43 0 2MB
PIPELINE COATINGS / FIELD JOINT COATING EXTERNAL
1
TYPE OF MAIN LINE COATINGS
3 LPE (2 to 3.5mm thk)
FBE (0.45mm thk)
3 LPP (2 to 3.5mm thk)
DFBE (0.7mm thk) 2
PIPELINE COATINGS
DFBE ANTI CORROSION COATING HDPU THERMAL INSULATION (90mm thk) HDPE JACKET 5mm thk CTE COATING – 4.8mm thk
3
BASIS OF SELECTION OF MAIN LINE COATINGS (NEW)
PIPELINE OPERATING TEMPERATURE PIPELINE DESIGN LIFE PIPELINE DIAMETER TYPE OF SOIL AMBIENT TEMPERATURE ROW CONDITIONS
CONSTRUCTION PERFORMANCE
4
BASIS OF SELECTION OF MAIN LINE COATING – OPERATING TEMPERATURE
Polyethylene Coatings – 800C Fusion Bond Epoxy Coatings – 1100C ~ 1400C
Polypropylene Coatings – 1200C Polymeric Tape Coatings - 600C
Liquid Epoxy Coating - 1500C 5
THREE LAYER POLYETHYLENE COATING
DIN-30670 – “POLYETHYLENE COATING FOR STEEL PIPES & FITTINGS.
ISO-21809-1 – “ PETROLEUM & NATURAL GAS INDUSTRIES – EXTERNAL COATINGS FOR BURIED AND SUBMEREGED PIPELINES USED IN PIPELINES TRANSPORTATION SYSTEM PART-1 (3 LAYER PE & 3 LAYER PP) CAN/CAZ-Z245.21-06 – “EXTERNAL POLYETHYLENE COATING FOR PIPES.
6
3LPE COATING PROCESS
7
THREE LAYER POLYETHYLENE COATING DESIGNATION / COATING CLASSIFICATION DIN-30670
ISO-21809-1
CAN/CAZ.2451-06
DIN-30670 - N-n
Class-A
System-B1
DIN-30670 - N-v
Class-B
System-B2
DIN-30670 - S-n
Class-C
DIN-30670 - S-v Coating classes are based on N-Normal expected field duty - Operating Temperature S-Special - Transport -Handling n- normal thickness -Layer conditions - Operating conditions v- reinforced thickness - Soil Conditions - Expected Environmental Conditions
8
THREE LAYER POLYETHYLENE COATING FUNCTIONAL PROPERTIES DIN-30670 Peel Strength(N/mm) @23°c
N-n 3.5
Tmax (Pull speed 10N/mm)
Impact Strength J/mm @ 23°c Indentation -23°c - Tmax Cathodic disbondment 65°C/24hrs(-3.5V) 20°C/28 days(-15V) 65°C/28days(-1.5V)
ISO-21809-1
S-n 3.5
A 10
1.5 (50°c)
2.5 (70°c)
2 (60°c)
N-n 5
S-n 5
N-n ≤ 0.2mm ≤ 0.3mm (50°c)
S-n 0.2mm ≤ 0.3mm (70°c)
-
A 5
B 15
3 (80°c)
B 7
C 23
B1 6
4 (90°c)
-
C 10
A B C ≤ 0.3mm ≤ 0.2mm ≤ 0.1mm ≤ 0.3mm ≤ 0.2mm ≤ 0.1mm
≤ 7mm ≤ 7mm ≤ 15mm
CAS-Z245.21-06
B1 3 -
≤ 12mm
9
THREE LAYER POLYETHYLENE COATING OPERATING TEMPERATURES
DIN-30670
ISO-21809-1
CAN/CAZ.2451-06
Class-A : (– )20°C to (+) 60°C DIN-30670- N up to 50° C
(LDPE) Class-B : (– )40° C to (+) 80 °C
(MDPE/HDPE) DIN-30670- S up to 70° C
Not Clearly Specified. However, the purchaser has to specify the max design temp.
Class-C ; (– )20°C to (+)110°C (PP)
10
VIPUL KUMAR, PEng, Deputy General ManagerEngineering
M 1 Infield Pipeline Pressure Class Length Kms Power Fluid Lines 1500# 10 Water Injection Lines 900# 10 Production Fluid Lines 600# 53 R1 Infield Pipeline 600# 7 MR Pipeline Gas Line 12” API 5LX60 PSL2 300# 90 Condensate Line 4” API 5LX 65 600# 90 T Pipeline Water Supply Line 20” API 5LX 65 PSL2 20 Total Pipeline Length
280 Vipul Kumar, PEng
Innovative Techniques Four Cluster of Well pads created to save on Flow lines cost from 18 individual well pads to M Field Trunk lines laid for Power Fluid & Water Injection in pipeline corridor & connecting well pads to Trunk lines thus saving cost on lines from individual well pads to MPT.
Cairn India – 2010 Technical Forum (October 20th & 21st) Celebrating Our Technical Achievements
Initial Design Concept Heavy design on Anchor Flanges and Anchor Blocks Anchor Block Estimated Quantity of RCC=24000 Cum
Innovative Efforts Improvisation on Basic Design of Anchor Flanges & Blocks Added bends to reduce total applicable force Anchor flanges on downstream of Water and gas lines eliminated after review Above resulted in to Reduction of RCC to 10000 Cum(i.e. reduction of 58 %)
Vipul Kumar, PEng
ANCHOR FLANGE/ BLOCK DESIGN
Cairn India – 2010 Technical Forum (October 20th & 21st) Celebrating Our Technical Achievements
Vipul Kumar, PEng
Reinstatement of Flow-lines Prior to Re-Start Oil in flow lines likely to congeal in black out/ shut down condition. Original design envisaged tapping at every 500 meters for flushing congealed oil with hot water. On design review the arrangement considered of high risk.
INNOVATIVE TECHNIQUE
On power black out/ shut down displace oil in flowlines with water to ensure oil will not stay in flow lines.
Installed diesel driven high capacity pump at MPT end itself. Vipul Kumar, PEng
Thumbli Main Header
Originally header design concept • Horizontal header on sloped graded area • Header of uniform size pipes
Design Review Sloped header to match graded slope Header of Multiple sizes matching with flow requirement
Advantages Saving on concrete cost Saving on pipe cost
Vipul Kumar, PEng
Sectionalizing Valve Location
As per ASME B 31.8 Sectionalizing valves provided as per location Class
Original design provided for installation of vents and drains along with Sectionalizing valves. However, various constraints were not permitting this feasible.
On design review, risk assessment and proper interpretation of OISD 141 recommended design was modified to eliminate drains and vents. Cairn India – 2010 Technical Forum (October 20th & 21st) Celebrating Our Technical Achievements
Gas and Condensate lines from MPT to RGT(90 Kms) passing through villages and populated area Considered high safety and Security Risks Intrusion detection system introduced
Multifunctional120 Core Optical Fiber cable • Intrusion Detection System • Access control system • Data Network • Hotline • PAGA System Vipul Kumar, PEng
ZINC RIBBON CONFIGURATION IN CASING
Cairn India – 2010 Technical Forum (October 20th & 21st) Celebrating Our Technical Achievements
Anti-buoyancy Method
Innovative Technique
Original design concept for concrete coating Recommended in coating yard to achieve desired density
Geo text bags filled with gravel material used
Advantages
Saving on time Saving in logistics Vipul andKumar, cost PEng
OPTIONS CONSIDERED All 14 Pipelines on Steel / Concrete structure Bridge Horizontal Directional Drilling Bury below soil erosion point
TECHNO-COMMERCIAL FEASIBLE OPTION IMPLEMENTED 1200 X 25 X 6 meters open excavation Pipe-layers, cranes, trailers, welding sets etc lowered in excavated trench All 14 pipelines laid & trench backfilled
ADAVANTAGES ACCRUED
Saving on time and cost Vipul Kumar, PEng
Launcher and Receiver skids matching Hot bends and Cold bends Inclusion of Magnetic Pigging TCP and PCP System MIJs GOC OFC Hydro-testing Drying with Compressor Magnetic pigging Nitrogen Packing of Pipelines Vipul Kumar, PEng
Launcher and Receiver skids matching Hot bends and Cold bends Inclusion of Magnetic Pigging TCP and PCP System MIJs GOC OFC Hydro-testing Drying with Compressor Magnetic pigging Nitrogen Packing of Pipelines Vipul Kumar, PEng
Vipul Kumar, PEng
Vipul Kumar, PEng
Cairn India – 2010 Technical Forum (October 20th & 21st) Celebrating Our Technical Achievements
Cairn India – 2010 Technical Forum (October 20th & 21st) Celebrating Our Technical Achievements