pipe Weight Pipe Volume (Cube Volume) Quantity of Pipes Total Pipe Length Total Pipe Weight Total Pipe Volume Hauling Distance Equipment Specifications Parameter Speed (Loaded) Speed (Empty) Load Capacity Fuel Consumption Loading Bay Width Loading Bay Length Loading Bay Height Loading Bay Volume Capacity (number of Pipes)
300Ø mm to Hauling Distance: 25.00 km(s)
Quantity
Activity
Waiting / Maneuvering Loading of Pipes Travel (Loaded) Unloading of Pipes Travel (Empty)
Unit m m kgs m3 no(s) m kgs m3 km
Remarks
Unit km/hr km/hr tons li/hr m m m m3 pcs
Remarks
Time Required hrs
Time Required minutes
0.50 1.00 49.09 0.25 145.00 145.00 7,117.67 36.25 25.00
Truck with Liting Boom Quantity 40.00 60.00 20.00 10.00 3.00 6.00 2.00 36.00 145.00
Time-Motion Table Rate
8.00 40.00 8.00 60.00
Total Productivity
RC Pipe Hauling
Trial Pipe Set Parameter Pipe Diameter
500Ø mm
0.17 18.13 0.63 18.13 0.42
10.00 1,087.50 37.50 1,087.50 25.00
37.46
2,247.50
3.87 lm/hr
1600Ø mm to Hauling Distance: 20.00 km(s)
Quantity
2.00
Unit m
2000Ø mm
Remarks
Pipe Length Pipe Weight Pipe Volume (Cube Volume) Quantity of Pipes Total Pipe Length Total Pipe Weight Total Pipe Volume Hauling Distance Equipment Specifications Parameter Speed (Loaded) Speed (Empty) Load Capacity Fuel Consumption Loading Bay Width Loading Bay Length Loading Bay Height Loading Bay Volume Capacity (number of Pipes)
1.00 785.40 4.00 10.00 10.00 7,853.98 40.00 20.00 Truck with Liting Boom Quantity 40.00 60.00 20.00 10.00 3.00 6.00 2.00 36.00 10.00
Time-Motion Table Activity
Waiting / Maneuvering Loading of Pipes Travel (Loaded) Unloading of Pipes Travel (Empty)
m kgs m3 no(s) m kgs m3 km
Rate
Unit km/hr km/hr tons li/hr m m m m3 pcs
Remarks
Time Required hrs
Time Required minutes
7.50 40.00 7.50 60.00
Total Productivity
RC Pipe Hauling
Trial Pipe Set Parameter Pipe Diameter Pipe Length Pipe Weight Pipe Volume (Cube Volume) Quantity of Pipes Total Pipe Length Total Pipe Weight Total Pipe Volume
0.17 1.33 0.50 1.33 0.33
10.00 80.00 30.00 80.00 20.00
3.67
220.00
2.73 lm/hr
1200Ø mm to Hauling Distance: 20.00 km(s)
Quantity
1.50 1.00 441.79 2.25 17.00 17.00 7,510.37 38.25
Unit m m kgs m3 no(s) m kgs m3
1500Ø mm
Remarks
Hauling Distance Equipment Specifications Parameter Speed (Loaded) Speed (Empty) Load Capacity Fuel Consumption Loading Bay Width Loading Bay Length Loading Bay Height Loading Bay Volume Capacity (number of Pipes)
20.00 Truck with Liting Boom Quantity 40.00 60.00 20.00 10.00 3.00 6.00 2.00 36.00 17.00
Time-Motion Table Activity
Waiting / Maneuvering Loading of Pipes Travel (Loaded) Unloading of Pipes Travel (Empty)
km
Rate
Unit km/hr km/hr tons li/hr m m m m3 pcs
Remarks
Time Required hrs
Time Required minutes
7.66 40.00 7.66 60.00
Total Productivity
RC Pipe Hauling
Parameter Parameter Pipe Diameter Pipe Length Pipe Weight Pipe Volume (Cube Volume) Quantity of Pipes Total Pipe Length Total Pipe Weight Total Pipe Volume Hauling Distance Equipment Specifications Parameter Speed (Loaded) Speed (Empty) Load Capacity
0.17 2.22 0.50 2.22 0.33
10.00 133.17 30.00 133.17 20.00
5.44
326.33
3.13 lm/hr
600Ø mm to Hauling Distance: 20.00 km(s) Quantity Quantity
1.00 1.00 196.35 1.00 37.00 37.00 7,264.93 37.00 20.00
Truck with Liting Boom Quantity 40.00 60.00 20.00
1000Ø mm
Unit Unit m m kgs m3 no(s) m kgs m3 km
Remarks Remarks
Unit km/hr km/hr tons
Remarks
Fuel Consumption Loading Bay Width Loading Bay Length Loading Bay Height Loading Bay Volume Capacity (number of Pipes)
10.00 3.00 6.00 2.00 36.00 37.00
Time-Motion Table Activity
Waiting / Maneuvering Loading of Pipes Travel (Loaded) Unloading of Pipes Travel (Empty)
li/hr m m m m3 pcs
Time Required hrs
Rate
7.83 40.00 7.83 60.00
Total Productivity
RC Pipe Hauling
Trial Pipe Set Parameter Pipe Diameter Pipe Length Pipe Weight Pipe Volume (Cube Volume) Quantity of Pipes Total Pipe Length Total Pipe Weight Total Pipe Volume Hauling Distance Equipment Specifications Parameter Speed (Loaded) Speed (Empty) Load Capacity Fuel Consumption Loading Bay Width Loading Bay Length Loading Bay Height Loading Bay Volume Capacity (number of Pipes)
Time Required minutes
0.17 4.73 0.50 4.73 0.33
10.00 283.67 30.00 283.67 20.00
10.46
627.33
3.54 lm/hr
300Ø mm to Hauling Distance: 20.00 km(s)
Quantity
0.50 1.00 49.09 0.25 145.00 145.00 7,117.67 36.25 20.00
Truck with Liting Boom Quantity 40.00 60.00 20.00 10.00 3.00 6.00 2.00 36.00 145.00
500Ø mm
Unit m m kgs m3 no(s) m kgs m3 km
Remarks
Unit km/hr km/hr tons li/hr m m m m3 pcs
Remarks
Time-Motion Table Activity
Time Required hrs
Rate
Waiting / Maneuvering Loading of Pipes Travel (Loaded) Unloading of Pipes Travel (Empty)
8.00 40.00 8.00 60.00
Total Productivity
Time Required minutes
0.17 18.13 0.50 18.13 0.33
10.00 1,087.50 30.00 1,087.50 20.00
37.25
2,235.00
3.89 lm/hr
RC Pipe Hauling
Trial Pipe Set Parameter Pipe Diameter Pipe Length Pipe Weight Pipe Volume (Cube Volume) Quantity of Pipes Total Pipe Length Total Pipe Weight Total Pipe Volume Hauling Distance Equipment Specifications Parameter Speed (Loaded) Speed (Empty) Load Capacity Fuel Consumption Loading Bay Width Loading Bay Length Loading Bay Height Loading Bay Volume Capacity (number of Pipes)
1600Ø mm to Hauling Distance: 15.00 km(s)
Quantity
Activity
Waiting / Maneuvering Loading of Pipes
Unit m m kgs m3 no(s) m kgs m3 km
Remarks
Unit km/hr km/hr tons li/hr m m m m3 pcs
Remarks
Time Required hrs
Time Required minutes
2.00 1.00 785.40 4.00 10.00 10.00 7,853.98 40.00 15.00
Truck with Liting Boom Quantity 40.00 60.00 20.00 10.00 3.00 6.00 2.00 36.00 10.00
Time-Motion Table Rate
7.50
2000Ø mm
0.17 1.33
10.00 80.00
Travel (Loaded) Unloading of Pipes Travel (Empty)
40.00 7.50 60.00
Total Productivity
22.50 80.00 15.00
3.46
207.50
2.89 lm/hr
RC Pipe Hauling
Trial Pipe Set Parameter Pipe Diameter Pipe Length Pipe Weight Pipe Volume (Cube Volume) Quantity of Pipes Total Pipe Length Total Pipe Weight Total Pipe Volume Hauling Distance Equipment Specifications Parameter Speed (Loaded) Speed (Empty) Load Capacity Fuel Consumption Loading Bay Width Loading Bay Length Loading Bay Height Loading Bay Volume Capacity (number of Pipes)
1200Ø mm to Hauling Distance: 15.00 km(s)
Quantity
Activity
Waiting / Maneuvering Loading of Pipes Travel (Loaded) Unloading of Pipes Travel (Empty) Total
Remarks
Unit km/hr km/hr tons li/hr m m m m3 pcs
Remarks
Time Required hrs
Time Required minutes
Truck with Liting Boom Quantity 40.00 60.00 20.00 10.00 3.00 6.00 2.00 36.00 17.00
Rate
7.66 40.00 7.66 60.00
1500Ø mm
Unit m m kgs m3 no(s) m kgs m3 km
1.50 1.00 441.79 2.25 17.00 17.00 7,510.37 38.25 15.00
Time-Motion Table
Productivity
0.38 1.33 0.25
0.17 2.22 0.38 2.22 0.25
10.00 133.17 22.50 133.17 15.00
5.23
313.83
3.25 lm/hr
RC Pipe Hauling
Trial Pipe Set Parameter Pipe Diameter Pipe Length Pipe Weight Pipe Volume (Cube Volume) Quantity of Pipes Total Pipe Length Total Pipe Weight Total Pipe Volume Hauling Distance Equipment Specifications Parameter Speed (Loaded) Speed (Empty) Load Capacity Fuel Consumption Loading Bay Width Loading Bay Length Loading Bay Height Loading Bay Volume Capacity (number of Pipes)
600Ø mm to Hauling Distance: 15.00 km(s)
Quantity
Activity
Waiting / Maneuvering Loading of Pipes Travel (Loaded) Unloading of Pipes Travel (Empty)
Unit m m kgs m3 no(s) m kgs m3 km
Remarks
Unit km/hr km/hr tons li/hr m m m m3 pcs
Remarks
Time Required hrs
Time Required minutes
1.00 1.00 196.35 1.00 37.00 37.00 7,264.93 37.00 15.00
Truck with Liting Boom Quantity 40.00 60.00 20.00 10.00 3.00 6.00 2.00 36.00 37.00
Time-Motion Table Rate
7.83 40.00 7.83 60.00
Total Productivity
RC Pipe Hauling
Trial Pipe Set Parameter
1000Ø mm
0.17 4.73 0.38 4.73 0.25
10.00 283.67 22.50 283.67 15.00
10.25
614.83
3.61 lm/hr
300Ø mm to Hauling Distance: 15.00 km(s)
Quantity
Unit
500Ø mm
Remarks
Pipe Diameter Pipe Length Pipe Weight Pipe Volume (Cube Volume) Quantity of Pipes Total Pipe Length Total Pipe Weight Total Pipe Volume Hauling Distance Equipment Specifications Parameter Speed (Loaded) Speed (Empty) Load Capacity Fuel Consumption Loading Bay Width Loading Bay Length Loading Bay Height Loading Bay Volume Capacity (number of Pipes)
0.50 1.00 49.09 0.25 145.00 145.00 7,117.67 36.25 15.00 Truck with Liting Boom Quantity 40.00 60.00 20.00 10.00 3.00 6.00 2.00 36.00 145.00
Time-Motion Table Activity
Waiting / Maneuvering Loading of Pipes Travel (Loaded) Unloading of Pipes Travel (Empty)
m m kgs m3 no(s) m kgs m3 km
Rate
Unit km/hr km/hr tons li/hr m m m m3 pcs
Remarks
Time Required hrs
Time Required minutes
8.00 40.00 8.00 60.00
Total Productivity
RC Pipe Hauling
Trial Pipe Set Parameter Pipe Diameter Pipe Length Pipe Weight Pipe Volume (Cube Volume) Quantity of Pipes Total Pipe Length Total Pipe Weight
0.17 18.13 0.38 18.13 0.25
10.00 1,087.50 22.50 1,087.50 15.00
37.04
2,222.50
3.91 lm/hr
1600Ø mm to Hauling Distance: 10.00 km(s)
Quantity
2.00 1.00 785.40 4.00 10.00 10.00 7,853.98
Unit m m kgs m3 no(s) m kgs
2000Ø mm
Remarks
Total Pipe Volume Hauling Distance Equipment Specifications Parameter Speed (Loaded) Speed (Empty) Load Capacity Fuel Consumption Loading Bay Width Loading Bay Length Loading Bay Height Loading Bay Volume Capacity (number of Pipes)
40.00 10.00 Truck with Liting Boom Quantity 40.00 60.00 20.00 10.00 3.00 6.00 2.00 36.00 10.00
Time-Motion Table Activity
Waiting / Maneuvering Loading of Pipes Travel (Loaded) Unloading of Pipes Travel (Empty)
m3 km
Rate
Unit km/hr km/hr tons li/hr m m m m3 pcs
Remarks
Time Required hrs
Time Required minutes
7.50 40.00 7.50 60.00
Total Productivity
RC Pipe Hauling
Trial Pipe Set Parameter Pipe Diameter Pipe Length Pipe Weight Pipe Volume (Cube Volume) Quantity of Pipes Total Pipe Length Total Pipe Weight Total Pipe Volume Hauling Distance Equipment Specifications Parameter Speed (Loaded) Speed (Empty)
0.17 1.33 0.25 1.33 0.17
10.00 80.00 15.00 80.00 10.00
3.25
195.00
3.08 lm/hr
1200Ø mm to Hauling Distance: 10.00 km(s)
Quantity
1.50 1.00 441.79 2.25 17.00 17.00 7,510.37 38.25 10.00
Unit m m kgs m3 no(s) m kgs m3 km
Truck with Liting Boom Quantity Unit 40.00 km/hr 60.00 km/hr
1500Ø mm
Remarks
Remarks
Load Capacity Fuel Consumption Loading Bay Width Loading Bay Length Loading Bay Height Loading Bay Volume Capacity (number of Pipes)
20.00 10.00 3.00 6.00 2.00 36.00 17.00
Time-Motion Table Activity
Waiting / Maneuvering Loading of Pipes Travel (Loaded) Unloading of Pipes Travel (Empty)
tons li/hr m m m m3 pcs
Time Required hrs
Rate
7.66 40.00 7.66 60.00
Total Productivity
RC Pipe Hauling
Trial Pipe Set Parameter Pipe Diameter Pipe Length Pipe Weight Pipe Volume (Cube Volume) Quantity of Pipes Total Pipe Length Total Pipe Weight Total Pipe Volume Hauling Distance Equipment Specifications Parameter Speed (Loaded) Speed (Empty) Load Capacity Fuel Consumption Loading Bay Width Loading Bay Length Loading Bay Height Loading Bay Volume Capacity (number of Pipes)
Time Required minutes
0.17 2.22 0.25 2.22 0.17
10.00 133.17 15.00 133.17 10.00
5.02
301.33
3.38 lm/hr
600Ø mm to Hauling Distance: 10.00 km(s)
Quantity
1.00 1.00 196.35 1.00 37.00 37.00 7,264.93 37.00 10.00
Truck with Liting Boom Quantity 40.00 60.00 20.00 10.00 3.00 6.00 2.00 36.00 37.00
1000Ø mm
Unit m m kgs m3 no(s) m kgs m3 km
Remarks
Unit km/hr km/hr tons li/hr m m m m3 pcs
Remarks
Time-Motion Table Activity
Time Required hrs
Rate
Waiting / Maneuvering Loading of Pipes Travel (Loaded) Unloading of Pipes Travel (Empty)
7.83 40.00 7.83 60.00
Total Productivity
Time Required minutes
0.17 4.73 0.25 4.73 0.17
10.00 283.67 15.00 283.67 10.00
10.04
602.33
3.69 lm/hr
RC Pipe Hauling
Trial Pipe Set Parameter Pipe Diameter Pipe Length Pipe Weight Pipe Volume (Cube Volume) Quantity of Pipes Total Pipe Length Total Pipe Weight Total Pipe Volume Hauling Distance Equipment Specifications Parameter Speed (Loaded) Speed (Empty) Load Capacity Fuel Consumption Loading Bay Width Loading Bay Length Loading Bay Height Loading Bay Volume Capacity (number of Pipes)
300Ø mm to Hauling Distance: 10.00 km(s)
Quantity
Activity
Waiting / Maneuvering
Unit m m kgs m3 no(s) m kgs m3 km
Remarks
Unit km/hr km/hr tons li/hr m m m m3 pcs
Remarks
Time Required hrs
Time Required minutes
0.50 1.00 49.09 0.25 145.00 145.00 7,117.67 36.25 10.00
Truck with Liting Boom Quantity 40.00 60.00 20.00 10.00 3.00 6.00 2.00 36.00 145.00
Time-Motion Table Rate
500Ø mm
0.17
10.00
Loading of Pipes Travel (Loaded) Unloading of Pipes Travel (Empty)
8.00 40.00 8.00 60.00
Total Productivity
18.13 0.25 18.13 0.17
1,087.50 15.00 1,087.50 10.00
36.83
2,210.00
3.94 lm/hr
RC Pipe Hauling
Trial Pipe Set Parameter Pipe Diameter Pipe Length Pipe Weight Pipe Volume (Cube Volume) Quantity of Pipes Total Pipe Length Total Pipe Weight Total Pipe Volume Hauling Distance Equipment Specifications Parameter Speed (Loaded) Speed (Empty) Load Capacity Fuel Consumption Loading Bay Width Loading Bay Length Loading Bay Height Loading Bay Volume Capacity (number of Pipes)
1600Ø mm to Hauling Distance: 7.00 km(s)
Quantity
Activity
Waiting / Maneuvering Loading of Pipes Travel (Loaded) Unloading of Pipes Travel (Empty) Total
Unit m m kgs m3 no(s) m kgs m3 km
Remarks
Unit km/hr km/hr tons li/hr m m m m3 pcs
Remarks
Time Required hrs
Time Required minutes
2.00 1.00 785.40 4.00 10.00 10.00 7,853.98 40.00 7.00
Truck with Liting Boom Quantity 40.00 60.00 20.00 10.00 3.00 6.00 2.00 36.00 10.00
Time-Motion Table Rate
7.50 40.00 7.50 60.00
2000Ø mm
0.17 1.33 0.18 1.33 0.12
10.00 80.00 10.50 80.00 7.00
3.13
187.50
Productivity
3.20 lm/hr
RC Pipe Hauling
Trial Pipe Set Parameter Pipe Diameter Pipe Length Pipe Weight Pipe Volume (Cube Volume) Quantity of Pipes Total Pipe Length Total Pipe Weight Total Pipe Volume Hauling Distance Equipment Specifications Parameter Speed (Loaded) Speed (Empty) Load Capacity Fuel Consumption Loading Bay Width Loading Bay Length Loading Bay Height Loading Bay Volume Capacity (number of Pipes)
1200Ø mm to Hauling Distance: 7.00 km(s)
Quantity
Activity
Waiting / Maneuvering Loading of Pipes Travel (Loaded) Unloading of Pipes Travel (Empty) Total Productivity
RC Pipe Hauling
Trial Pipe Set
Unit m m kgs m3 no(s) m kgs m3 km
Remarks
Unit km/hr km/hr tons li/hr m m m m3 pcs
Remarks
Time Required hrs
Time Required minutes
1.50 1.00 441.79 2.25 17.00 17.00 7,510.37 38.25 7.00
Truck with Liting Boom Quantity 40.00 60.00 20.00 10.00 3.00 6.00 2.00 36.00 17.00
Time-Motion Table Rate
7.66 40.00 7.66 60.00
1500Ø mm
0.17 2.22 0.18 2.22 0.12
10.00 133.17 10.50 133.17 7.00
4.90
293.83
3.47 lm/hr
600Ø mm to Hauling Distance: 7.00 km(s)
1000Ø mm
Parameter Pipe Diameter Pipe Length Pipe Weight Pipe Volume (Cube Volume) Quantity of Pipes Total Pipe Length Total Pipe Weight Total Pipe Volume Hauling Distance Equipment Specifications Parameter Speed (Loaded) Speed (Empty) Load Capacity Fuel Consumption Loading Bay Width Loading Bay Length Loading Bay Height Loading Bay Volume Capacity (number of Pipes)
Quantity
Waiting / Maneuvering Loading of Pipes Travel (Loaded) Unloading of Pipes Travel (Empty)
Remarks
Unit km/hr km/hr tons li/hr m m m m3 pcs
Remarks
Time Required hrs
Time Required minutes
Truck with Liting Boom Quantity 40.00 60.00 20.00 10.00 3.00 6.00 2.00 36.00 37.00
Time-Motion Table Activity
Unit m m kgs m3 no(s) m kgs m3 km
1.00 1.00 196.35 1.00 37.00 37.00 7,264.93 37.00 7.00
Rate
7.83 40.00 7.83 60.00
Total Productivity
RC Pipe Hauling
Trial Pipe Set Parameter Pipe Diameter Pipe Length Pipe Weight Pipe Volume (Cube Volume) Quantity of Pipes Total Pipe Length
0.17 4.73 0.18 4.73 0.12
10.00 283.67 10.50 283.67 7.00
9.91
594.83
3.73 lm/hr
300Ø mm to Hauling Distance: 7.00 km(s)
Quantity
0.50 1.00 49.09 0.25 145.00 145.00
Unit m m kgs m3 no(s) m
500Ø mm
Remarks
Total Pipe Weight Total Pipe Volume Hauling Distance Equipment Specifications Parameter Speed (Loaded) Speed (Empty) Load Capacity Fuel Consumption Loading Bay Width Loading Bay Length Loading Bay Height Loading Bay Volume Capacity (number of Pipes)
7,117.67 36.25 7.00 Truck with Liting Boom Quantity 40.00 60.00 20.00 10.00 3.00 6.00 2.00 36.00 145.00
Time-Motion Table Activity
Waiting / Maneuvering Loading of Pipes Travel (Loaded) Unloading of Pipes Travel (Empty)
kgs m3 km
Rate
Unit km/hr km/hr tons li/hr m m m m3 pcs
Remarks
Time Required hrs
Time Required minutes
8.00 40.00 8.00 60.00
Total Productivity
RC Pipe Hauling
Trial Pipe Set Parameter Pipe Diameter Pipe Length Pipe Weight Pipe Volume (Cube Volume) Quantity of Pipes Total Pipe Length Total Pipe Weight Total Pipe Volume Hauling Distance Equipment Specifications Parameter Speed (Loaded)
0.17 18.13 0.18 18.13 0.12
10.00 1,087.50 10.50 1,087.50 7.00
36.71
2,202.50
3.95 lm/hr
1600Ø mm to Hauling Distance: 5.00 km(s)
Quantity
2.00 1.00 785.40 4.00 10.00 10.00 7,853.98 40.00 5.00
Unit m m kgs m3 no(s) m kgs m3 km
Truck with Liting Boom Quantity Unit 40.00 km/hr
2000Ø mm
Remarks
Remarks
Speed (Empty) Load Capacity Fuel Consumption Loading Bay Width Loading Bay Length Loading Bay Height Loading Bay Volume Capacity (number of Pipes)
60.00 20.00 10.00 3.00 6.00 2.00 36.00 10.00
Time-Motion Table Activity
Waiting / Maneuvering Loading of Pipes Travel (Loaded) Unloading of Pipes Travel (Empty)
km/hr tons li/hr m m m m3 pcs
Time Required hrs
Rate
7.50 40.00 7.50 60.00
Total Productivity
RC Pipe Hauling
Trial Pipe Set Parameter Pipe Diameter Pipe Length Pipe Weight Pipe Volume (Cube Volume) Quantity of Pipes Total Pipe Length Total Pipe Weight Total Pipe Volume Hauling Distance Equipment Specifications Parameter Speed (Loaded) Speed (Empty) Load Capacity Fuel Consumption Loading Bay Width Loading Bay Length Loading Bay Height Loading Bay Volume
Time Required minutes
0.17 1.33 0.13 1.33 0.08
10.00 80.00 7.50 80.00 5.00
3.04
182.50
3.29 lm/hr
1200Ø mm to Hauling Distance: 5.00 km(s)
Quantity
1.50 1.00 441.79 2.25 17.00 17.00 7,510.37 38.25 5.00
Truck with Liting Boom Quantity 40.00 60.00 20.00 10.00 3.00 6.00 2.00 36.00
1500Ø mm
Unit m m kgs m3 no(s) m kgs m3 km
Remarks
Unit km/hr km/hr tons li/hr m m m m3
Remarks
Capacity (number of Pipes)
17.00
Time-Motion Table Activity
Time Required hrs
Rate
Waiting / Maneuvering Loading of Pipes Travel (Loaded) Unloading of Pipes Travel (Empty)
pcs
7.66 40.00 7.66 60.00
Total Productivity
Time Required minutes
0.17 2.22 0.13 2.22 0.08
10.00 133.17 7.50 133.17 5.00
4.81
288.83
3.53 lm/hr
RC Pipe Hauling
Trial Pipe Set Parameter Pipe Diameter Pipe Length Pipe Weight Pipe Volume (Cube Volume) Quantity of Pipes Total Pipe Length Total Pipe Weight Total Pipe Volume Hauling Distance Equipment Specifications Parameter Speed (Loaded) Speed (Empty) Load Capacity Fuel Consumption Loading Bay Width Loading Bay Length Loading Bay Height Loading Bay Volume Capacity (number of Pipes)
600Ø mm to Hauling Distance: 5.00 km(s)
Quantity
Activity
Unit m m kgs m3 no(s) m kgs m3 km
Remarks
Unit km/hr km/hr tons li/hr m m m m3 pcs
Remarks
Time Required hrs
Time Required minutes
1.00 1.00 196.35 1.00 37.00 37.00 7,264.93 37.00 5.00
Truck with Liting Boom Quantity 40.00 60.00 20.00 10.00 3.00 6.00 2.00 36.00 37.00
Time-Motion Table Rate
1000Ø mm
Waiting / Maneuvering Loading of Pipes Travel (Loaded) Unloading of Pipes Travel (Empty)
7.83 40.00 7.83 60.00
Total Productivity
0.17 4.73 0.13 4.73 0.08
10.00 283.67 7.50 283.67 5.00
9.83
589.83
3.76 lm/hr
RC Pipe Hauling
Trial Pipe Set Parameter Pipe Diameter Pipe Length Pipe Weight Pipe Volume (Cube Volume) Quantity of Pipes Total Pipe Length Total Pipe Weight Total Pipe Volume Hauling Distance Equipment Specifications Parameter Speed (Loaded) Speed (Empty) Load Capacity Fuel Consumption Loading Bay Width Loading Bay Length Loading Bay Height Loading Bay Volume Capacity (number of Pipes)
300Ø mm to Hauling Distance: 5.00 km(s)
Quantity
Activity
Waiting / Maneuvering Loading of Pipes Travel (Loaded) Unloading of Pipes Travel (Empty) Total
Unit m m kgs m3 no(s) m kgs m3 km
Remarks
Unit km/hr km/hr tons li/hr m m m m3 pcs
Remarks
Time Required hrs
Time Required minutes
0.50 1.00 49.09 0.25 145.00 145.00 7,117.67 36.25 5.00
Truck with Liting Boom Quantity 40.00 60.00 20.00 10.00 3.00 6.00 2.00 36.00 145.00
Time-Motion Table Rate
8.00 40.00 8.00 60.00
500Ø mm
0.17 18.13 0.13 18.13 0.08
10.00 1,087.50 7.50 1,087.50 5.00
36.63
2,197.50
Productivity
3.96 lm/hr
PRODUCTIVITY CALCULATIONS Concreting Concreting by Crane and Bucket Equipment Specifications Parameter Forward Speed Reverse Speed Capacity Bucket Capacity Fuel Consumption
Crane 25 Tons with 0.5 m3 Bucket Quantity Unit 40.00 km/hr 10.00 km/hr 25.00 tons 0.50 m3 10.00 li/hr
Time-Motion Table Activity
Maneuver Swing Boom w/ Empty Bucket Load Concrete Swing Boom w/ Loaded Bucket Unload Concrete Swing Boom w/ Empty Bucket Load Concrete Swing Boom w/ Loaded Bucket Unload Concrete Swing Boom w/ Empty Bucket Load Concrete Swing Boom w/ Loaded Bucket Unload Concrete Swing Boom w/ Empty Bucket Load Concrete Swing Boom w/ Loaded Bucket Unload Concrete Swing Boom w/ Empty Bucket Load Concrete Swing Boom w/ Loaded Bucket Unload Concrete Swing Boom w/ Empty Bucket Load Concrete Swing Boom w/ Loaded Bucket Unload Concrete Swing Boom w/ Empty Bucket Load Concrete Swing Boom w/ Loaded Bucket Unload Concrete Swing Boom w/ Empty Bucket
Rate
Volume = Time Required hrs
8.00 cu.m. Time Required minutes
0.08 0.01 0.02 0.01 0.05 0.01 0.02 0.01 0.05 0.01 0.02 0.01 0.05 0.01 0.02 0.01 0.05 0.01 0.02 0.01 0.05 0.01 0.02 0.01 0.05 0.01 0.02 0.01 0.05 0.01
5.00 0.33 1.00 0.75 3.00 0.33 1.00 0.75 3.00 0.33 1.00 0.75 3.00 0.33 1.00 0.75 3.00 0.33 1.00 0.75 3.00 0.33 1.00 0.75 3.00 0.33 1.00 0.75 3.00 0.33
Load Concrete Swing Boom w/ Loaded Bucket Unload Concrete Swing Boom w/ Empty Bucket Load Concrete Swing Boom w/ Loaded Bucket Unload Concrete Swing Boom w/ Empty Bucket Load Concrete Swing Boom w/ Loaded Bucket Unload Concrete Swing Boom w/ Empty Bucket Load Concrete Swing Boom w/ Loaded Bucket Unload Concrete Swing Boom w/ Empty Bucket Load Concrete Swing Boom w/ Loaded Bucket Unload Concrete Swing Boom w/ Empty Bucket Load Concrete Swing Boom w/ Loaded Bucket Unload Concrete Swing Boom w/ Empty Bucket Load Concrete Swing Boom w/ Loaded Bucket Unload Concrete Swing Boom w/ Empty Bucket Load Concrete Swing Boom w/ Loaded Bucket Unload Concrete Swing Boom w/ Empty Bucket Load Concrete Swing Boom w/ Loaded Bucket Unload Concrete
Total Productivity
1.00 0.75 3.00 0.33 1.00 0.75 3.00 0.33 1.00 0.75 3.00 0.33 1.00 0.75 3.00 0.33 1.00 0.75 3.00 0.33 1.00 0.75 3.00 0.33 1.00 0.75 3.00 0.33 1.00 0.75 3.00 0.33 1.00 0.75 3.00
1.44
86.33
5.56 m3/hr
Concreting by Truck-Mounted Concrete Pump Equipment Specifications Parameter Forward Speed Reverse Speed Pump Rate Fuel Consumption
0.02 0.01 0.05 0.01 0.02 0.01 0.05 0.01 0.02 0.01 0.05 0.01 0.02 0.01 0.05 0.01 0.02 0.01 0.05 0.01 0.02 0.01 0.05 0.01 0.02 0.01 0.05 0.01 0.02 0.01 0.05 0.01 0.02 0.01 0.05
Truck-mounted Concrete Quantity Unit 60.00 km/hr 10.00 km/hr 50.00 m3/hr 10.00 li/hr
Time-Motion Table Activity
Maneuver / Set-up Extend / Swing / Position Boom Prime / Grout Pump Pre-load Pump Pump Concrete (Mixer 1) Wait / Reposition Boom Pump Concrete (Mixer 2) Wait / Reposition Boom Pump Concrete (Mixer 3) Wait / Reposition Boom Pump Concrete (Mixer 4) Wait / Reposition Boom Pump Concrete (Mixer 5) Wait / Reposition Boom Pump Concrete (Mixer 6) Wait / Reposition Boom Pump Concrete (Mixer 7) Wait / Reposition Boom Pump Concrete (Mixer 8) Wait / Reposition Boom Pump Concrete (Mixer 9) Wait / Reposition Boom Pump Concrete (Mixer 10) Wait / Reposition Boom Clean-up Swing / Retract Boom
Total Productivity
Rate
50.00 50.00 50.00 50.00 50.00 50.00 50.00 50.00 50.00 50.00
Volume = Time Required hrs
80.00 cu.m. Time Required minutes
0.25 0.17 0.17 0.03 0.16 0.08 0.16 0.08 0.16 0.08 0.16 0.08 0.16 0.08 0.16 0.08 0.16 0.08 0.16 0.08 0.16 0.08 0.16 0.08 0.25 0.08
15.00 10.00 10.00 2.00 9.60 5.00 9.60 5.00 9.60 5.00 9.60 5.00 9.60 5.00 9.60 5.00 9.60 5.00 9.60 5.00 9.60 5.00 9.60 5.00 15.00 5.00
3.38
203.00
23.65 m3/hr
PRODUCTIVITY CALCULATIONS
MATERIALS HANDLING MATERIALS LOADING/UNLOADING REBAR LOADING/UNLOADING Load Assumptions Parameter Weight per Bundle Maximum Truck Capacity Total Number of Bundles Equipment Specifications Parameter Forward Speed Reverse Speed Lifting Capacity Fuel Consumption Swing-Hoist Up-Swing-Hoist Down
Quantity 2,500.00 20,000.00 8.00
Unit kgs kgs bundles
Remarks
Crane 25.00 Tons Quantity 2.00 2.00 25.00 27.00 120.00
Unit km/hr km/hr tons li/hr secs
Remarks
Rate
Time Required hrs
Time Required minutes
Time-Motion Table Activity
Equipment Set-up / Waiting Set-up / Waiting / Maneuvering Loading/Unloading Tie/Rig Bundle Swing-Hoist Up-Swing-Hoist Down Unrig Bundle Misc. Waiting
120.00
Loading/Unloading Cycle Total Productivity
0.33
20.00
0.05 0.03 0.05 0.02
3.00 2.00 3.00 1.00
1.05
63.00
1.53
92.00
13.04 ton(s)/hr
FORMWORKS LOADING / UNLOADING Load Assumptions Parameter Weight per Load/Lift Volume per Load/Lift Area / Load Maximum Truck Capacity (Weight)
Quantity 1,235.50 3.65 28.80 10,000.00
Unit kgs m3 m2 kgs
Remarks
Maximum Truck Capacity (Volume) Total Number of Loads/Lifts Total Area
15.00 4.00 115.20
m3 loads/lifts m2
Equipment Specifications Parameter Forward Speed Reverse Speed Lifting Capacity Fuel Consumption Swing-Hoist Up-Swing-Hoist Down
Crane 25.00 Tons Quantity 2.00 2.00 25.00 27.00 120.00
Unit km/hr km/hr tons li/hr secs
Remarks
Rate
Time Required hrs
Time Required minutes
Time-Motion Table Activity
Equipment Set-up / Waiting Set-up / Waiting / Maneuvering Loading/Unloading Tie/Rig Load Swing-Hoist Up-Swing-Hoist Down Unrig Load Misc. Waiting
120.00
Loading/Unloading Cycle Total Productivity
0.33
20.00
0.08 0.03 0.08 0.02
5.00 2.00 5.00 1.00
0.65
39.00
1.20
72.00
96.00 m2/hr
MATERIALS HAULING REINFORCING BAR HAULING Equipment Specifications Parameter Loaded Speed Empty Speed Load Capacity (Weight) Fuel Consumption
Flat Bed Truck Quantity 35.00 40.00 20,000.00 15.00
AHD = Time-Motion Table
5.000 km(s)
Activity
Rate
Unit km/hr km/hr kgs. li/hr
###
Time Required hrs
Time Required minutes
Maneuver & Wait Wait While Loading Travel (Loaded) Wait While Unloading Travel (Empty)
13.04 ton(s)/hr 35.00 13.04 ton(s)/hr 40.00
Total Productivity
AHD= 5.000 km(s)
AHD = Time-Motion Table Activity
Maneuver & Wait Wait While Loading Travel (Loaded) Wait While Unloading Travel (Empty)
Rate
13.04 ton(s)/hr 35.00 13.04 ton(s)/hr 40.00
AHD= 7.000 km(s)
AHD = Time-Motion Table Activity
Maneuver & Wait Wait While Loading Travel (Loaded) Wait While Unloading Travel (Empty)
Rate
13.04 ton(s)/hr 35.00 13.04 ton(s)/hr 40.00
AHD= 10.000 km(s)
AHD = Time-Motion Table Activity
3.42
205.07
5.85 ton(s)/hr
Time Required hrs
Time Required minutes
0.08 1.53 0.20 1.53 0.18
5.00 92.00 12.00 92.00 10.50
3.53
211.50
5.67 ton(s)/hr
10.000 km(s)
Total Productivity
5.00 92.00 8.57 92.00 7.50
7.000 km(s)
Total Productivity
0.08 1.53 0.14 1.53 0.13
Time Required hrs
Time Required minutes
0.08 1.53 0.29 1.53 0.25
5.00 92.00 17.14 92.00 15.00
3.69
221.14
5.43 ton(s)/hr
15.000 km(s)
Rate
Time Required hrs
Time Required minutes
Activity
Maneuver & Wait Wait While Loading Travel (Loaded) Wait While Unloading Travel (Empty)
Rate
13.04 ton(s)/hr 35.00 13.04 ton(s)/hr 40.00
Total Productivity
AHD= 15.000 km(s)
AHD = Time-Motion Table Activity
Maneuver & Wait Wait While Loading Travel (Loaded) Wait While Unloading Travel (Empty)
Rate
13.04 ton(s)/hr 35.00 13.04 ton(s)/hr 40.00
AHD= 20.000 km(s)
AHD = Time-Motion Table Activity
Maneuver & Wait Wait While Loading Travel (Loaded) Wait While Unloading Travel (Empty)
Rate
13.04 ton(s)/hr 35.00 13.04 ton(s)/hr 40.00
AHD= 25.000 km(s)
AHD = Time-Motion Table Activity
3.95
237.21
5.06 ton(s)/hr
Time Required hrs
Time Required minutes
0.08 1.53 0.57 1.53 0.50
5.00 92.00 34.29 92.00 30.00
4.22
253.29
4.74 ton(s)/hr
25.000 km(s)
Total Productivity
5.00 92.00 25.71 92.00 22.50
20.000 km(s)
Total Productivity
0.08 1.53 0.43 1.53 0.38
Time Required hrs
Time Required minutes
0.08 1.53 0.71 1.53 0.63
5.00 92.00 42.86 92.00 37.50
4.49
269.36
4.46 ton(s)/hr
30.000 km(s)
Rate
Time Required
Time Required
Activity
Maneuver & Wait Wait While Loading Travel (Loaded) Wait While Unloading Travel (Empty)
Rate
hrs
13.04 ton(s)/hr 35.00 13.04 ton(s)/hr 40.00
Total Productivity
minutes
0.08 1.53 0.86 1.53 0.75
5.00 92.00 51.43 92.00 45.00
4.76
285.43
4.20 ton(s)/hr
AHD= 30.000 km(s)
FORMWORKS HAULING Equipment Specifications Parameter Loaded Speed Empty Speed Load Capacity (Form Area) Load Capacity (Weight) Fuel Consumption
Cargo Truck Quantity 40.00 60.00 115.20 4,941.99 15.00
AHD = Time-Motion Table
5.000 km(s)
Activity
96.00 40.00 96.00 60.00
Total Productivity
AHD= 5.000 km(s)
AHD = Time-Motion Table Activity
Maneuver & Wait Wait While Loading Travel (Loaded)
###
Time Required hrs
Rate
Maneuver & Wait Wait While Loading Travel (Loaded) Wait While Unloading Travel (Empty)
Unit km/hr km/hr m2 kgs. li/hr
Time Required minutes
0.08 1.20 0.13 1.20 0.08
5.00 72.00 7.50 72.00 5.00
2.69
161.50
42.80 m2/hr
7.000 km(s) Time Required hrs
Rate
96.00 40.00
0.08 1.20 0.18
Time Required minutes
5.00 72.00 10.50
Wait While Unloading Travel (Empty)
96.00 60.00
Total Productivity
AHD= 7.000 km(s)
AHD = Time-Motion Table Activity
96.00 40.00 96.00 60.00
AHD= 10.000 km(s)
Activity
96.00 40.00 96.00 60.00
AHD= 15.000 km(s)
Activity
Maneuver & Wait Wait While Loading
41.51 m2/hr
Time Required minutes
0.08 1.20 0.35 1.20 0.17
5.00 72.00 21.08 72.00 10.00
3.00
180.08
38.38 m2/hr
Time Required hrs
Rate
Total
AHD = Time-Motion Table
166.50
15.000 km(s)
Maneuver & Wait Wait While Loading Travel (Loaded) Wait While Unloading Travel (Empty)
Productivity
2.78
Time Required hrs
Rate
Total
AHD = Time-Motion Table
72.00 7.00
10.000 km(s)
Maneuver & Wait Wait While Loading Travel (Loaded) Wait While Unloading Travel (Empty)
Productivity
1.20 0.12
Time Required minutes
0.08 1.20 0.38 1.20 0.25
5.00 72.00 22.50 72.00 15.00
3.11
186.50
37.06 m2/hr
20.000 km(s) Time Required hrs
Rate
96.00
0.08 1.20
Time Required minutes
5.00 72.00
Travel (Loaded) Wait While Unloading Travel (Empty)
40.00 96.00 60.00
Total Productivity
Activity
Rate
96.00 40.00 96.00 60.00
Maneuver & Wait Wait While Loading Travel (Loaded) Wait While Unloading Travel (Empty)
0.08 1.20 0.63 1.20 0.42
5.00 72.00 37.50 72.00 25.00
3.53
211.50
30.000 km(s) Time Required hrs
Rate
96.00 40.00 96.00 60.00
Total Productivity
5.00 72.00 45.00 72.00 30.00
3.73
224.00
30.86 m2/hr
AHD= 30.000 km(s)
Cargo Truck Quantity 40.00 60.00 15,000.00
Time Required minutes
0.08 1.20 0.75 1.20 0.50
CEMENT (IN BAGS) HAULING Equipment Specifications Parameter Loaded Speed Empty Speed Load Capacity (Weight)
Time Required minutes
32.68 m2/hr
AHD= 25.000 km(s)
Activity
199.00
Time Required hrs
Total
AHD = Time-Motion Table
3.32
25.000 km(s)
Maneuver & Wait Wait While Loading Travel (Loaded) Wait While Unloading Travel (Empty)
Productivity
30.00 72.00 20.00
34.73 m2/hr
AHD= 20.000 km(s)
AHD = Time-Motion Table
0.50 1.20 0.33
Unit km/hr km/hr kgs.
###
Load Capacity (Bags) Fuel Consumption
375.00 15.00
kgs. li/hr
Cement Loading / Unloading Rate
109.76
bags/hr
AHD = Time-Motion Table Activity
Maneuver & Wait Wait While Loading Travel (Loaded) Wait While Unloading Travel (Empty)
5.000 km(s)
Rate
109.76 40.00 109.76 60.00
Total Productivity
AHD= 5.000 km(s)
AHD = Time-Motion Table Activity
Maneuver & Wait Wait While Loading Travel (Loaded) Wait While Unloading Travel (Empty)
Rate
109.76 40.00 109.76 60.00
AHD= 7.000 km(s)
AHD = Time-Motion Table Activity
Maneuver & Wait Wait While Loading Travel (Loaded) Wait While Unloading Travel (Empty)
Time Required hrs
Time Required minutes
0.08 3.42 0.13 3.42 0.08
5.00 205.00 7.50 205.00 5.00
7.13
427.50
52.63 bags/hr
7.000 km(s)
Total Productivity
Refer to Labor Productivity
Time Required hrs
Time Required minutes
0.08 3.42 0.18 3.42 0.12
5.00 205.00 10.50 205.00 7.00
7.21
432.50
52.02 bags/hr
10.000 km(s)
Rate
109.76 40.00 109.76 60.00
Time Required hrs
0.08 3.42 0.25 3.42 0.17
Time Required minutes
5.00 205.00 15.00 205.00 10.00
Total Productivity
7.33 AHD= 10.000 km(s)
AHD = Time-Motion Table Activity
Maneuver & Wait Wait While Loading Travel (Loaded) Wait While Unloading Travel (Empty)
Rate
109.76 40.00 109.76 60.00
AHD= 15.000 km(s)
AHD = Time-Motion Table Activity
Maneuver & Wait Wait While Loading Travel (Loaded) Wait While Unloading Travel (Empty)
Rate
109.76 40.00 109.76 60.00
AHD= 20.000 km(s)
AHD = Time-Motion Table Activity
Maneuver & Wait Wait While Loading Travel (Loaded) Wait While Unloading
Time Required hrs
Time Required minutes
0.08 3.42 0.38 3.42 0.25
5.00 205.00 22.50 205.00 15.00
7.54
452.50
49.72 bags/hr
20.000 km(s)
Total Productivity
51.14 bags/hr
15.000 km(s)
Total Productivity
440.00
Time Required hrs
Time Required minutes
0.08 3.42 0.50 3.42 0.33
5.00 205.00 30.00 205.00 20.00
7.75
465.00
48.39 bags/hr
25.000 km(s)
Rate
109.76 40.00 109.76
Time Required hrs
0.08 3.42 0.63 3.42
Time Required minutes
5.00 205.00 37.50 205.00
Travel (Empty)
60.00 Total
Productivity
AHD= 25.000 km(s)
AHD = Time-Motion Table Activity
Maneuver & Wait Wait While Loading Travel (Loaded) Wait While Unloading Travel (Empty)
25.00
7.96
477.50
47.12 bags/hr
30.000 km(s)
Rate
109.76 40.00 109.76 60.00
Total Productivity
0.42
AHD= 30.000 km(s)
Time Required hrs
Time Required minutes
0.08 3.42 0.75 3.42 0.50
5.00 205.00 45.00 205.00 30.00
8.17
490.00
45.92 bags/hr
Material Plywood Timber/Wood Scaffolds
Dimension 2.4mx1.2mx12mm 100mm x 50mm x 6m 1500mm x 1200mm
Unit Weight 300 kg/m3 500 kg/m3 7850 kg/m3
For Columns / Walls: Plywood Timber/Wood Scaffolds
1 m2 10.4 lm 0 pcs
10.4
For Slab Plywood Timber/Wood Scaffolds
1 m2 9 lm 2 pcs
9 2
to Labor Productivity
Volume / Pc. 0.03 cu.m. 0.03 cu.m. 0.09 cu.m.
Weight / Pc. 10.37 kgs 15.00 kgs 19.09 kgs
No. of Pcs. Total Volume 10 0.35 cu.m. 50 1.5 cu.m. 20 1.8 cu.m. Total 3.65 cu.m.
Total Weight 103.68 kgs 750.00 kgs 381.82 kgs 1235.50 kgs
Total Area 28.80 sq.m.
28.80 kgs
lm/m
2
lm/m pcs/m2 2
0.01 m3/m2 0.05 m3/m2
3.60 kgs/m2 26.00 kgs/m2
Total
29.60 kgs/m2
0.01 m3/m2 0.05 m3/m2 0.18 m3/m2 Total
3.60 22.50 38.18 64.28
kgs/m2 kgs/m2 kgs/m2 kgs/m2
0.42 5.00
0.42 4.00 2.00
Remarks
pc pcs/pc of plywood
USE
pc pcs/pc of plywood pcs/pc of plywood
USE
PRODUCTIVITY CALCULATIONS Concrete Paving Concrete Paving t = 230.00 mm Equipment Specifications Parameter Forward Speed Reverse Speed Capacity (area/pass) Screed Width Boom Speed Trial Strip
Parameter Pavement Length Pavement Width Pavement Thickness Area of Pavement Volume No of Setups / Positions
Somero 160 - Concrete Paver/Finisher Quantity Unit 6.10 km/hr 3.00 km/hr 14.90 m2/pass 2.44 m 108.00 m/hr
Quantity 30.00 3.65 230.00 109.50 25.19 13.00
Time-Motion Table Activity
Rate
Mobilization / Setup / Wait Move Forward Extend Boom Lower Boom / Adjust Retract Boom / Pave Concrete Raise Boom / Adjust Move Forward Extend Boom Lower Boom / Adjust Retract Boom / Pave Concrete Raise Boom / Adjust Move Forward Extend Boom Lower Boom / Adjust Retract Boom / Pave Concrete Raise Boom / Adjust Move Forward Extend Boom Lower Boom / Adjust Retract Boom / Pave Concrete
6.10 108.00 81.00 6.10 108.00 81.00 6.10 108.00 81.00 6.10 108.00 81.00
Unit m m mm m2 m3
Volume = Time Required hrs
25.19 cu.m. Time Required minutes
0.67
40.00
0.00 0.03 0.01 0.05 0.01 0.00 0.03 0.01 0.05 0.01 0.00 0.03 0.01 0.05 0.01 0.00 0.03 0.01 0.05
0.02 2.03 0.50 2.70 0.50 0.02 2.03 0.50 2.70 0.50 0.02 2.03 0.50 2.70 0.50 0.02 2.03 0.50 2.70
Raise Boom / Adjust Move Forward Extend Boom Lower Boom / Adjust Retract Boom / Pave Concrete Raise Boom / Adjust Move Forward Extend Boom Lower Boom / Adjust Retract Boom / Pave Concrete Raise Boom / Adjust Move Forward Extend Boom Lower Boom / Adjust Retract Boom / Pave Concrete Raise Boom / Adjust Move Forward Extend Boom Lower Boom / Adjust Retract Boom / Pave Concrete Raise Boom / Adjust Move Forward Extend Boom Lower Boom / Adjust Retract Boom / Pave Concrete Raise Boom / Adjust Move Forward Extend Boom Lower Boom / Adjust Retract Boom / Pave Concrete Raise Boom / Adjust Move Forward Extend Boom Lower Boom / Adjust Retract Boom / Pave Concrete Raise Boom / Adjust Move Forward Extend Boom Lower Boom / Adjust Retract Boom / Pave Concrete Raise Boom / Adjust Move Forward Extend Boom Lower Boom / Adjust Retract Boom / Pave Concrete Raise Boom / Adjust
6.10 108.00 81.00 6.10 108.00 81.00 6.10 108.00 81.00 6.10 108.00 81.00 6.10 108.00 81.00 6.10 108.00 81.00 6.10 108.00 81.00 6.10 108.00 81.00 6.10 108.00 81.00 0 0 0 0
-
0.01 0.00 0.03 0.01 0.05 0.01 0.00 0.03 0.01 0.05 0.01 0.00 0.03 0.01 0.05 0.01 0.00 0.03 0.01 0.05 0.01 0.00 0.03 0.01 0.05 0.01 0.00 0.03 0.01 0.05 0.01 0.00 0.03 0.01 0.05 0.01 0.00 0.03 0.01 0.05 0.01 0.00 0.03 0.01 0.05 0.01 -
0.50 0.02 2.03 0.50 2.70 0.50 0.02 2.03 0.50 2.70 0.50 0.02 2.03 0.50 2.70 0.50 0.02 2.03 0.50 2.70 0.50 0.02 2.03 0.50 2.70 0.50 0.02 2.03 0.50 2.70 0.50 0.02 2.03 0.50 2.70 0.50 0.02 2.03 0.50 2.70 0.50 0.02 2.03 0.50 2.70 0.50 -
0 0 0 0 0 0
-
-
Cleanup / Demobilization Total
-
0.67
40.00
2.58
154.82
Productivity
9.76 m3/hr
Productivity
42.44 m2/hr
Concrete Paving t = 270.00 mm Equipment Specifications Parameter Forward Speed Reverse Speed Capacity (area/pass) Screed Width Boom Speed Trial Strip
Parameter Pavement Length Pavement Width Pavement Thickness Area of Pavement Volume No of Setups / Positions
Somero 160 - Concrete Paver/Finisher Quantity Unit 6.10 km/hr 3.00 km/hr 14.90 m2/pass 2.44 m 90.00 m/hr
Quantity 30.00 3.65 270.00 109.50 29.57 13.00
Time-Motion Table Activity
Rate
Mobilization / Setup / Wait Move Forward Extend Boom Lower Boom / Adjust Retract Boom / Pave Concrete Raise Boom / Adjust
6.10 90.00 81.00
Unit m m mm m2 m3
Volume = Time Required hrs
29.57 cu.m. Time Required minutes
0.67
40.00
0.00 0.04 0.01 0.05 0.01
0.02 2.43 0.50 2.70 0.50
Move Forward Extend Boom Lower Boom / Adjust Retract Boom / Pave Concrete Raise Boom / Adjust Move Forward Extend Boom Lower Boom / Adjust Retract Boom / Pave Concrete Raise Boom / Adjust Move Forward Extend Boom Lower Boom / Adjust Retract Boom / Pave Concrete Raise Boom / Adjust Move Forward Extend Boom Lower Boom / Adjust Retract Boom / Pave Concrete Raise Boom / Adjust Move Forward Extend Boom Lower Boom / Adjust Retract Boom / Pave Concrete Raise Boom / Adjust Move Forward Extend Boom Lower Boom / Adjust Retract Boom / Pave Concrete Raise Boom / Adjust Move Forward Extend Boom Lower Boom / Adjust Retract Boom / Pave Concrete Raise Boom / Adjust Move Forward Extend Boom Lower Boom / Adjust Retract Boom / Pave Concrete Raise Boom / Adjust Move Forward Extend Boom Lower Boom / Adjust Retract Boom / Pave Concrete Raise Boom / Adjust Move Forward Extend Boom Lower Boom / Adjust Retract Boom / Pave Concrete Raise Boom / Adjust
6.10 90.00 81.00 6.10 90.00 81.00 6.10 90.00 81.00 6.10 90.00 81.00 6.10 90.00 81.00 6.10 90.00 81.00 6.10 90.00 81.00 6.10 90.00 81.00 6.10 90.00 81.00 6.10 90.00 81.00
0.00 0.04 0.01 0.05 0.01 0.00 0.04 0.01 0.05 0.01 0.00 0.04 0.01 0.05 0.01 0.00 0.04 0.01 0.05 0.01 0.00 0.04 0.01 0.05 0.01 0.00 0.04 0.01 0.05 0.01 0.00 0.04 0.01 0.05 0.01 0.00 0.04 0.01 0.05 0.01 0.00 0.04 0.01 0.05 0.01 0.00 0.04 0.01 0.05 0.01
0.02 2.43 0.50 2.70 0.50 0.02 2.43 0.50 2.70 0.50 0.02 2.43 0.50 2.70 0.50 0.02 2.43 0.50 2.70 0.50 0.02 2.43 0.50 2.70 0.50 0.02 2.43 0.50 2.70 0.50 0.02 2.43 0.50 2.70 0.50 0.02 2.43 0.50 2.70 0.50 0.02 2.43 0.50 2.70 0.50 0.02 2.43 0.50 2.70 0.50
Move Forward Extend Boom Lower Boom / Adjust Retract Boom / Pave Concrete Raise Boom / Adjust Move Forward Extend Boom Lower Boom / Adjust Retract Boom / Pave Concrete Raise Boom / Adjust
6.10 90.00 81.00 6.10 90.00 81.00 0 0 0 0 0 0 0 0 0 0
-
Cleanup / Demobilization Total
0.00 0.04 0.01 0.05 0.01 0.00 0.04 0.01 0.05 0.01 -
0.02 2.43 0.50 2.70 0.50 0.02 2.43 0.50 2.70 0.50 -
0.67
40.00
2.67
160.09
Productivity
11.08 m3/hr
Productivity
41.04 m2/hr
Concrete Paving t = 300.00 mm Equipment Specifications Parameter Forward Speed Reverse Speed Capacity (area/pass) Screed Width Boom Speed Trial Strip
Parameter Pavement Length Pavement Width Pavement Thickness Area of Pavement Volume No of Setups / Positions
Somero 160 - Concrete Paver/Finisher Quantity Unit 6.10 km/hr 3.00 km/hr 14.90 m2/pass 2.44 m 72.00 m/hr
Quantity 30.00 3.65 300.00 109.50 32.85 13.00
Unit m m mm m2 m3
Time-Motion Table Activity
Rate
Mobilization / Setup / Wait Move Forward Extend Boom Lower Boom / Adjust Retract Boom / Pave Concrete Raise Boom / Adjust Move Forward Extend Boom Lower Boom / Adjust Retract Boom / Pave Concrete Raise Boom / Adjust Move Forward Extend Boom Lower Boom / Adjust Retract Boom / Pave Concrete Raise Boom / Adjust Move Forward Extend Boom Lower Boom / Adjust Retract Boom / Pave Concrete Raise Boom / Adjust Move Forward Extend Boom Lower Boom / Adjust Retract Boom / Pave Concrete Raise Boom / Adjust Move Forward Extend Boom Lower Boom / Adjust Retract Boom / Pave Concrete Raise Boom / Adjust Move Forward Extend Boom Lower Boom / Adjust Retract Boom / Pave Concrete Raise Boom / Adjust Move Forward Extend Boom Lower Boom / Adjust Retract Boom / Pave Concrete Raise Boom / Adjust Move Forward
6.10 72.00 81.00 6.10 72.00 81.00 6.10 72.00 81.00 6.10 72.00 81.00 6.10 72.00 81.00 6.10 72.00 81.00 6.10 72.00 81.00 6.10 72.00 81.00 6.10
Volume = Time Required hrs
32.85 cu.m. Time Required minutes
0.67
40.00
0.00 0.05 0.01 0.05 0.01 0.00 0.05 0.01 0.05 0.01 0.00 0.05 0.01 0.05 0.01 0.00 0.05 0.01 0.05 0.01 0.00 0.05 0.01 0.05 0.01 0.00 0.05 0.01 0.05 0.01 0.00 0.05 0.01 0.05 0.01 0.00 0.05 0.01 0.05 0.01 0.00
0.02 3.04 0.50 2.70 0.50 0.02 3.04 0.50 2.70 0.50 0.02 3.04 0.50 2.70 0.50 0.02 3.04 0.50 2.70 0.50 0.02 3.04 0.50 2.70 0.50 0.02 3.04 0.50 2.70 0.50 0.02 3.04 0.50 2.70 0.50 0.02 3.04 0.50 2.70 0.50 0.02
Extend Boom Lower Boom / Adjust Retract Boom / Pave Concrete Raise Boom / Adjust Move Forward Extend Boom Lower Boom / Adjust Retract Boom / Pave Concrete Raise Boom / Adjust Move Forward Extend Boom Lower Boom / Adjust Retract Boom / Pave Concrete Raise Boom / Adjust Move Forward Extend Boom Lower Boom / Adjust Retract Boom / Pave Concrete Raise Boom / Adjust Move Forward Extend Boom Lower Boom / Adjust Retract Boom / Pave Concrete Raise Boom / Adjust
Cleanup / Demobilization Total
72.00 81.00 6.10 72.00 81.00 6.10 72.00 81.00 6.10 72.00 81.00 6.10 72.00 81.00 0 0 0 0 0 0 0 0 0 0
-
0.05 0.01 0.05 0.01 0.00 0.05 0.01 0.05 0.01 0.00 0.05 0.01 0.05 0.01 0.00 0.05 0.01 0.05 0.01 0.00 0.05 0.01 0.05 0.01 -
3.04 0.50 2.70 0.50 0.02 3.04 0.50 2.70 0.50 0.02 3.04 0.50 2.70 0.50 0.02 3.04 0.50 2.70 0.50 0.02 3.04 0.50 2.70 0.50 -
0.67
40.00
2.80
168.00
Productivity
11.73 m3/hr
Productivity
39.11 m2/hr
Setup Number
-
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
9.00
10.00
11.00
12.00
13.00
13.00
13.00
-
Setup Number
-
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
9.00
10.00
11.00
12.00
13.00
13.00
13.00
-
Setup Number
-
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
9.00
10.00
11.00
12.00
13.00
13.00
13.00
-
PRODUCTIVITY CALCULATIONS Asphalt Paving Asphalt Paver Specifications Paver Type / Make / Model
Paver Width (m)
Dynapac F300 CS Dynapac F182 CS Dynapac F181 C Dynapac F141 CS
Working Speed (km/hr)
16.00 6.10 3.00 5.10
Travel Speed (km/hr)
1.2 1.38 1.2 1.2
3.6 5 3.8 4.6
Tonnage = Time Required hrs
120.45 tons Time Required minutes
0.67
40.00
1.20
0.08 0.03 0.08
5.00 1.67 5.00
Load Pave Stop & Wait
1.20
0.08 0.03 0.08
5.00 1.67 5.00
Load Pave Stop & Wait
1.20
0.08 0.03 0.08
5.00 1.67 5.00
0.08 0.03
5.00 1.67
Asphalt Paving t = 50.00 mm Trial Strip
Parameter Pavement Length Pavement Width Pavement Thickness Area of Pavement Volume Tonnage Number of Load(s) Length Paved / Load
Quantity 300.00 3.65 50.00 1,095.00 54.75 120.45 9.00 33.33
Time-Motion Table Activity
Rate
Mobilization / Setup / Wait Load Pave Stop & Wait
Load Pave
1.20
Unit m m mm m2 m3 tons m
Stop & Wait
0.08
5.00
Load Pave Stop & Wait
1.20
0.08 0.03 0.08
5.00 1.67 5.00
Load Pave Stop & Wait
1.20
0.08 0.03 0.08
5.00 1.67 5.00
Load Pave Stop & Wait
1.20
0.08 0.03 0.08
5.00 1.67 5.00
Load Pave Stop & Wait
1.20
0.08 0.03 0.08
5.00 1.67 5.00
Load Pave Stop & Wait
1.20
0.08 0.03 0.08
5.00 1.67 5.00
0 0 0
-
-
-
0 0 0
-
-
-
0 0 0
-
-
-
0 0 0
-
-
-
0 0 0
-
-
-
0 0 0
-
-
-
-
-
-
0 0 0
0 0 0
-
-
-
0 0 0
-
-
-
Cleanup / Demobilization Total Productivity
0.67
40.00
3.08
185.00
39.06 ton(s)/hr
Productivity
355.14 m2/hr
Asphalt Paving t = 75.00 mm Trial Strip
Parameter Pavement Length Pavement Width Pavement Thickness Area of Pavement Volume Tonnage Number of Load(s) Length Paved / Load
Quantity 300.00 3.65 75.00 1,095.00 82.13 180.68 14.00 21.43
Time-Motion Table
Unit m m mm m2 m3 tons m Tonnage = Time Required hrs
180.68 tons Time Required minutes
Mobilization / Setup / Wait
0.67
40.00
Load Pave Stop & Wait
1.14
0.08 0.02 0.08
5.00 1.13 5.00
Load Pave Stop & Wait
1.14
0.08 0.02 0.08
5.00 1.13 5.00
0.08 0.02
5.00 1.13
Activity
Load Pave
Rate
1.14
Stop & Wait
0.08
5.00
Load Pave Stop & Wait
1.14
0.08 0.02 0.08
5.00 1.13 5.00
Load Pave Stop & Wait
1.14
0.08 0.02 0.08
5.00 1.13 5.00
Load Pave Stop & Wait
1.14
0.08 0.02 0.08
5.00 1.13 5.00
Load Pave Stop & Wait
1.14
0.08 0.02 0.08
5.00 1.13 5.00
Load Pave Stop & Wait
1.14
0.08 0.02 0.08
5.00 1.13 5.00
Load Pave Stop & Wait
1.14
0.08 0.02 0.08
5.00 1.13 5.00
Load Pave Stop & Wait
1.14
0.08 0.02 0.08
5.00 1.13 5.00
Load Pave Stop & Wait
1.14
0.08 0.02 0.08
5.00 1.13 5.00
Load Pave Stop & Wait
1.14
0.08 0.02 0.08
5.00 1.13 5.00
Load Pave Stop & Wait
1.14
0.08 0.02 0.08
5.00 1.13 5.00
Load Pave Stop & Wait
1.14
0.08 0.02 0.08
5.00 1.13 5.00
-
-
-
0 0 0
0 0 0
-
-
-
0 0 0
-
-
-
-
-
-
0 0 0
Cleanup / Demobilization Total Productivity
0.67
40.00
3.93
235.79
45.98 ton(s)/hr
Productivity
278.64 m2/hr
Asphalt Paving t = 100.00 mm Trial Strip
Parameter Pavement Length Pavement Width Pavement Thickness Area of Pavement Volume Tonnage Number of Load(s) Length Paved / Load
Quantity 300.00 3.65 100.00 1,095.00 109.50 240.90 18.00 16.67
Time-Motion Table Activity
Rate
Mobilization / Setup / Wait Load Pave Stop & Wait Load Pave
1.08
1.08
Unit m m mm m2 m3 tons m Tonnage = Time Required hrs
240.90 tons Time Required minutes
0.67
40.00
0.08 0.02 0.08
5.00 0.93 5.00
0.08 0.02
5.00 0.93
Stop & Wait
0.08
5.00
Load Pave Stop & Wait
1.08
0.08 0.02 0.08
5.00 0.93 5.00
Load Pave Stop & Wait
1.08
0.08 0.02 0.08
5.00 0.93 5.00
Load Pave Stop & Wait
1.08
0.08 0.02 0.08
5.00 0.93 5.00
Load Pave Stop & Wait
1.08
0.08 0.02 0.08
5.00 0.93 5.00
Load Pave Stop & Wait
1.08
0.08 0.02 0.08
5.00 0.93 5.00
Load Pave Stop & Wait
1.08
0.08 0.02 0.08
5.00 0.93 5.00
Load Pave Stop & Wait
1.08
0.08 0.02 0.08
5.00 0.93 5.00
Load Pave Stop & Wait
1.08
0.08 0.02 0.08
5.00 0.93 5.00
Load Pave Stop & Wait
1.08
0.08 0.02 0.08
5.00 0.93 5.00
Load Pave Stop & Wait
1.08
0.08 0.02 0.08
5.00 0.93 5.00
Load Pave Stop & Wait
1.08
0.08 0.02 0.08
5.00 0.93 5.00
1.08
0.08 0.02 0.08
5.00 0.93 5.00
Load Pave Stop & Wait
Cleanup / Demobilization Total Productivity Productivity
0 0 0
1.08
0.08 0.02 0.08
5.00 0.93 5.00
0 0 0
1.08
0.08 0.02 0.08
5.00 0.93 5.00
0 0 0
1.08
0.08 0.02 0.08
5.00 0.93 5.00
0 0 0
1.08
0.08 0.02 0.08
5.00 0.93 5.00
0 0 0
-
-
-
0 0 0
-
-
-
0.67
40.00
4.61
276.67
52.24 ton(s)/hr 237.47 m2/hr
Laying Thickness (mm) 350 350 300 300
Setup Number
1.00
2.00
3.00
Hopper Capacity (m3) tons 6.80 7.80 6.00 6.00
15.00 18.10 13.00 13.00
4.00
5.00
6.00
7.00
8.00
9.00
9.00
9.00
9.00
9.00
9.00
9.00
9.00
9.00
9.00
-
6.00 truckloads 30.83 mins/truckloads
Setup Number
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
9.00
10.00
11.00
12.00
13.00
14.00
14.00
14.00
14.00
14.00
-
6.00 truckloads 39.30 mins/truckloads
Setup Number
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
9.00
10.00
11.00
12.00
13.00
14.00
15.00
16.00
17.00
18.00
18.00
18.00
-
6.00 truckloads 46.11 mins/truckloads
PRODUCTIVITY CALCULATIONS Asphalt Compacting Asphalt Compactor Specifications Paver Type / Make / Model
Drum Width (m)
Dynapac CC142 Dynapac CG223HF Dynapac CC322
Working Speed (km/hr)
1.30 1.45 1.68
Travel Speed (km/hr)
1 1.2 1.3
10 12 13
Tonnage = Time Required hrs
13.38 tons Time Required minutes
0.17
10.00
Asphalt Paving t = 50.00 mm Asphalt Compactor Specifications Parameter Forward Speed Reverse Speed Drum Width Trial Strip
Parameter Pavement Length Pavement Width Pavement Thickness Area of Pavement Volume Tonnage No. of Passes (per drum width) Total No. of Passes
Quantity
1.30 1.30 1.68
Quantity 33.33 3.65 50.00 121.67 6.08 13.38 7.00 3.00
Time-Motion Table Activity
Rate
Wait
Unit km/hr km/hr m
Unit m m mm m2 m3 tons passes passes
Move Forward Reverse
1.30 1.30
0.03 0.03
1.54 1.54
Move Forward Reverse
1.30 1.30
0.03 0.03
1.54 1.54
Move Forward
1.30
0.03
1.54
Reverse
1.30
0.03
1.54
Move Forward Reverse
1.30 1.30
0.03 0.03
1.54 1.54
Move Forward Reverse
1.30 1.30
0.03 0.03
1.54 1.54
Move Forward Reverse
1.30 1.30
0.03 0.03
1.54 1.54
Move Forward Reverse
1.30 1.30
0.03 0.03
1.54 1.54
0 0
-
-
-
0 0
-
-
-
0 0
-
-
-
0 0
-
-
-
0 0
-
-
-
Compaction Cycle
3 cycles
Wait Total Productivity
21.54
0.17
10.00
1.41
41.54
9.49 ton(s)/hr
Productivity
86.27 m2/hr
Asphalt Paving t = 75.00 mm Asphalt Compactor Specifications Parameter Forward Speed Reverse Speed Drum Width
1.08
Quantity
1.30 1.30 1.68
Unit km/hr km/hr m
Trial Strip
Parameter Pavement Length Pavement Width Pavement Thickness Area of Pavement Volume Tonnage No. of Passes (per drum width) Total No. of Passes
Quantity 21.43 3.65 75.00 78.21 5.87 12.91 7.00 3.00
Time-Motion Table Activity
Rate
Wait
Unit m m mm m2 m3 tons passes passes Tonnage = Time Required hrs
12.91 tons Time Required minutes
0.17
10.00
Move Forward Reverse
1.30 1.30
0.02 0.02
0.99 0.99
Move Forward Reverse
1.30 1.30
0.02 0.02
0.99 0.99
Move Forward Reverse
1.30 1.30
0.02 0.02
0.99 0.99
Move Forward Reverse
1.30 1.30
0.02 0.02
0.99 0.99
Move Forward Reverse
1.30 1.30
0.02 0.02
0.99 0.99
Move Forward Reverse
1.30 1.30
0.02 0.02
0.99 0.99
Move Forward Reverse
1.30 1.30
0.02 0.02
0.99 0.99
0 0
-
-
-
0 0
-
-
-
0 0
-
-
-
0 0
-
-
-
0 0
-
-
-
Compaction Cycle
3 cycles
0.69
13.85
cycles
0.17
10.00
1.03
33.85
Wait Total Productivity
12.58 ton(s)/hr
Productivity
76.26 m2/hr
Asphalt Paving t = 100.00 mm Asphalt Compactor Specifications Parameter Forward Speed Reverse Speed Drum Width Trial Strip
Parameter Pavement Length Pavement Width Pavement Thickness Area of Pavement Volume Tonnage No. of Passes (per drum width) Total No. of Passes
Quantity
1.30 1.30 1.68
Quantity 16.67 3.65 100.00 60.83 6.08 13.38 7.00 3.00
Time-Motion Table Activity
Rate
Wait
Move Forward
1.30
Unit km/hr km/hr m
Unit m m mm m2 m3 tons passes passes Tonnage = Time Required hrs
13.38 tons Time Required minutes
0.17
10.00
0.01
0.77
Reverse
1.30
0.01
0.77
Move Forward Reverse
1.30 1.30
0.01 0.01
0.77 0.77
Move Forward Reverse
1.30 1.30
0.01 0.01
0.77 0.77
Move Forward Reverse
1.30 1.30
0.01 0.01
0.77 0.77
Move Forward Reverse
1.30 1.30
0.01 0.01
0.77 0.77
Move Forward Reverse
1.30 1.30
0.01 0.01
0.77 0.77
Move Forward Reverse
1.30 1.30
0.01 0.01
0.77 0.77
0 0
-
-
-
0 0
-
-
-
0 0
-
-
-
0 0
-
-
-
0 0
-
-
-
Compaction Cycle Wait Total
3 cycles
0.54
10.77
0.17
10.00
0.87
30.77
Productivity
15.35 ton(s)/hr
Productivity
69.78 m2/hr
Weight (tons) 4.40 8.20 8.80
Setup Number
1.00
2.00
3.00
4.00
5.00
6.00
7.00
7.00
7.00
7.00
7.00
7.00
Setup Number
1.00
2.00
3.00
4.00
5.00
6.00
7.00
7.00
7.00
7.00
7.00
7.00
Setup Number
1.00
2.00
3.00
4.00
5.00
6.00
7.00
7.00
7.00
7.00
7.00
7.00
PRODUCTIVITY CALCULATIONS Prime Coat Distributing Asphalt Distributor Specifications Parameter Tank Capacity Tank Capacity Travel Speed (Loaded) Travel Speed (Empty) Pump (Rated) Capacity Application Rate Application Rate Application Rate Spray Bar Length Application Speed Application Speed Area per Truckload
Quantity 5.00 6,250.00 30.00 50.00 15.00 1.00 0.0008 15,000.00 6.20 2,419.35 40.32 6,250.00
Unit tons li km/hr km/hr m3/hr li/m2 tons/m2 m2/hr m m/hr m/min m2
Site Conditions Parameter Pavement Length Pavement Width Area of Pavement Application Requirement Volume Distance to/from Plant
Quantity 500.00 7.30 3,650.00 2.00 7,300.00 30.00
Unit m m m2 li/m2 li kms
Time-Motion Table Activity
Load Bitumen Travel to Site (Loaded) Wait at Site Unload Bitumen Travel to Plant (Empty) Adjustment Factor Total Productivity Productivity
Rate
30.00 1,209.68 50.00
Tonnage = Time Required hrs
5.84 tons Time Required minutes
2.34 1.00 0.35 0.41 0.60
140.16 60.00 21.00 24.80 36.00
4.70 9.40 0.62 ton(s)/hr 388.35 m2/hr
281.96
Setup Number
PRODUCTIVITY CALCULATIONS Tack Coat Distributing Asphalt Distributor Specifications Parameter Tank Capacity Tank Capacity Travel Speed (Loaded) Travel Speed (Empty) Pump (Rated) Capacity Application Rate Application Rate Application Rate Spray Bar Length Application Speed Application Speed Area per Truckload
Quantity 5.00 6,250.00 30.00 50.00 15.00 1.00 0.0008 15,000.00 6.20 2,419.35 40.32 6,250.00
Unit tons li km/hr km/hr m3/hr li/m2 tons/m2 m2/hr m m/hr m/min m2
Site Conditions Parameter Pavement Length Pavement Width Area of Pavement Application Requirement Volume Distance to/from Plant
Quantity 500.00 7.30 3,650.00 0.75 2,737.50 30.00
Unit m m m2 li/m2 li kms
Time-Motion Table Activity
Load Bitumen Travel to Site (Loaded) Wait at Site Unload Bitumen Travel to Plant (Empty) Adjustment Factor Total Productivity Productivity
Rate
30.00 3,225.81 50.00
Tonnage = Time Required hrs
2.19 tons Time Required minutes
0.88 1.00 0.35 0.16 0.60
52.56 60.00 21.00 9.30 36.00
2.98 0.73 ton(s)/hr 1,224.42 m2/hr
178.86
Setup Number
PRODUCTIVITY CALCULATIONS Asphalt Material Application (1) Asphalt Distributor Specifications Parameter Tank Capacity Tank Capacity Travel Speed (Loaded) Travel Speed (Empty) Pump (Rated) Capacity Application Rate Application Rate Application Rate Spray Bar Length Application Speed Application Speed Area per Truckload
Quantity 5.00 6,250.00 30.00 50.00 15.00 1.00 0.0008 15,000.00 6.20 2,419.35 40.32 6,250.00
Unit tons li km/hr km/hr m3/hr li/m2 tons/m2 m2/hr m m/hr m/min m2
Site Conditions Parameter Pavement Length Pavement Width Area of Pavement Application Requirement Volume Distance to/from Plant
Quantity 500.00 7.30 3,650.00 1.20 4,380.00 30.00
Unit m m m2 li/m2 li kms
Time-Motion Table Activity
Load Bitumen Travel to Site (Loaded) Wait at Site Unload Bitumen Travel to Plant (Empty) Adjustment Factor Total Productivity Productivity
Rate
30.00 2,016.13 50.00
Tonnage = Time Required hrs
3.50 tons Time Required minutes
1.40 1.00 0.35 0.25 0.60
84.10 60.00 21.00 14.88 36.00
3.60 0.97 ton(s)/hr 1,014.00 m2/hr
215.98
Setup Number
PRODUCTIVITY CALCULATIONS Asphalt Material Application (2) Asphalt Distributor Specifications Parameter Tank Capacity Tank Capacity Travel Speed (Loaded) Travel Speed (Empty) Pump (Rated) Capacity Application Rate Application Rate Application Rate Spray Bar Length Application Speed Application Speed Area per Truckload
Quantity 5.00 6,250.00 30.00 50.00 15.00 1.00 0.0008 15,000.00 6.20 2,419.35 40.32 6,250.00
Unit tons li km/hr km/hr m3/hr li/m2 tons/m2 m2/hr m m/hr m/min m2
Site Conditions Parameter Pavement Length Pavement Width Area of Pavement Application Requirement Volume Distance to/from Plant
Quantity 500.00 7.30 3,650.00 2.00 7,300.00 30.00
Unit m m m2 li/m2 li kms
Time-Motion Table Activity
Load Bitumen Travel to Site (Loaded) Wait at Site Unload Bitumen Travel to Plant (Empty) Adjustment Factor Total Productivity Productivity
Rate
30.00 1,209.68 50.00
Tonnage = Time Required hrs
5.84 tons Time Required minutes
2.34 1.00 0.35 0.41 0.60
140.16 60.00 21.00 24.80 36.00
4.70 4.70 1.24 ton(s)/hr 776.71 m2/hr
281.96
Setup Number
PRODUCTIVITY CALCULATIONS Water Hauling by Water Truck
Equipment Specifications Parameter Loaded Speed Empty Speed Load Capacity Fuel Consumption Suction/Discharge Rate
Water Truck Quantity 45.00 60.00 4.00 15.00 350.00
AHD = Time-Motion Table
5.000 km(s)
Activity
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Discharge Load Travel (Empty)
Rate
350.000 lpm 45.00 350.000 lpm 60.00
Total Productivity
AHD= 5.000 km(s)
AHD = Time-Motion Table Activity
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Discharge Load Travel (Empty)
Time Required hrs
Time Required minutes
0.08 0.19 0.11 0.08 0.19 0.08
5.00 11.43 6.67 5.00 11.43 5.00
0.74
44.52
5.39 m3/hr
7.000 km(s)
Rate
350.000 lpm 45.00 350.000 lpm 60.00
Total Productivity
Cap = 4.00 cu.m. Unit km/hr km/hr m3 li/hr li/m
AHD= 7.000 km(s)
Time Required hrs
Time Required minutes
0.08 0.19 0.16 0.08 0.19 0.12
5.00 11.43 9.33 5.00 11.43 7.00
0.82
49.19
4.88 m3/hr
AHD = Time-Motion Table Activity
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Discharge Load Travel (Empty)
10.000 km(s)
Rate
350.000 lpm 45.00 350.000 lpm 60.00
Total Productivity
AHD= 10.000 km(s)
AHD = Time-Motion Table Activity
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Discharge Load Travel (Empty)
Rate
350.000 lpm 45.00 350.000 lpm 60.00
AHD= 15.000 km(s)
AHD = Time-Motion Table Activity
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Discharge Load Travel (Empty) Total
Time Required minutes
0.08 0.19 0.22 0.08 0.19 0.17
5.00 11.43 13.33 5.00 11.43 10.00
0.94
56.19
4.27 m3/hr
15.000 km(s)
Total Productivity
Time Required hrs
Time Required hrs
Time Required minutes
0.08 0.19 0.33 0.08 0.19 0.25
5.00 11.43 20.00 5.00 11.43 15.00
1.13
67.86
3.54 m3/hr
20.000 km(s)
Rate
350.000 lpm 45.00 350.000 lpm 60.00
Time Required hrs
Time Required minutes
0.08 0.19 0.44 0.08 0.19 0.33
5.00 11.43 26.67 5.00 11.43 20.00
1.33
79.52
Productivity
AHD= 20.000 km(s)
AHD = Time-Motion Table Activity
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Discharge Load Travel (Empty)
25.000 km(s)
Rate
350.000 lpm 45.00 350.000 lpm 60.00
Total Productivity
AHD= 25.000 km(s)
AHD = Time-Motion Table Activity
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Discharge Load Travel (Empty)
Time Required hrs
Time Required minutes
0.08 0.19 0.56 0.08 0.19 0.42
5.00 11.43 33.33 5.00 11.43 25.00
1.52
91.19
2.63 m3/hr
30.000 km(s)
Rate
350.000 lpm 45.00 350.000 lpm 60.00
Total Productivity
3.02 m3/hr
AHD= 30.000 km(s)
Time Required hrs
Time Required minutes
0.08 0.19 0.67 0.08 0.19 0.50
5.00 11.43 40.00 5.00 11.43 30.00
1.71
102.86
2.33 m3/hr
PRODUCTIVITY CALCULATIONS Fuel Hauling Hauling by Fuel Truck
Equipment Specifications Parameter Loaded Speed Empty Speed Load Capacity Fuel Consumption Suction/Discharge Rate
Fuel Truck Quantity 45.00 60.00 13.00 15.00 65.00
AHD = Time-Motion Table
5.000 km(s)
Activity
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Discharge Load Travel (Empty)
Rate
65.000 lpm 45.00 65.000 lpm 60.00
Total Productivity
AHD= 5.000 km(s)
AHD = Time-Motion Table Activity
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Discharge Load Travel (Empty)
###
Time Required hrs
Time Required minutes
0.08 3.33 0.11 0.08 3.33 0.08
5.00 200.00 6.67 5.00 200.00 5.00
7.03
421.67
1.85 m3/hr
7.000 km(s)
Rate
65.000 lpm 45.00 65.000 lpm 60.00
Total Productivity
Unit km/hr km/hr m3 li/hr li/m
AHD= 7.000 km(s)
Time Required hrs
Time Required minutes
0.08 3.33 0.16 0.08 3.33 0.12
5.00 200.00 9.33 5.00 200.00 7.00
7.11
426.33
1.83 m3/hr
AHD = Time-Motion Table Activity
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Discharge Load Travel (Empty)
10.000 km(s)
Rate
65.000 lpm 45.00 65.000 lpm 60.00
Total Productivity
AHD= 10.000 km(s)
AHD = Time-Motion Table Activity
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Discharge Load Travel (Empty)
Rate
65.000 lpm 45.00 65.000 lpm 60.00
AHD= 15.000 km(s)
AHD = Time-Motion Table Activity
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Discharge Load Travel (Empty) Total
Time Required minutes
0.08 3.33 0.22 0.08 3.33 0.17
5.00 200.00 13.33 5.00 200.00 10.00
7.22
433.33
1.80 m3/hr
15.000 km(s)
Total Productivity
Time Required hrs
Time Required hrs
Time Required minutes
0.08 3.33 0.33 0.08 3.33 0.25
5.00 200.00 20.00 5.00 200.00 15.00
7.42
445.00
1.75 m3/hr
20.000 km(s)
Rate
65.000 lpm 45.00 65.000 lpm 60.00
Time Required hrs
Time Required minutes
0.08 3.33 0.44 0.08 3.33 0.33
5.00 200.00 26.67 5.00 200.00 20.00
7.61
456.67
Productivity
AHD= 20.000 km(s)
AHD = Time-Motion Table Activity
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Discharge Load Travel (Empty)
25.000 km(s)
Rate
65.000 lpm 45.00 65.000 lpm 60.00
Total Productivity
AHD= 25.000 km(s)
AHD = Time-Motion Table Activity
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Discharge Load Travel (Empty)
Time Required hrs
Time Required minutes
0.08 3.33 0.56 0.08 3.33 0.42
5.00 200.00 33.33 5.00 200.00 25.00
7.81
468.33
1.67 m3/hr
30.000 km(s)
Rate
65.000 lpm 45.00 65.000 lpm 60.00
Total Productivity
1.71 m3/hr
AHD= 30.000 km(s)
Time Required hrs
Time Required minutes
0.08 3.33 0.67 0.08 3.33 0.50
5.00 200.00 40.00 5.00 200.00 30.00
8.00
480.00
1.63 m3/hr
PRODUCTIVITY CALCULATIONS Rock Breaking Rock Breaking
Diameter = 5000.00 mm
Trial Boulder Parameter Boulder Length Boulder Width Boulder Height Area of Boulder Volume Equipment Specifications Parameter Forward Speed Reverse Speed Bucket Capacity Fuel Consumption
Quantity
Backhoe w/ Breaker Quantity 2.63 2.63 0.80 16.00
Productivity Rates - Breaking Breaker Penetration Rate
4.00 14.40 0.347 35.00 2.00 5.76 12.50 2.18 2.00 4.36
Duration per Breaking Stroke Swing-Lower/Raise-Swing Cycle Area Covered / Penetration Direct Area Breaking Rate Area Covered / Position Duration per Position Number of Positions Total Duration (Breaking) Time-Motion Table Activity
Breaking Fix Breaker, Maneuver, Wait Moving Forward, Positioning Breaking Maneuver, Wait
Total Productivity
Unit m m m sm m3
5.00 5.00 5.00 25.00 125.00
Rate
Unit km/hr km/hr m3 li/hr
mm/sec m/hr hrs secs m2 m2/hr m2 hrs positions hrs
Time Required hrs
Excluding Travel
Time Required minutes
1.00 0.17 4.36 0.25
60.00 10.23 261.58 15.00
5.78
346.81
21.63 m3/hr
PRODUCTIVITY CALCULATIONS Rock Loading from Stockpile - Loader Trial Pile Pile Length Pile Width Height Area of Pile Volume
Parameter
Equipment Specifications Parameter Forward Speed Reverse Speed Actual Bucket Capacity : 75.000% Dig - Raise Cycle Reverse-Forward Cycle Dump - Lower Empty Cycle Fuel Consumption
Quantity
Unit m m m sm m3
Loader 100HP Dump Truck Quantity 6.40 7.70 1.13 16.40 10.30 5.50 15.00
Cap = 1.50 cu.m. ### Unit km/hr km/hr m3 secs secs secs li/hr
Rate
75% Time Required hrs
5.00 5.00 4.00 25.00 33.33
Time-Motion Table Activity
Maneuver & Waiting Time Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty
0.167 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 -
1.78 2.14
Dump Truck Capacity Time Required minutes
10.00 0.54 0.54 0.54 0.54 0.54 0.54 0.54 0.54 0.54 0.54 -
Total
0.26
Productivity
43.93 m3/hr
Equipment Specifications Parameter Forward Speed Reverse Speed Actual Bucket Capacity : 75.000% Dig - Raise Cycle Reverse-Forward Cycle Dump - Lower Empty Cycle Fuel Consumption
Loader 117HP Dump Truck Quantity 7.10 7.80 1.80 16.60 9.69 5.20 19.00
Cap = 2.40 cu.m. ### Unit km/hr km/hr m3 secs secs secs li/hr
Rate
75% Time Required hrs
Time-Motion Table Activity
Maneuver & Waiting Time Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty
Total Productivity
15.37
1.97 2.17
Dump Truck Capacity Time Required minutes
0.167 0.009 0.009 0.009 0.009 0.009 0.009 0.009 -
10.00 0.52 0.52 0.52 0.52 0.52 0.52 0.52 -
0.23
13.67
49.37 m3/hr
m/s m/s
Dump Truck Capacity = Volume (m3)
1.13 1.13 1.13 1.13 1.13 1.13 1.13 1.13 1.13 1.13 -
11.25 cu.m. Running Volume (m3)
1.13 2.25 3.38 4.50 5.63 6.75 7.88 9.00 10.13 11.25 11.25 11.25 11.25 11.25 11.25 11.25 11.25 11.25 11.25 11.25 11.25
m/s m/s
Dump Truck Capacity = Volume (m3)
1.80 1.80 1.80 1.80 1.80 1.80 1.80 -
11.25 cu.m. Running Volume (m3)
1.80 3.60 5.40 7.20 9.00 10.80 12.60 12.60 12.60 12.60 12.60 12.60 12.60 12.60 12.60 12.60 12.60 12.60 12.60 12.60 12.60
PRODUCTIVITY CALCULATIONS Rock Hauling by Dump Truck
Equipment Specifications Parameter Loaded Speed Empty Speed Actual Capacity : 75.000% Fuel Consumption
Dump Truck Quantity 30.00 60.00 11.25 15.00
Unit km/hr km/hr m3 li/hr
###
LOADING BY WHEEL LOADER AHD = Time-Motion Table Activity
5.000 km(s) Time Required hrs
Rate
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Dump Travel (Empty)
30.00
60.00
Total Productivity
AHD= 5.000 km(s)
AHD = Time-Motion Table Activity
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Dump Travel (Empty)
0.08 0.23 0.17 0.08 0.03 0.08
5.00 13.67 10.00 5.00 2.00 5.00
0.68
40.67
16.60 m3/hr
7.000 km(s) Time Required hrs
Rate
30.00
60.00
Total Productivity
Time Required minutes
AHD= 7.000 km(s)
Time Required minutes
0.08 0.23 0.23 0.08 0.03 0.12
5.00 13.67 14.00 5.00 2.00 7.00
0.78
46.67
14.46 m3/hr
AHD = Time-Motion Table Activity
10.000 km(s) Time Required hrs
Rate
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Dump Travel (Empty)
30.00
60.00
Total Productivity
AHD= 10.000 km(s)
AHD = Time-Motion Table Activity
30.00
60.00
AHD= 15.000 km(s)
Activity
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Dump Travel (Empty)
5.00 13.67 21.08 5.00 2.00 10.00
0.95
56.76
11.89 m3/hr
Time Required hrs
Rate
Total
AHD = Time-Motion Table
0.08 0.23 0.35 0.08 0.03 0.17
15.000 km(s)
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Dump Travel (Empty)
Productivity
Time Required minutes
Time Required minutes
0.08 0.23 0.50 0.08 0.03 0.25
5.00 13.67 30.00 5.00 2.00 15.00
1.18
70.67
9.55 m3/hr
20.000 km(s) Time Required hrs
Rate
30.00
60.00
0.08 0.23 0.67 0.08 0.03 0.33
Time Required minutes
5.00 13.67 40.00 5.00 2.00 20.00
Total Productivity
1.43 AHD= 20.000 km(s)
AHD = Time-Motion Table Activity
Time Required hrs
Rate
30.00
60.00
Total AHD= 25.000 km(s)
AHD = Time-Motion Table Activity
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Dump Travel (Empty)
Time Required minutes
0.08 0.23 0.83 0.08 0.03 0.42
5.00 13.67 50.00 5.00 2.00 25.00
1.68
100.67
6.70 m3/hr
30.000 km(s) Time Required hrs
Rate
30.00
60.00
Total Productivity
7.88 m3/hr
25.000 km(s)
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Dump Travel (Empty)
Productivity
85.67
AHD= 30.000 km(s)
Time Required minutes
0.08 0.23 1.00 0.08 0.03 0.50
5.00 13.67 60.00 5.00 2.00 30.00
1.93
115.67
5.84 m3/hr
PRODUCTIVITY CALCULATIONS Stone Loading from Stockpile - Loader Trial Pile Pile Length Pile Width Height Area of Pile Volume
Parameter
Equipment Specifications Parameter Forward Speed Reverse Speed Actual Bucket Capacity : 85.000% Dig - Raise Cycle Reverse-Forward Cycle Dump - Lower Empty Cycle Fuel Consumption
Quantity
Unit m m m sm m3
Loader 100HP Dump Truck Quantity 6.40 7.70 1.28 16.40 10.30 5.50 15.00
Cap = 1.50 cu.m. ### Unit km/hr km/hr m3 secs secs secs li/hr
Rate
85% Time Required hrs
5.00 5.00 4.00 25.00 33.33
Time-Motion Table Activity
Maneuver & Waiting Time Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty
0.167 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 -
1.78 2.14
Dump Truck Capacity Time Required minutes
10.00 0.54 0.54 0.54 0.54 0.54 0.54 0.54 0.54 0.54 0.54 -
Total
0.26
Productivity
49.78 m3/hr
Equipment Specifications Parameter Forward Speed Reverse Speed Actual Bucket Capacity : 85.000% Dig - Raise Cycle Reverse-Forward Cycle Dump - Lower Empty Cycle Fuel Consumption
Loader 117HP Dump Truck Quantity 7.10 7.80 2.04 16.60 9.69 5.20 19.00
Cap = 2.40 cu.m. ### Unit km/hr km/hr m3 secs secs secs li/hr
Rate
85% Time Required hrs
Time-Motion Table Activity
Maneuver & Waiting Time Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty
Total Productivity
15.37
1.97 2.17
Dump Truck Capacity Time Required minutes
0.167 0.009 0.009 0.009 0.009 0.009 0.009 0.009 -
10.00 0.52 0.52 0.52 0.52 0.52 0.52 0.52 -
0.23
13.67
55.95 m3/hr
m/s m/s
Dump Truck Capacity = Volume (m3)
1.28 1.28 1.28 1.28 1.28 1.28 1.28 1.28 1.28 1.28 -
12.75 cu.m. Running Volume (m3)
1.28 2.55 3.83 5.10 6.38 7.65 8.93 10.20 11.48 12.75 12.75 12.75 12.75 12.75 12.75 12.75 12.75 12.75 12.75 12.75 12.75
m/s m/s
Dump Truck Capacity = Volume (m3)
2.04 2.04 2.04 2.04 2.04 2.04 2.04 -
12.75 cu.m. Running Volume (m3)
2.04 4.08 6.12 8.16 10.20 12.24 14.28 14.28 14.28 14.28 14.28 14.28 14.28 14.28 14.28 14.28 14.28 14.28 14.28 14.28 14.28
PRODUCTIVITY CALCULATIONS Stone Hauling by Dump Truck
Equipment Specifications Parameter Loaded Speed Empty Speed Actual Capacity : 85.000% Fuel Consumption
Dump Truck Quantity 30.00 60.00 12.75 15.00
Unit km/hr km/hr m3 li/hr
###
LOADING BY WHEEL LOADER AHD = Time-Motion Table Activity
5.000 km(s) Time Required hrs
Rate
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Dump Travel (Empty)
30.00
60.00
Total Productivity
AHD= 5.000 km(s)
AHD = Time-Motion Table Activity
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Dump Travel (Empty)
0.08 0.23 0.17 0.08 0.03 0.08
5.00 13.67 10.00 5.00 2.00 5.00
0.68
40.67
18.81 m3/hr
7.000 km(s) Time Required hrs
Rate
30.00
60.00
Total Productivity
Time Required minutes
AHD= 7.000 km(s)
Time Required minutes
0.08 0.23 0.23 0.08 0.03 0.12
5.00 13.67 14.00 5.00 2.00 7.00
0.78
46.67
16.39 m3/hr
AHD = Time-Motion Table Activity
10.000 km(s) Time Required hrs
Rate
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Dump Travel (Empty)
30.00
60.00
Total Productivity
AHD= 10.000 km(s)
AHD = Time-Motion Table Activity
30.00
60.00
AHD= 15.000 km(s)
Activity
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Dump Travel (Empty)
5.00 13.67 21.08 5.00 2.00 10.00
0.95
56.76
13.48 m3/hr
Time Required hrs
Rate
Total
AHD = Time-Motion Table
0.08 0.23 0.35 0.08 0.03 0.17
15.000 km(s)
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Dump Travel (Empty)
Productivity
Time Required minutes
Time Required minutes
0.08 0.23 0.50 0.08 0.03 0.25
5.00 13.67 30.00 5.00 2.00 15.00
1.18
70.67
10.82 m3/hr
20.000 km(s) Time Required hrs
Rate
30.00
60.00
0.08 0.23 0.67 0.08 0.03 0.33
Time Required minutes
5.00 13.67 40.00 5.00 2.00 20.00
Total Productivity
1.43 AHD= 20.000 km(s)
AHD = Time-Motion Table Activity
Time Required hrs
Rate
30.00
60.00
Total AHD= 25.000 km(s)
AHD = Time-Motion Table Activity
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Dump Travel (Empty)
Time Required minutes
0.08 0.23 0.83 0.08 0.03 0.42
5.00 13.67 50.00 5.00 2.00 25.00
1.68
100.67
7.60 m3/hr
30.000 km(s) Time Required hrs
Rate
30.00
60.00
Total Productivity
8.93 m3/hr
25.000 km(s)
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Dump Travel (Empty)
Productivity
85.67
AHD= 30.000 km(s)
Time Required minutes
0.08 0.23 1.00 0.08 0.03 0.50
5.00 13.67 60.00 5.00 2.00 30.00
1.93
115.67
6.61 m3/hr
PRODUCTIVITY CALCULATIONS Boulder Loading from Stockpile - Loader Trial Pile Pile Length Pile Width Height Area of Pile Volume
Parameter
Equipment Specifications Parameter Forward Speed Reverse Speed Actual Bucket Capacity : 45.000% Dig - Raise Cycle Reverse-Forward Cycle Dump - Lower Empty Cycle Fuel Consumption
Quantity
Unit m m m sm m3
Loader 100HP Dump Truck Quantity 6.40 7.70 0.68 21.40 10.30 6.10 15.00
Cap = 1.50 cu.m. ### Unit km/hr km/hr m3 secs secs secs li/hr
Rate
45% Time Required hrs
5.00 5.00 4.00 25.00 33.33
Time-Motion Table Activity
Maneuver & Waiting Time Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty
0.167 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 -
1.78 2.14
Dump Truck Capacity Time Required minutes
10.00 0.63 0.63 0.63 0.63 0.63 0.63 0.63 0.63 0.63 0.63 -
Total
0.27
Productivity
24.85 m3/hr
Equipment Specifications Parameter Forward Speed Reverse Speed Actual Bucket Capacity : 45.000% Dig - Raise Cycle Reverse-Forward Cycle Dump - Lower Empty Cycle Fuel Consumption
Loader 117HP Dump Truck Quantity 7.10 7.80 1.08 16.60 9.69 5.20 19.00
Cap = 2.40 cu.m. ### Unit km/hr km/hr m3 secs secs secs li/hr
Rate
45% Time Required hrs
Time-Motion Table Activity
Maneuver & Waiting Time Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty Dig-Raise-Dump-Lower Empty
Total Productivity
16.30
1.97 2.17
Dump Truck Capacity Time Required minutes
0.167 0.009 0.009 0.009 0.009 0.009 0.009 0.009 -
10.00 0.52 0.52 0.52 0.52 0.52 0.52 0.52 -
0.23
13.67
29.62 m3/hr
m/s m/s
Dump Truck Capacity = Volume (m3)
0.68 0.68 0.68 0.68 0.68 0.68 0.68 0.68 0.68 0.68 -
6.75 cu.m. Running Volume (m3)
0.68 1.35 2.03 2.70 3.38 4.05 4.73 5.40 6.08 6.75 6.75 6.75 6.75 6.75 6.75 6.75 6.75 6.75 6.75 6.75 6.75
m/s m/s
Dump Truck Capacity = Volume (m3)
1.08 1.08 1.08 1.08 1.08 1.08 1.08 -
6.75 cu.m. Running Volume (m3)
1.08 2.16 3.24 4.32 5.40 6.48 7.56 7.56 7.56 7.56 7.56 7.56 7.56 7.56 7.56 7.56 7.56 7.56 7.56 7.56 7.56
PRODUCTIVITY CALCULATIONS Stone Hauling by Dump Truck
Equipment Specifications Parameter Loaded Speed Empty Speed Actual Capacity : 45.000% Fuel Consumption
Dump Truck Quantity 30.00 50.00 6.75 15.00
Unit km/hr km/hr m3 li/hr
###
LOADING BY WHEEL LOADER AHD = Time-Motion Table Activity
5.000 km(s) Time Required hrs
Rate
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Dump Travel (Empty)
30.00
50.00
Total Productivity
AHD= 5.000 km(s)
AHD = Time-Motion Table Activity
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Dump Travel (Empty)
0.08 0.23 0.17 0.08 0.03 0.10
5.00 13.67 10.00 5.00 2.00 6.00
0.69
41.67
9.72 m3/hr
7.000 km(s) Time Required hrs
Rate
30.00
50.00
Total Productivity
Time Required minutes
AHD= 7.000 km(s)
Time Required minutes
0.08 0.23 0.23 0.08 0.03 0.14
5.00 13.67 14.00 5.00 2.00 8.40
0.80
48.07
8.42 m3/hr
AHD = Time-Motion Table Activity
10.000 km(s) Time Required hrs
Rate
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Dump Travel (Empty)
30.00
50.00
Total Productivity
AHD= 10.000 km(s)
AHD = Time-Motion Table Activity
30.00
50.00
AHD= 15.000 km(s)
Activity
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Dump Travel (Empty)
5.00 13.67 21.08 5.00 2.00 12.00
0.98
58.76
6.89 m3/hr
Time Required hrs
Rate
Total
AHD = Time-Motion Table
0.08 0.23 0.35 0.08 0.03 0.20
15.000 km(s)
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Dump Travel (Empty)
Productivity
Time Required minutes
Time Required minutes
0.08 0.23 0.50 0.08 0.03 0.30
5.00 13.67 30.00 5.00 2.00 18.00
1.23
73.67
5.50 m3/hr
20.000 km(s) Time Required hrs
Rate
30.00
50.00
0.08 0.23 0.67 0.08 0.03 0.40
Time Required minutes
5.00 13.67 40.00 5.00 2.00 24.00
Total Productivity
1.49 AHD= 20.000 km(s)
AHD = Time-Motion Table Activity
Time Required hrs
Rate
30.00
50.00
Total AHD= 25.000 km(s)
AHD = Time-Motion Table Activity
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Dump Travel (Empty)
Time Required minutes
0.08 0.23 0.83 0.08 0.03 0.50
5.00 13.67 50.00 5.00 2.00 30.00
1.76
105.67
3.83 m3/hr
30.000 km(s) Time Required hrs
Rate
30.00
50.00
Total Productivity
4.52 m3/hr
25.000 km(s)
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Dump Travel (Empty)
Productivity
89.67
AHD= 30.000 km(s)
Time Required minutes
0.08 0.23 1.00 0.08 0.03 0.60
5.00 13.67 60.00 5.00 2.00 36.00
2.03
121.67
3.33 m3/hr
PRODUCTIVITY CALCULATIONS Asphalt Hauling by Dump Truck
Equipment Specifications Parameter Loaded Speed Empty Speed Load Capacity Load Capacity Fuel Consumption Unloading Rate
Dump Truck Quantity 30.00 60.00 10.50 23.10 15.00 39.30
### Unit km/hr km/hr m3 tons li/hr mins/truckload
Equipment Specifications Parameter Loading Rate
Asphalt Plant Quantity 85.00
Cap = 100.00 tph Unit tons/hr
Quantity
Unit tons/m3
Asphalt Specifications Parameter Density AHD = Time-Motion Table Activity
2.20 5.000 km(s)
Time Required hrs
Rate
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Dump Travel (Empty)
30.00
60.00
Total
Time Required minutes
0.08 0.27 0.17 0.08 0.65 0.08
5.00 16.31 10.00 5.00 39.30 5.00
1.34
80.60
Productivity
AHD= 5.000 km(s)
7.82 m3/hr
Productivity
AHD= 5.000 km(s)
17.20 tons/hr
AHD = Time-Motion Table Activity
Maneuver & Wait Wait While Loading
7.000 km(s)
Rate
Time Required hrs
0.08 0.27
Time Required minutes
5.00 16.31
Travel (Loaded) Maneuver & Wait Dump Travel (Empty)
30.00
60.00
Total
0.23 0.08 0.65 0.12
14.00 5.00 39.30 7.00
1.44
86.60
Productivity
AHD= 7.000 km(s)
7.27 m3/hr
Productivity
AHD= 7.000 km(s)
16.00 tons/hr
AHD = Time-Motion Table Activity
10.000 km(s) Time Required hrs
Rate
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Dump Travel (Empty)
30.00
60.00
Total
Time Required minutes
0.08 0.27 0.35 0.08 0.65 0.17
5.00 16.31 21.08 5.00 39.30 10.00
1.61
96.69
Productivity
AHD= 10.000 km(s)
6.52 m3/hr
Productivity
AHD= 10.000 km(s)
14.33 tons/hr
AHD = Time-Motion Table Activity
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Dump Travel (Empty)
15.000 km(s) Time Required hrs
Rate
30.00
60.00
Total
Time Required minutes
0.08 0.27 0.50 0.08 0.65 0.25
5.00 16.31 30.00 5.00 39.30 15.00
1.84
110.60
Productivity
AHD= 15.000 km(s)
5.70 m3/hr
Productivity
AHD= 15.000 km(s)
12.53 tons/hr
AHD = Time-Motion Table Activity
20.000 km(s) Time Required hrs
Rate
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Dump Travel (Empty)
30.00
60.00
Total
Time Required minutes
0.08 0.27 0.67 0.08 0.65 0.33
5.00 16.31 40.00 5.00 39.30 20.00
2.09
125.60
Productivity
AHD= 20.000 km(s)
5.02 m3/hr
Productivity
AHD= 20.000 km(s)
11.03 tons/hr
AHD = Time-Motion Table Activity
25.000 km(s) Time Required hrs
Rate
Maneuver & Wait Wait While Loading Travel (Loaded) Maneuver & Wait Dump Travel (Empty)
30.00
60.00
Total
Time Required minutes
0.08 0.27 0.83 0.08 0.65 0.42
5.00 16.31 50.00 5.00 39.30 25.00
2.34
140.60
Productivity
AHD= 25.000 km(s)
4.48 m3/hr
Productivity
AHD= 25.000 km(s)
9.86 tons/hr
AHD = Time-Motion Table Activity
Maneuver & Wait Wait While Loading
30.000 km(s)
Rate
Time Required hrs
0.08 0.27
Time Required minutes
5.00 16.31
Travel (Loaded) Maneuver & Wait Dump Travel (Empty)
30.00
60.00
Total
1.00 0.08 0.65 0.50
60.00 5.00 39.30 30.00
2.59
155.60
Productivity
AHD= 30.000 km(s)
4.05 m3/hr
Productivity
AHD= 30.000 km(s)
8.91 tons/hr
PRODUCTIVITY CALCULATIONS
PC Girder Setting AASHTO TYPE 1
Length :
Equipment Specifications Parameter Forward Speed Reverse Speed Lifting Capacity Fuel Consumption
Crane 80.00 Tons Quantity 2.00 2.00 80.00 27.00
Unit km/hr km/hr tons li/hr
Remarks
Rate
Time Required hrs
Time Required minutes
Time-Motion Table Activity
8.000 m
Equipment Mobilization / Waiting Mobilization/Waiting
0.75
45.00
Loading/Unloading Tie/Rig Girder Swing-Hoist Up-Swing-Hoist Up Set - Hoist Down - Untie/Rig Girder Swing-Hoist Up
0.25 0.42 0.25 0.17
15.00 25.00 15.00 10.00
Demobilization Demobilization
0.50
30.00
2.33
140.00
Total Number of Units Total Time for 2 Units
2 nos. 4.67 hrs
Productivity
1.71 lm/hr
AASHTO TYPE 2
Length :
Equipment Specifications Parameter Forward Speed Reverse Speed Lifting Capacity Fuel Consumption
Crane 80.00 Tons Quantity 2.00 2.00 80.00 27.00
Time-Motion Table Activity
Rate
10.000 m
Unit km/hr km/hr tons li/hr
Remarks
Time Required
Time Required
Activity
Rate
hrs
minutes
Equipment Mobilization / Waiting Mobilization/Waiting
0.75
45.00
Loading/Unloading Tie/Rig Girder Swing-Hoist Up-Swing-Hoist Up Set - Hoist Down - Untie/Rig Girder Swing-Hoist Up
0.25 0.47 0.25 0.17
15.00 28.00 15.00 10.00
Demobilization Demobilization
0.50
30.00
2.38
143.00
Total Number of Units Total Time for 2 Units
2 nos. 4.77 hrs
Productivity
2.10 lm/hr
AASHTO TYPE 3
Length :
Equipment Specifications Parameter Forward Speed Reverse Speed Lifting Capacity Fuel Consumption
Crane 80.00 Tons Quantity 2.00 2.00 80.00 27.00
Unit km/hr km/hr tons li/hr
Remarks
Rate
Time Required hrs
Time Required minutes
Time-Motion Table Activity
18.000 m
Equipment Mobilization / Waiting Mobilization/Waiting
0.75
45.00
Loading/Unloading Tie/Rig Girder Swing-Hoist Up-Swing-Hoist Up Set - Hoist Down - Untie/Rig Girder Swing-Hoist Up
0.25 0.50 0.25 0.17
15.00 30.00 15.00 10.00
Demobilization Demobilization
0.50
30.00
2.42
145.00
Total
Number of Units Total Time for 2 Units
2 nos. 4.83 hrs
Productivity
3.72 lm/hr
AASHTO TYPE 4
Length :
Equipment Specifications Parameter Forward Speed Reverse Speed Lifting Capacity Fuel Consumption
Crane 80.00 Tons Quantity 2.00 2.00 80.00 27.00
Unit km/hr km/hr tons li/hr
Remarks
Rate
Time Required hrs
Time Required minutes
Time-Motion Table Activity
30.000 m
Equipment Mobilization / Waiting Mobilization/Waiting
0.75
45.00
Loading/Unloading Tie/Rig Girder Swing-Hoist Up-Swing-Hoist Up Set - Hoist Down - Untie/Rig Girder Swing-Hoist Up
0.25 0.58 0.25 0.17
15.00 35.00 15.00 10.00
Demobilization Demobilization
0.50
30.00
2.50
150.00
Total Number of Units Total Time for 2 Units
2 nos. 5.00 hrs
Productivity
6.00 lm/hr
AASHTO TYPE 5
Length :
Equipment Specifications Parameter Forward Speed Reverse Speed Lifting Capacity Fuel Consumption
Crane 80.00 Tons Quantity 2.00 2.00 80.00 27.00
40.000 m
Unit km/hr km/hr tons li/hr
Remarks
Time-Motion Table Activity
Rate
Time Required hrs
Time Required minutes
Equipment Mobilization / Waiting Mobilization/Waiting
0.75
45.00
Loading/Unloading Tie/Rig Girder Swing-Hoist Up-Swing-Hoist Up Set - Hoist Down - Untie/Rig Girder Swing-Hoist Up
0.25 0.67 0.25 0.17
15.00 40.00 15.00 10.00
Demobilization Demobilization
0.50
30.00
2.58
155.00
Total Number of Units Total Time for 2 Units
2 nos. 5.17 hrs
Productivity
7.74 lm/hr
PRODUCTIVITY CALCULATIONS PC Panel Hauling by Truck with Lifting Crane
Equipment Specifications Parameter Loaded Speed Empty Speed Actual Capacity : 100.000% Fuel Consumption Loading/Unloading Rate
Boom Truck Quantity 30.00 50.00 20.00 15.00 20.00
Cap = 20.00 tons Unit km/hr km/hr tons li/hr tons/hr
Self Loading AHD = Time-Motion Table Activity
5.000 km(s) Time Required hrs
Rate
Maneuver & Wait Load Travel (Loaded) Maneuver & Wait Unload Travel (Empty)
30.00
50.00
Total Productivity
AHD= 5.000 km(s)
AHD = Time-Motion Table Activity
Maneuver & Wait Load Travel (Loaded) Maneuver & Wait Unload Travel (Empty)
0.08 1.00 0.17 0.08 1.00 0.10
5.00 60.00 10.00 5.00 60.00 6.00
2.43
146.00
8.22 tons/hr
7.000 km(s) Time Required hrs
Rate
30.00
50.00
Total Productivity
Time Required minutes
AHD= 7.000 km(s)
Time Required minutes
0.08 1.00 0.23 0.08 1.00 0.14
5.00 60.00 14.00 5.00 60.00 8.40
2.54
152.40
7.87 tons/hr
AHD = Time-Motion Table Activity
10.000 km(s) Time Required hrs
Rate
Maneuver & Wait Load Travel (Loaded) Maneuver & Wait Unload Travel (Empty)
30.00
50.00
Total Productivity
AHD= 10.000 km(s)
AHD = Time-Motion Table Activity
30.00
50.00
AHD= 15.000 km(s)
Activity
Maneuver & Wait Load Travel (Loaded) Maneuver & Wait Unload Travel (Empty)
5.00 60.00 21.08 5.00 60.00 12.00
2.72
163.08
7.36 tons/hr
Time Required hrs
Rate
Total
AHD = Time-Motion Table
0.08 1.00 0.35 0.08 1.00 0.20
15.000 km(s)
Maneuver & Wait Load Travel (Loaded) Maneuver & Wait Unload Travel (Empty)
Productivity
Time Required minutes
Time Required minutes
0.08 1.00 0.50 0.08 1.00 0.30
5.00 60.00 30.00 5.00 60.00 18.00
2.97
178.00
6.74 tons/hr
20.000 km(s) Time Required hrs
Rate
30.00
50.00
0.08 1.00 0.67 0.08 1.00 0.40
Time Required minutes
5.00 60.00 40.00 5.00 60.00 24.00
Total Productivity
3.23 AHD= 20.000 km(s)
AHD = Time-Motion Table Activity
Time Required hrs
Rate
30.00
50.00
Total AHD= 25.000 km(s)
AHD = Time-Motion Table Activity
Maneuver & Wait Load Travel (Loaded) Maneuver & Wait Unload Travel (Empty)
Time Required minutes
0.08 1.00 0.83 0.08 1.00 0.50
5.00 60.00 50.00 5.00 60.00 30.00
3.50
210.00
5.71 tons/hr
30.000 km(s) Time Required hrs
Rate
30.00
50.00
Total Productivity
6.19 tons/hr
25.000 km(s)
Maneuver & Wait Load Travel (Loaded) Maneuver & Wait Unload Travel (Empty)
Productivity
194.00
AHD= 30.000 km(s)
Time Required minutes
0.08 1.00 1.00 0.08 1.00 0.60
5.00 60.00 60.00 5.00 60.00 36.00
3.77
226.00
5.31 tons/hr