41 0 85KB
PRODUCTIVITY RATES
01 GENERAL RE a.
SITE FACILITIES
b. c. d.
02 SITE W Excavation a. b. c. d. e.
EARTHWORK
f.
Backfilling a. b. c. d.
Interlock Paving a. b. c.
PAVING & SURFACING
d.
Precast Kerb Stone a. b. c. d.
03 CONC
Shuttering (with supports) a. b. c. d. e. f. g. h.
CONCRETE FORMWORK
i. j. k. l. m. n. o. p. s. u. t.
Reinforcement (Lightening for Cut & Bend Steel) a. b. c. d. e. f.
REINFORCEMENT
g. h. i. j.
REINFORCEMENT
k. l. l.
Mesh Reinforcement a.
Casting Concreting (Readymix) a. b. c. d. e. f. g. h. i.
PLACE CONCRETE
j. k. l. m. n. o. p. q. r. s. u. v.
04 MASO Solid Block a.
Hollow Block a. b.
c. d. e. f. g.
Claustra Block a. b.
05 MET Steel Structure a. b. c. d. e. f.
STRUCTURAL STEEL
g. h. i. j. k. l. m. n. o.
07 MOISTURE THE Polythene Sheets a. b. c.
Bitumin Paint a. b.
Bituminous Membranes a.
Construction Joints a. b.
09 FINI Internal Plaster a. b. c. d. e.
PLASTER
f.
External Plaster a. b. c.
Mosaic a. b. c. d.
Ceramic a. b. c. d. e.
TILING
f. g. h.
PVC Tiles a. b.
Marble a. b. c. d.
Floor Screed (50mm) a.
SCREED
b.
Wooden Skirting a.
Threshold a.
False Ceiling a.
Dry Wall Partition a.
Tyrolene (Cullamix) a. b.
Normal Paint (Emulsion Oil) WALL COVERINGS
a. c. d. e.
Epoxy Painting a.
15 MECHA
Copper & PVC Pipes PLUMBING INSTALLATIONS
a. b. c. d.
Plumbing Fixtures a. b. c.
PLUMBING FIXTURES
d. e. f. g. h. i.
PLUMBING APPLIANCES
Plumbing Appliances a.
16 ELECT
RACE WAYS
Race Ways a. b.
CONDUCTORS Conductors & Grounding & GROUNDING
WIRING
a.
Wiring a.
BOARDS
Boards a. b.
PRODUCTIVITY RATES 01 GENERAL REQUIREMENT Watchman & Curing
(Duration x 2H)
Site Cleaning
(Dhs. Contract value/ 50,000) Helper-Day
Fencing
1C + 2H + 1P
Fixing of Light Weight Scaffolding
1C + 1H
02 SITE WORK
Soft Soil (Hand Tools)
1H
Hard Soil (Hand Tools)
1H
Soft Soil
-
Hard Soil
-
Soft Soil
-
Hard Soil
-
Filling in foundation, pinth
-
Level, Compaction
1H
Spreading 200mm layer (Subkha, Road Base)
-
Compaction 200mm layer (Subkha, Road Base)
1H
Compaction / Levelling
2H
Spreading Sand and Brushing
2H
Laying Tiles
1M+2H
Filling, Compaction
1H
Excavation & Blinding for Curbstone
1H
Laying Kerbs
1M+2H
Karb stone on curved lines
1M+1H
Hunching
1M+1H
03 CONCRETE
Shutt. of Blinding
1C+1H
Shutt. of Footing (Plywood)
1C+1H
Shutt. of Footing (Plates)
1C+1H
Shutt. of Slub Column
1C+1H
Shutt. of Strap / Tie Beam (Plywood)
1C+1H
Shutt. of Strap / Tie Beam (Plates)
1C+1H
Shutt. of Wall
1C+1H
Shutt. of Column 20x20
1C+1H
Shutt. of Column 20x40
1C+1H
Shutt. of Beam with support
1C+1H
Shutt. of Roof Slab
1C+2H
Shutt. of Lintel
1C+1H
Shutt. of Copying Beam 20x20cm
1C+1H
Shutt. of Parapet
1C+1H
Shutt. of Arch Lintel
1C+1H
Expansion Joints / Ground Slab
1C+1H
Shutt. of Beam & Column for 8m to 12m high
1C+1H
Shutt. of Staircase
1C+1H
De-shuttering Works
20% of Shuttering Works
Reinf. of Footing
1 SF + 1 H
Reinf. of Slub Column
1 SF + 1 H
Reinf. of Strap Beam
1 SF + 1 H
Reinf. of Tie Beam
1 SF + 1 H
Reinf. of Wall
1 SF + 1 H
Reinf. of Column
1 SF + 1 H
Reinf. of Beam
1 SF + 1 H
Reinf. of Solid Slab
1 SF + 1 H
Reinf. of Lintel
1 SF + 1 H
Reinf. Copying Beam 20x20cm
1 SF + 1 H
Reinf. of Parapet
1 SF + 1 H
Reinf. of Arch Lintel
1 SF + 1 H
Reinf. of Staircase
1 SF + 1 H
Mesh Reinforcement
1 SF + 2 H
Cast. Blinding 5cm
1M+2H
Cast. Blinding 10cm
1M+2H
Cast. Blinding 5cm, 10cm
2M+4H
Cast. of Footing
2M+4H
Cast. of Footing (Pump)
3M+8H
Cast. of Strap / Tie Beam
1M+6H
Cast. of Tie Beam (Pump)
2M+6H
Cast. of Ground Floor Slab 10cm
3M+5H
Cast. of Ground Floor Slab 15cm
3M+5H
Cast. of Ground Floor Slab 20cm
3M+5H
Cast. of Wall
1M+1C+3H
Cast. of Column
1M+4H
Cast. of Beam of Slab
1M+4H
Cast. of Roof Slab
2M+2C+5H
Cast. of Lintel
1M+2H
Cast. of Copying Beam 20x20cm (up to2.5m)
1C+5H
Cast. of Copying Beam 20x20cm (above 2.5m)
1C+5H
Cast. of Parapet
1M+1C+4H
Cast. of Arch Lintel
1M+3H
Casting of Neck Column
1M+3H
Casting of Staircase
1C+1H
04 MASONRY 200mm Solid Block up to 2.5m Height
1M+2H
100mm Hollow Block up to 2.5m Height
1M+1H
100mm Hollow Block - 2.5m to 6m Height
1M+2H
150mm Hollow Block up to 2.5m Height
1M+1H
200mm Hollow Block up to 2.5m Height
1M+1H
200mm Hollow Block - 2.5m to 6m Height
1M+2H
200mm Block Work above 6m Height
1M+2H
200mm Block Work including pointing
1M+1H
Claustra Block 200x200
1M+1H
Claustra Block 150x150
1M+1H
05 METALS
Painting for steel structure columns
1P+1H
Painting for steel structure rafters
1P+1H
Erection of steel structure main frame ( Eave Height up to 6m span up to 25m) Erection of steel structure main frame ( Eave Height up to 6m span up to 36m) Fixing of Single Skin Sheet (Roof)
3E+3H
Fixing of Single Skin Sheet (Walls)
3E+3H
Single skin with Fibre Glass Insulation (Roof)
3E+3H
Single skin with Fibre Glass Insulation (Wall)
3E+3H
Sandwich Panels (Roof)
3E+3H
Sandwich Panels (Wall)
3E+3H
Corner Fisshing & Trims, etc
1E+3H
4m x 4m Double Sliding Door
1E+3H
Wall or Roof opening + Frames (1.0mx1.0m)
1E+3H
Ridge Ventilator
1E+3H
Gutter / Down Spout
1E+3H
3E+3H 3E+3H
07 MOISTURE THERMAL CONTROL
Polythene under footings
1C+1H
Polythene under slab
1C+1H
Polythene under tie beam
1H
Cold Bituminous Painting
1H
Hot Bituminous Painting
2H
Bituminous Membrane + Protection Board
1C+1H
Flexel Board
1C+1H
Sealant
1H
09 FINISHES Ceiling Plaster
1M+1H
Wall Plaster up to 3m Height
1M+1H
Wall Plaster 3m to 6m Height
1M+2H
Wall Plaster above 6m Height
1M+2H
Fixing of Plaster Mesh
1C+1H
Fixing of Corner Beed
1M+1H
Wall Plaster up to 3m Height
1M+1H
Wall Plaster 3m to 6m Height
1M+2H
Wall Plaster above 6m Height
1M+2H
Floor Mosaic Tiles
1M+1H
Mosaic Skirting
1M+1H
Mosaic Steps (Riser & Tread)
1M+1H
Mosaic Polishing
1 Po + 1 H
Fixing of Ceramic Wall Tiles (Glur Type)
1M+1H
Grouting of Ceramic Wall Tiles
1M+1H
Fixing of Ceramic Wall Tiles (Cement Monar Type)
1M+1H
Fixing of Ceramic Floor Tiles 20x20cm
1M+1H
Fixing of Ceramic Floor Tiles 30x30cm
1M+1H
Fixing of Ceramic Floor Tiles 50x50cm
1M+1H
Grouting of Ceramic Floor Tiles
1M+1H
Ceramic Skirting
1M+1H
PVC Tiles
1M+1H
PVC Skirting
1M+1H
Marble Wall
1M+1H
Marble Floor
1M+1H
Marble Skirting
1M+1H
Marble Steps (Riser & Treads)
1M+1H
Floor Screed (50mm)
1M+1H
Cement Skirting
1M+1H
Timber
1C+1H
Threshold
1M
False Ceiling - Suspended Type
1C+1H
Dry Wall Partition
1C+1H
Tyrolene over plastered surface
1M+1H
Tyrolene over block wall
1M+1H
Primer
1P
Stucco (Putty)
1P
Emulsion Paint
1P
Oil Paint
1P
Epoxy Painting
1P+1H
15 MECHANICAL
1/2" to 1" Copper Pipe (Hot water)
1 Pl + 1 H
1/2" to 1 1/2" PVC Pipe
1 Pl + 1 H
2" to 3" PVC Pipe
1 Pl + 1 H
4" to 6" PVC Pipe
1 Pl + 1 H
Shower Tray
1 Pl + 1 H
Kitchen Sink
1 Pl + 1 H
Urinals + Partition
1 Pl + 1 H
Wash Basin
1 Pl + 1 H
W/C Asian
1 Pl + 1 H
W/C Western
1 Pl + 1 H
Bidet
1 Pl + 1 H
Booster Pump
1 Pl
Manhole 60cm to 90cm
1M+1H
Water Heater
1 Pl + 1 H
16 ELECTRICAL
Conduits
1 El + 1 H
Trunking
1 El + 1 H
Laying Cables
1 El + 2 H
Wiring
1 El + 1 H
D.B's
1 El + 1 H
M.D.B's
1 El + 1 H
C=Carpenter, M=Mason, P=Painter, SF=Steel Fitter, E=Erector, H=Helper, Po=Polisher, Elec=El, Pl=Plumber One Day is considered as 8 working hours.
Rev. 01
02/11/05
Day
-
Day
1
Rm/Day
50
M2/Day
70
Hand Tools
M3/Day
3
Hand Tools
M3/Day
1
Shovel
M3/Hr
40
Shovel
M3/Hr
25
JCB
M3/Hr
20
J.C.B.
M3/Hr
10
Shovel
M3/Hr
30
Roller Compr.
M2/Day
100
Shovel
M2/Hr
100
Roller Compr.
M2/Day
200
Roller Compr.
M2/Day
200
M2/Day
200
M2/Day
60
M2/Day
150
R.M/Day
10
R.M/Day
35
R.M/Day
15
R.M/Hr
20
Plate Compr.
M2/Day
35
M2/Day
15
M2/Day
20
M2/Day
5
M2/Day
12
M2/Day
20
M2/Day
14
M2/Day
10
M2/Day
10
M2/Day
12
M2/Day
10
M2/Day
6
M2/Day
6
M2/Day
12
M2/Day
6
L.M/Day
70
M2/Day
8
M2/Day
12
KG/Day
400
KG/Day
250
KG/Day
300
KG/Day
350
KG/Day
400
KG/Day
300
KG/Day
300
KG/Day
300
KG/Day
150
KG/Day
200
Pump
Pump
Pump
Pump
Pump
Pump
KG/Day
300
KG/Day
150
KG/Day
250
M2/Day
300
M2/Day
30
M2/Day
40
M2/Day
250
M3/Day
40
M3/Day
120
M3/Day
20
M3/Day
50
M3/Day
30
M3/Day
45
M3/Day
50
M3/Day
40
M3/Day
4
M3/Day
12
M3/Day
50
Nos./Hr
4
RM/Day
150
RM/Day
60
M3/Day
10
M3/Day
5
M3/Day
4
M3/Day
12
Nos./Day
140
Nos./Day
150
Nos./Day
140
Nos./Day
150
Nos./Day
180
Nos./Day
140
Nos./Day
100
Nos./Day
120
M2/Day
10
M2/Day
8
M2/Day/ Coat M2/Day/ Coat M2/Day
50 250
M2/Day
175
M2/Day
350
M2/Day
150
M2/Day
250
M2/Day
100
M2/Day
250
M2/Day
150
Rm/Day
80
40
No.
1
No.
8
No./Day
6
Rm/Day
70
M2/Day
200
M2/Day
1000
Rm/Day
200
M2/Day/ Coat M2/Day/ Coat
100 60
M2/Day
30
RM/Hr
18
RM/Hr
7
M2/Day
10
M2/Day
20
M2/Day
17
M2/Day
15
Rm/Day
90
Rm
30
M2/Day
20
M2/Day
18
M2/Day
15
M2/Day
15
Rm/Day
40
Rm/Day
14
M2/Day
100
M2/Day
10
M2/Day
30
M2/Day
8
M2/Day
12
M2/Day
15
M2/Day
20
M2/Day
40
Rm/Day
30
M2/Day
35
Lm/Day
40
M2/Day
6
M2/Day
15
Rm/Day
30
Rm/Day
10
M2/Day
50
Rm/Day
25
Rm/Day
100
Rm/Day
10
M2/Day
30
M2/Day
20
M2/Day/ Coat M2/Day/ Coat
100
M2/Day/ Coat M2/Day/ Coat M2/Day/ Coat M2/Day/ Coat
200
M2/Day/ Coat
50
R.M/Day
12
R.M/Day
20
R.M/Day
75
R.M/Day
60
100
80 100 60
Nos./Day
2
Nos./Day
2
Nos./Day
3
Nos./Day
2
Nos./Day
2
Nos./Day
2
Nos./Day
2
Nos./Day
1
Nos./Day
2
Nos./Day
2
R.M/Day
50
R.M/Day
50
R.M/Day
150
R.M/Day
300
Nos./Day
2
Nos./Day
1