MUSE MRL ACD3 CONTROLLER
Date : 7 Aug 2012 Sheet / Sheets : 1 / 42 DOC No.: Draft
Testing & Commissioning MSK Operation (Start-up)
1. Controller Installation Install the controller, LCRD(Regen Drive), ARO & EIP according to a shop drawing. Controller UD/LCRD* ARO E&I Panel Model Standard Standard Option Standard Muse Top floor Overhead landing *) ”Regen” logo is indicated at the box of LCRD & UD.
[Data plate for LCRD(or UD)] [LCRD (or UD)]
Unpublished Work Copyright © OTIS Elevator Company
MUSE MRL ACD3 CONTROLLER
Date : 7 Aug 2012 Sheet / Sheets : 2 / 42 DOC No.: Draft
Testing & Commissioning MSK Operation (Start-up)
1.1. Controller Install controller as following figures.
< Steel beam structure >
< Steel beam structure with ARO >
< Concrete structure >
< Concrete structure with ARO >
*) The function of ARO is equal to the function of ARD (or ALP)
Unpublished Work Copyright © OTIS Elevator Company
MUSE MRL ACD3 CONTROLLER
Date : 7 Aug 2012 Sheet / Sheets : 3 / 42 DOC No.: Draft
Testing & Commissioning MSK Operation (Start-up)
1.2. EIP (E&I Panel) Install EIP at top landing as following photos
EIP
Fixing bracket
Unpublished Work Copyright © OTIS Elevator Company
MUSE MRL ACD3 CONTROLLER
Date : 7 Aug 2012 Sheet / Sheets : 4 / 42 DOC No.: Draft
Testing & Commissioning MSK Operation (Start-up)
[Shop drawing]
Unpublished Work Copyright © OTIS Elevator Company
MUSE MRL ACD3 CONTROLLER
Date : 7 Aug 2012 Sheet / Sheets : 5 / 42 DOC No.: Draft
Testing & Commissioning MSK Operation (Start-up)
Model Muse MMR
Controller Standard
UD/LCRD ARO Standard Option Machine room
Unpublished Work Copyright © OTIS Elevator Company
EIP Standard
MUSE MRL ACD3 CONTROLLER
Date : 7 Aug 2012 Sheet / Sheets : 6 / 42 DOC No.: Draft
Testing & Commissioning MSK Operation (Start-up)
2. Machine room wiring GeN2 MMR(w/ LCRD) GeN2 MRL KAA21311AB 2.1. 3 phases wiring [Building DB EIP] R – S – T, N(Neutral) & Earth shall be provided to EIP.
[EIP] R – S – T, N(Neutral) & Earth (EIP to Controller)
TB2
Unpublished Work Copyright © OTIS Elevator Company
MUSE MRL ACD3 CONTROLLER
Date : 7 Aug 2012 Sheet / Sheets : 7 / 42 DOC No.: Draft
Testing & Commissioning MSK Operation (Start-up)
2.2. Lighting power wiring [EIP Controller] No need for lighting power from building DB. Connect 1 of 3 phases and neutral.
4E
R S T N
4E of controller (Car fan & light)
Hoistway & pit light
Unpublished Work Copyright © OTIS Elevator Company
MUSE MRL ACD3 CONTROLLER
Date : 7 Aug 2012 Sheet / Sheets : 8 / 42 DOC No.: Draft
Testing & Commissioning MSK Operation (Start-up)
2.3. 3 phases wiring [Controller Drive (UD, LCRD, 60CR)] -.OVFR3B-401/402 UD – w/o ARO
TB1
TB2
-.OVFR2B-403/404 & OVF2A-406(60CR)
TB2
TB1
Unpublished Work Copyright © OTIS Elevator Company
TB1
MUSE MRL ACD3 CONTROLLER
Date : 7 Aug 2012 Sheet / Sheets : 9 / 42 DOC No.: Draft
Testing & Commissioning MSK Operation (Start-up)
2.4. 3 phases wiring [Drive (UD, LCRD, 60CR) Motor] -.OVFR3B-401/402 UD – ARO+GGP 1.5T, 2.0T
TB7
PIN -.OVFR2B-403/404 – optimized 2.6T, 3.2T, 4.1T
TB7
U,V,W
Unpublished Work Copyright © OTIS Elevator Company
MUSE MRL ACD3 CONTROLLER
Date : 7 Aug 2012 Sheet / Sheets : 10 / 42 DOC No.: Draft
Testing & Commissioning MSK Operation (Start-up)
2.5. Connection [Controller EIP] GeN2 MMR(w/ LCRD) GeN2 MRL KAA21311AB
Field panel
SPBC-2
AP-I/O
START 1E 3E 4E P4M PX5
CONN. 8P 8P 2P 9P 8P
Function Safety line at hoistway, brake power Landing door jumper Car lighting (220Vac) ERO line for EPI CAN communication
END EC1 EC3 FSK1 EC2 SPBC-P100
Unpublished Work Copyright © OTIS Elevator Company
CONN. 8P 7P TERM 9P 9P
MUSE MRL ACD3 CONTROLLER
Date : 7 Aug 2012 Sheet / Sheets : 11 / 42 DOC No.: Draft
Testing & Commissioning MSK Operation (Start-up)
2.1.6. Connection between controller & drive -.OVFR3B-401/402 UD
Field panel DCPB
AP-I/O
START CONN. Function (Field panel) 1D 4P CAN Communication 2D 4P UIB/DIB power (110Vac) 3D 2P Brake power (GGP) 5D 4P Brake_SFC 6D 3P Brake_I-BRK 10D 7P Brake power (24Vdc), BS1/2 Signal (BOMCO-W) PX8 7P PRS
END (Drive) P2(DCPB) P1(DCPB) P5(DCPB) P21(DCPB) P8(DCPB) P7(DCPB)
CONN.
P3(DCPB)
5P
Unpublished Work Copyright © OTIS Elevator Company
4P 4P 4P 4P 3P 6P
MUSE MRL ACD3 CONTROLLER
Date : 7 Aug 2012 Sheet / Sheets : 12 / 42 DOC No.: Draft
Testing & Commissioning MSK Operation (Start-up)
-.OVFR2B-403/404 LCRD
START CONN. Function (Field panel) 1D 4P CAN communication 2D 4P UIB/DIB power(110Vac) 3D 2P Brake power 5D 4P Brake_SFC(MRL) 6D 3P Brake_I-BRK 10D 7P Brake power(24Vdc), BS1/2 signal (BOMCO-W) PX8 7P PRS(1LV, 2LV, UIS,DIS, THB)
END
CONN.
P8(GDCB) P11(GDCB) P111(HVIB) P102(HVIB) P6(HVIB) P5(GDCB)
4P 10P 4P 4P 3P 7P
P6(GDCB)
9P
-.OVFR2A-406 60CR
START (Field panel) 1D 2D 5D
CONN.
Function
4P 4P 4P
CAN communication UIB/DIB ower (110Vac) Brake_SFC, BRK power(24Vdc)
PX8
7P
PRS(1LV, 2LV, UIS, DIS, THB)
END (Drive) P8(GDCB) P11(GDCB) P102(PDB2) P6(GDCB)
Unpublished Work Copyright © OTIS Elevator Company
CONN. 4P 10P 4P 9P
MUSE MRL ACD3 CONTROLLER
Date : 7 Aug 2012 Sheet / Sheets : 13 / 42 DOC No.: Draft
Testing & Commissioning MSK Operation (Start-up)
2. 7. Connection between DRIVE & MOTOR_BRK -.OVFR3B-401/402 UD + GGP 1.5T, 2.0T
START P7 P8
CONN. 6P 3P
Function BS1, BS2(Machine brake), THB 140C BRK DC+, BRK DC-
END P2 P1
CONN. 6P 3P
BRK_DC+ P1:1
P8:1
B
M
B
P8:2 BRK_DC- P1:3
B1
BRK power
PE
P1:2
P8:3
U
BV
B
Machine
P7:2
BS1
P7:3 BS2
P7:1 24V P7:4
Return
Machine
P2 1
1/BN
P2 3
4/BK
P2 2
3/BU
P2 4
1/BN
P2 6
4/BK
P2 5
3/BU
BS1
BRK S/W BS2
Machine W/ BS Machine W/O BS
Unpublished Work Copyright © OTIS Elevator Company
MUSE MRL ACD3 CONTROLLER
Date : 7 Aug 2012 Sheet / Sheets : 14 / 42 DOC No.: Draft
Testing & Commissioning MSK Operation (Start-up)
-.OVFR3B-401/402 UD + BOMCO-W START 7D 4D
CONN. 4P 3P
4D 1
Function BS1, BS2(Machine brake), THB 140C BRK DC+, BRK DC-, BRK_PE
END P2
P2:5
BRK_DC+ B
BV 4D 3
U
P2:6 BRK_DC4D 2
P2:9
PE
Machine
NC1
P2:2
COM1 P2:1
7D 1 BS1 7D 3 BSR*30VDC
NO1
NC2
BS2
BRK power
B1
B
BRK_PE
BS1
M
B
7D 4 BS2 P2:4
7D 2
COM2 P2:3 NO2
Machine Brake
Unpublished Work Copyright © OTIS Elevator Company
BRK S/W
CONN. TERM TERM
MUSE MRL ACD3 CONTROLLER
Date : 7 Aug 2012 Sheet / Sheets : 15 / 42 DOC No.: Draft
Testing & Commissioning MSK Operation (Start-up)
-.OVFR2B-403/404 LCRD + GGP/Optimized 2.6T, 3.2T, 4.1T
START P5 4D
4D 1
CONN. 7P 3P
Function BS1, BS2(Machine brake) BRK DC+, BRK DC-
P5:1
P1:1 BRK_DC+
M
P1:3
U
BV
B1
CONN. 6P 3P
BS1
BRK S/W
B
B 4D 3
END P2 P1
P5:2 BS2
BRK_DC4D 2
P1:2
PE
P5:3
B
Machine
P5:4
P5:6 P5:7
BRK power
Machine
P2 1
1/BN
P2 3
4/BK
P2 2
3/BU
24V P2 4
1/BN
P2 6
4/BK
P2 5
3/BU
Return
Machine W/O BS Machine W/ BS
Unpublished Work Copyright © OTIS Elevator Company
BS1
BS2
MUSE MRL
Date : 7 Aug 2012 Sheet / Sheets : 16 / 42 DOC No.: Draft
ACD3 CONTROLLER
Testing & Commissioning MSK Operation (Start-up)
-.OVFR2B-403/404 LCRD +WAN-YUAN/BOMCO-W START 7D 4D
CONN. 4P 3P
4D 1
Function BS1, BS2(Machine brake), THB 140C BRK DC+, BRK DC-, BRK_PE
END P2 P1
CONN. TERM TERM
P1:1 BRK_DC+
B
M
B 4D 3
P1:3
U
BV
BRK power
B1
BRK_DC4D 2
P1:2
PE B
Machine
NC1
BS1
P2:2
COM1 P2:1
7D 3 BSR*30VDC
NO1
NC2
BS2
7D 1 BS1
7D 4 BS2 P2:4
7D 2
COM2 P2:3 NO2
Machine Brake
Unpublished Work Copyright © OTIS Elevator Company
BRK S/W
MUSE MRL ACD3 CONTROLLER
Date : 7 Aug 2012 Sheet / Sheets : 17 / 42 DOC No.: Draft
Testing & Commissioning MSK Operation (Start-up)
-. OVFR2B-403/404 LCRD/60CR +BOMCO2-S
START 7D 4D
CONN. 4P 3P
Function BS1, BS2(Machine brake), THB 140C BRK DC+, BRK DC-, BRK_PE
4D 1
END P2
CONN. TERM TERM
P2:5
BRK_DC+ B
BV 4D 3
U
P2:6 BRK_DC4D 2
P2:9
PE
Machine
NC1
P2:2
COM1 P2:1
7D 1 BS1 7D 3 BSR*30VDC
NO1
NC2
BS2
B1
B
BRK_PE
BS1
BRK power
M
B
7D 4 BS2 P2:4
7D 2
COM2 P2:3 NO2
Machine Brake
Unpublished Work Copyright © OTIS Elevator Company
BRK S/W
MUSE MRL ACD3 CONTROLLER
Date : 7 Aug 2012 Sheet / Sheets : 18 / 42 DOC No.: Draft
Testing & Commissioning MSK Operation (Start-up)
-. OVFR2B-403/404 LCRD/60CR +BOMCO2-B
START 8D 4D
CONN. 6P 3P
Function BS1, BS2(Machine brake), THB 140C BRK DC+, BRK DC-, BRK_PE
4D 1
END P2
CONN. TERM TERM
P2:5
BRK_DC+ B
BV 4D 3
U
P2:6 BRK_DC4D 2 BRK_PE
BS1 BSR*30VDC
P2:9
B1
PE B
Machine
8D 1
P2:2 NC1
8D 3
P2:1 COM1
8D 4
P2:4 NC2
8D 2
P2:3 COM2
BS2
8D 5
BS3
8D 6
BRK power
M
B
BS1
BS2
P2:6 NC3 P2:5 COM3
BS3
Machine Brake
Unpublished Work Copyright © OTIS Elevator Company
BRK S/W
MUSE MRL ACD3 CONTROLLER
Date : 7 Aug 2012 Sheet / Sheets : 19 / 42 DOC No.: Draft
Testing & Commissioning MSK Operation (Start-up)
2.8. Hoistway wiring
P9
START DCPB(UD) GDCB(LCRD) GDCB(60CR)
CONN. 8P
Function ENC(Rotary Encoder)
START P3M
CONN. 3P
Function Governor (GRS)
START P7
CONN. 5P
Function R-ENC(Sub_Encoder)_MRL
END
CONN.
ENC
8P
END TERM
CONN. 3P
END PIN
CONN. 4P
END (ARO) C1 C3 C2 P3A P3(BCB) P4(BCB)
CONN.
END (ARO) C5
CONN.
END (ARO) C4 TB3
CONN.
2.9. Wiring for ARO (Automatic Rescue Operation) *)MRL START (EIP) EA1 EA2 EA3
EA4
CONN.
Function
10P 4P 9P
UPS_24V, ARO_ST Drive*110V, MRO*BAT+, BAT*VF, BAT*SPB
10P
BAT
*)MRL/MR START CONN. (HIVB) TB9 TERM *)MRL/MR START CONN. (Field panel) 1A 5P 2A 3P
Function MRO+, MRO-
Function CAN_24V, SPB+ ARO*OUT
Unpublished Work Copyright © OTIS Elevator Company
9P 2P 2P 2P 6P 10P
3P
5 TERM
MUSE MRL ACD3 CONTROLLER
Date : 7 Aug 2012 Sheet / Sheets : 20 / 42 DOC No.: Draft
Testing & Commissioning MSK Operation (Start-up)
3. Checking connection of shield cable 3.1. Check the CAN bus cable (from drive to controller) to make sure the shield layer properly connected on both ends of the cable. Attention: Must connect drain wire to PE on both ends of the cable.
Check the drain wire of this cable
3.2. Check the Motor Cable and make sure the shield layer properly connected on both ends of the cable. Attention: Must put the shield layer out of cable skin and use clamps to fasten shield layer of the cable. 3.3. Check the fixing condition of EMC plate Attention: EMC plate must be installed on the sheet metal of Regen drive.
Attention: The cable of rotary encoder must be separated with motor 3 phases cable and the each wire of the encoder cable must be twisted.
Unpublished Work Copyright © OTIS Elevator Company
MUSE MRL ACD3 CONTROLLER
Date : 7 Aug 2012 Sheet / Sheets : 21 / 42 DOC No.: Draft
Testing & Commissioning MSK Operation (Start-up)
1. Shield cable must be earthed 2. The cable must be connected by the clamp.
Unpublished Work Copyright © OTIS Elevator Company
MUSE MRL ACD3 CONTROLLER
Date : 7 Aug 2012 Sheet / Sheets : 22 / 42 DOC No.: Draft
Testing & Commissioning MSK Operation (Start-up)
4. MSK connection 4.1. Prepare MSK tool as following (Korean standard) Items Drawing No. LSD cable AEG16C771*A/B/C/D MSK kit assy. FIE00C682*A Adapter cable AEG01C225*A #2 MSB Unit AEG01C226*A assy. Siren or alarm AEG01C227*B
Q’ty 1 1 1
Remarks Provided by factory Field tool kit assy. MSK adapter cable
1
Pendant switch
1
Siren assy. (A/V)
Jumper kit Asy (Field Tool)
Adapter cable #2 (Field tool) LSD Cable (Factory supply) Note) LSD cable will be used for interphone after MSK operation.
MSB Unit
Unpublished Work Copyright © OTIS Elevator Company
A/V Alarm
MUSE MRL ACD3 CONTROLLER
Date : 7 Aug 2012 Sheet / Sheets : 23 / 42 DOC No.: Draft
Testing & Commissioning MSK Operation (Start-up)
Procedure Remove P102C, P4M, & P104C from factory Connect P102C & P4M to LSD cable after checking cable number (Type: Wago connector) Connect P102C, P4M, connectors to controller Connect P104C (jumper connector) Connect 2H (jumper connector)
Location GECB AP-IO
GECB AP-IO GECB AP-IO Field panel
Connect GND of LSD to the earth plate
(P102C), (P4M), (P104C) GECB AP-IO
(2H) Field panel
1) MSK connectors should be removed after MSK operation. 2) Do not connect any cable without checking. Unpublished Work Copyright © OTIS Elevator Company
MUSE MRL ACD3 CONTROLLER
Date : 7 Aug 2012 Sheet / Sheets : 24 / 42 DOC No.: Draft
Testing & Commissioning MSK Operation (Start-up)
MSK kit
LSD Cable is for interphone at pit
For connection of Pit E. Stop & GTC
Unpublished Work Copyright © OTIS Elevator Company
MUSE MRL ACD3 CONTROLLER
Date : 7 Aug 2012 Sheet / Sheets : 25 / 42 DOC No.: Draft
Testing & Commissioning MSK Operation (Start-up)
Connection of MSK pendant switch
Pendant switch
MSK connector
Common
#8 of P102C
Up signal
#6 of P4M
Down signal
#7 of P4M
Safety chain
#1 of P102C
E.stop
#9 of P102C
Connection of MSK jumper
P102C (#4 & #5) P4M (#8 & #9) P104C (#1 & #2, #2 & #3) 2H (#2 & #4, #4 & #5)
Unpublished Work Copyright © OTIS Elevator Company
MUSE MRL
Date : 7 Aug 2012 Sheet / Sheets : 26 / 42 DOC No.: Draft
ACD3 CONTROLLER
Testing & Commissioning MSK Operation (Start-up)
4.1. Bridge of landing door switch Put the jumper bridge so that Inspection (or INS) is right position as following drawing (DW LED of GECB will be on)
[Door bypassed]
[Normal condition] Door bridge is located at the EIP (E&I panel) In case of MMR, door bridge can be at the controller
4.2. CDS(=Car Door Switch/Gate Switch) Jumper CDS can be bypassed by the bridge of #4 & #5 of P102C (DFC(=Door Fully Closed) LED of GECB will be on) P102C
#4
#5
Unpublished Work Copyright © OTIS Elevator Company
MUSE MRL ACD3 CONTROLLER
Date : 7 Aug 2012 Sheet / Sheets : 27 / 42 DOC No.: Draft
Testing & Commissioning MSK Operation (Start-up)
[Hoistway net cable]
Unpublished Work Copyright © OTIS Elevator Company
MUSE MRL ACD3 CONTROLLER
Date : 7 Aug 2012 Sheet / Sheets : 28 / 42 DOC No.: Draft
Testing & Commissioning MSK Operation (Start-up)
4.3. Install safety box and connect as following table for the safety chain. Housing Connection point Safety line Position 2H-02 SAF-06 GTC Pit safety box 2H-04 SAF-08 1PES/2PES *) For MSK, jump between SAF-06 & SAF-09 (GTC, 1PES/2PES), It shall be removed after MSK operation.
Note) The function of 2H is as followings after MSK. Housing 2H-02 2H-04
Connection Controller 4H-01 4H-02
Hoistway SAF-11 SAF-12
Function Pit lighting
Pay attention to poor contact for WAGO connector. It causes abnormal operation.
Unpublished Work Copyright © OTIS Elevator Company
MUSE MRL
Date : 7 Aug 2012 Sheet / Sheets : 29 / 42 DOC No.: Draft
ACD3 CONTROLLER
Testing & Commissioning MSK Operation (Start-up)
5. Start-up (MSK) Before start up, to ensure those: 1. Mechanical installation should be completed for MSK operation. (e.g. Governor, emergency stop switch, hoistway lighting, running platform, motor, & etc. 2. Electric connection should be completed for MSK. 3. Follow WWJSSS & local safety regulation.
5.1. Mega check Remove HL1 & HL2 from PE. If normal, connect again.
Check point PE & HL1 PE & HL2 PE & Line terminal(L1-L3) PE & motor terminal(U1-W1)
Standard More than 0.5 MΩ
5.2. Voltage check Measure 3 phases voltage & neutral at the line side of OCB after switching on building power. Measure 3 phases voltage & neutral at the line side of OCB after switching on OCB. Allowance: Rated voltage[Vac]±5% Unpublished Work Copyright © OTIS Elevator Company
MUSE MRL ACD3 CONTROLLER
Date : 7 Aug 2012 Sheet / Sheets : 30 / 42 DOC No.: Draft
Testing & Commissioning MSK Operation (Start-up)
Check the output of transformer (TRF1).
PS1 110Vac PS2
PS3 54Vac PS4
Check input & output of SMPS after switching on F2C
27Vdc
220Vac
Unpublished Work Copyright © OTIS Elevator Company
MUSE MRL ACD3 CONTROLLER
Date : 7 Aug 2012 Sheet / Sheets : 31 / 42 DOC No.: Draft
Testing & Commissioning MSK Operation (Start-up)
5.3. GECB check PY1 of GECB AP-IO Pin. No Terminal 1 27Vdc 2 27Vdc 3 HL2 4 HL2 5 27Vdc 6 HL2
Standard 27Vdc±10% 27Vdc±10% 0V 0V 27Vdc±10% 0V
PY2 of GECB AP-IO Pin. No Terminal 1 110V(Checking points: PY2:3) 2 HL1 3 HL1
Standard 110Vac±10%
5.4. RSL(Remote Serial Link) check Check the volt after removing P1H & P101C, connect back after measurement. Type Check points Standard Hall Link P1H:4 & HL2 27Vdc±10% Car Link P101C:4 & HL2 27Vdc±10% 5.5. Brake power check GGP/GeN2 1.5T/Optimized GeN2 2.6T/3.2T/4.1T/5T PS:03 54Vac 54Vdc±10% PS:04 OS2 BOMCO-1/BOMCO-2/BOMCO-W PS-03 124Vac(BRK*VAC_P) 124Vdc±10% PS-04 87.5Vac(BRK*VAC_H)_BOMCO-1 87.5Vdc±10% PS-05 62Vac(BRK*VAC_P)_BOMCO-2 62Vdc±10% PS-06 OS5 Unpublished Work Copyright © OTIS Elevator Company
MUSE MRL ACD3 CONTROLLER
Date : 7 Aug 2012 Sheet / Sheets : 32 / 42 DOC No.: Draft
Testing & Commissioning MSK Operation (Start-up)
5.6. Door power supply check Door motor supply (220Vac) 3C:01 220Vac (L) 3C:03 220Vac (N) Door controller supply (110Vac) 3C:01 110Vac (L) 3C:03 OS
220Vac±10%
110Vac±10%
5.7. Battery check (at controller) Check LED condition of SPBC board (After convert to ERO mode and switching on OCB. LED BAT-CHARGE MAINTENANCE FAULT BAT-MODE
Meaning Charging / Charging condition Charging finished Charging Battery providing power to SPBC
Condition
Off On Flickering
Note: The battery is charged by SPBC. For full charging, at least 8 hours shoul be charged. In case of power failure, battery will be discharged by the command of SPBC_III. If the power supply is cut for long period (>6hours), disconnect the battery temporarily.
Unpublished Work Copyright © OTIS Elevator Company
MUSE MRL ACD3 CONTROLLER
Date : 7 Aug 2012 Sheet / Sheets : 33 / 42 DOC No.: Draft
Testing & Commissioning MSK Operation (Start-up)
5.8. Safety chain check (110Vac) In case of MSK operation, some of safety switches are bypassed by MSK
adapter kit, but following switches are to be installed & connected 1PES (1st Pit Emergency Switch), 2PES (1st Pit Emergency Switch), GTC(Governor Tension Check Switch) 5.9. Main board input signal check To check if input signal of GECB board is correct. - P104C:1[/1LS-27Vdc], P104C:2[/2LS-27Vdc] - PX8:7 [MOT_THM – 24Vdc] - P7:2[BS1 – 24Vdc], P7:3[BS2-24Vdc] - P1:3[UIB-110Vac], P1:5[DIB-110Vac]
5.10. GECB & SPBC check -. Check if the signal of car & landing door is correct by LED of SPBC.
DW: Landing door DFC: Car & landing door
Unpublished Work Copyright © OTIS Elevator Company
MUSE MRL ACD3 CONTROLLER
Date : 7 Aug 2012 Sheet / Sheets : 34 / 42 DOC No.: Draft
Testing & Commissioning MSK Operation (Start-up)
-. Check communication between CAN & SVT (Service tool). Conditi LED Description on CAN_OK
CAN Bus communication normal
SPB_OK
Software condition ok
Off On Flicker
Press “DDO”
Service Tool port
Note) DW/DFC shall be capital letter in MSK operation. Unpublished Work Copyright © OTIS Elevator Company
MUSE MRL ACD3 CONTROLLER
Date : 7 Aug 2012 Sheet / Sheets : 35 / 42 DOC No.: Draft
Testing & Commissioning MSK Operation (Start-up)
-. Check communication between GECB & SPBC. Check input status by seeing LED on SPBC LED Description GRP/J Line voltage error NOR/DIAG Normal mode INS Inspection mode ES Emergency stop DW Landing door closed DFC Door closed (Car/landing) DOL Open limit switch DOB Door open button DZ Coor zone CAN-OK CAN link RSL Remote serial link
Status
Note) 3 LEDs, INS, DW & DFC, shall be on for MSK operation.
Unpublished Work Copyright © OTIS Elevator Company
Off On Flicker
/ /
MUSE MRL ACD3 CONTROLLER
Date : 7 Aug 2012 Sheet / Sheets : 36 / 42 DOC No.: Draft
Testing & Commissioning MSK Operation (Start-up)
6. Parameter setup 6.1. Parameter of GECB & GDCB will be set by the factory. However setting values are required to check before real operation. Refer to parameter list enclosed in the controller. M-GECB-1-3-1-7-GOON(Service) SPB Type 255 w/o ARO 0 w/ ARO M-GECB-1-3-1-4-GOON(Drive) DRV-TYP 1 M-GECB-1-3-1-1-GOON(System) TOP Top floor Start from 0 (Bottom floor = 0) M-GECB-1-3-1-5-GOON(Doors) Door 13 To be same each other Rear 13
-. Check GECB software version GeN2 MMR, IRIS: GAA30780DAK or higher [M-GECB-1-2-3-GOON(Part)] GeN2 comfort: GAA30780DAH or higher [M-GECB-1-2-3-GOON(Part)]
Unpublished Work Copyright © OTIS Elevator Company
MUSE MRL ACD3 CONTROLLER
Date : 7 Aug 2012 Sheet / Sheets : 37 / 42 DOC No.: Draft
Testing & Commissioning MSK Operation (Start-up)
31 Contract Interface Type Drive Type ARO Type
Min 0 25 1
Max 4 999 4
Default 1
Actual 1 Driver value 1: w/o ARO 4: w/ ARO Motor value Speed Motor RPM
Motor Type 100 999 Duty speed 10 16000 Rated rpm 1 5000 Inertia kg/m2 0.1 20000 Encoder Type 0 1 Encoder Encoder PPR 1000 10000 Duty load 10 16384 No of passenger AC Main 50 480 380Vac Load weigh Type 0 3 Load weighing device type Balance 0 77 45~47 Vane sensor Type 0 99 PRS type DDP 0 45 Number of DZ 2 140 Service floor Bottom DZ 0 20 0 DZ in 1LS 0 5 1 No of vane within 1LS zone E.g. If speed is 60m/min, data shall be 1000. (90m/min=1500, 105m/min=1750)
[Parameter display]
Duty Speed mm/s 1000>
XXXXX
Rated rpm 400>
XXXXX
Encoder 3600>
PPR XXXXX
1.Try to convert to ERO mode for changing parameter.
Unpublished Work Copyright © OTIS Elevator Company
MUSE MRL ACD3 CONTROLLER
Date : 7 Aug 2012 Sheet / Sheets : 38 / 42 DOC No.: Draft
Testing & Commissioning MSK Operation (Start-up)
32 Adjustment Profile delay ms VelRate div 35 Profile Insp Speed Nom Speed Accel Decel Jerk Base Speed(5)
Min 0
Max 10000
Default 0
0
3
0
Min 10 0 25 25 100 50
Max 630 16000 1200 1200 2400 100
Default -
Actual Increase by 10 in case of start jerk 0 Actual 300 Rated speed
Note) In case of no LWB with roll back, set LWB Type as 0. -. Check GDCB software version GeN2 MMR, IRIS: AP230924DAH or higher [M-DRIVE-1-1-GOON] GeN2 comfort: AP230924DAH or higher [M-DRIVE-1-1-GOON] -. In case that parameter of PROFILE (M-2-3-5 is changed, actual distance of LS shall be bigger than the requirement of LS distance in (M-2-1-7).
7. RE (Rotary Encoder) calibration 7.1. If the system is normal, Rotary encoder will be calibrated automatically. (LRT operation)
RE calibration will be conducted in following 3 cases. Resuming power supply and 1st operation After changing parameter After error outbreak
Unpublished Work Copyright © OTIS Elevator Company
MUSE MRL ACD3 CONTROLLER
Date : 7 Aug 2012 Sheet / Sheets : 39 / 42 DOC No.: Draft
Testing & Commissioning MSK Operation (Start-up)
During LRT operation, noise will come out from the motor, but it is normal. And it won’t be conducted in normal operation. If error is detected (Brake drop), it will be conducted.
During LRT operation, do not access car top, hoistway. Car will be moved.
The system is normal but a car is not moved even with up/down signal:
7.2. After RE calibration, the car direction should be checked by pressing pendant switch whether the direction is correct.
-. Follow instruction in following table
Unpublished Work Copyright © OTIS Elevator Company
MUSE MRL ACD3 CONTROLLER
Date : 7 Aug 2012 Sheet / Sheets : 40 / 42 DOC No.: Draft
Testing & Commissioning MSK Operation (Start-up)
1 2
3
Condition Direction is same with command Direction is opposite to command (Running condition is OK)
Action to be taken Move to next process Change car direction by SVT.
Car stopped or error outbreak
Change 2 motor phases Change motor phase by SVT Interchange 2 motor phases (HVIB)
501 Pos Tracking 000:00:00:00.04
Car Dir
Motor Phase
502 Vel Tracking 000:00:00:00.04 100 Inv SW Oct 000:00:00:00.04
Unpublished Work Copyright © OTIS Elevator Company
0/1
0/1
MUSE MRL ACD3 CONTROLLER
Date : 7 Aug 2012 Sheet / Sheets : 41 / 42 DOC No.: Draft
Testing & Commissioning MSK Operation (Start-up)
[To change parameter by SVT]
☞
M MODULE
2 DRIVE
3 SETUP
Note) Data value shall be “0” or “1”. Unpublished Work Copyright © OTIS Elevator Company
2 ADJUSTMENT
MUSE MRL ACD3 CONTROLLER
Date : 7 Aug 2012 Sheet / Sheets : 42 / 42 DOC No.: Draft
Testing & Commissioning MSK Operation (Start-up)
8. Test running 1. Try to run the car whether it moves to designated direction. 2. Check the condition is complied to local safety rules or WWJSSS. Siren shall be activated during running if landing door hasn’t been installed
Controller Adapter cable #1
LSD Cable Cross head
Travelling cable support
Bottom floor
300mm or bigger
400m m [Layout for MSK operation] Unpublished Work Copyright © OTIS Elevator Company