APQP ACTIVITIES MATRIX Development Category:
B - Type
PART NAME
PEDAL ASSY BRAKE
PART NUMBER
DATE
24-08-2016
49600-79M20
MODEL AA
DOCUMENT NO: F/DEV/03
YL1-MC
Absolutely new component : no Experience of production so far .
A
Expience in previous model / Experience in similar type Parts : For new model
B
In case of ECN/Minor Change
C
In case of Process Change.
S.NO
Description
Development
Responsibility
AA
A
B
C
1
Phase 1 : Plan & Define the Programme
I
CFT Formation
O
O
O
O
II
Review Customer drawing/SOR(Akka-pen)
O
O
O
O
III
Feasibility Study and Risk Assesment
O
O
O
O
IV
PFD Preliminary
O
O
V
MKT ENGG&DEV QA PROD MATLS PLANT HEAD
O
#
O
#
O
O
#
O
O
#
O
O
O
O
O
Bill of material Preliminary
O
O
O
O
#
O
VI
Define Critical Parameters
O
O
O
O
O
#
O
O
O
VII
Phase -1 Review
O
O
O
O
#
#
#
#
#
2
Phase 2 : Product Design & Development
I
DFMEA (if reqd)
#
O
O
#
O
II
Drawing approval from Collaborator(if reqd)
O
III
Line feasibility review (Capacity Planning)
O
O
O
O
O
#
O
IV
#
New Equipment & Facilities required (List to be made)
O
O
O
O
#
O
V
Sourcing of Raw material/BOPs
O
O
O
O
#
O
VI
New Tooling required
O
O
O
O
#
O
VII
O
O
O
Gauge / testing equipment requirements (List to be made)
O
O
O
O
#
#
O
Team Feasibility commitment & Mgmt. Support
O
O
O
O
#
#
O
O
IX
Past Defect Data Review
O
O
O
#
O
O
X
#
O
#
#
#
O
Prototype Control Plan (if reqd)
O
O
Phase -2 Review
O
O
O
O
3
Phase 3 : Process Design & Development
I
PFMEA
O
O
O
O
II
Floor plan layout
O
O
#
#
#
O
#
III
New Equipment & Facilities procurement
O
O
O
O
#
O
New Tooling procurement/Manufacturing
O
O
O
O
#
O
O
O
V
Gauge / testing equipment procurement/manufacturing
O
O
O
O
#
O
O
O
VI
O
O
O
#
O
O
O
O
O
#
O
O
VIII
Product / Process development review Insp. Std , Visual aids (Receiving,in-process,final) Define Packaging standards
O
O
O
#
#
#
IX
#
O
#
#
O
O
O
#
O
Process Sheet,Work Instructions
O
O
O
O
X
Procurement of Material (BOP/RM)
O
O
O
O
XI
Manpower requirment
O
O
XII
O
Operator Training plan
O
O
O
O
#
O
O
XIII
Sample Submission to Customer
O
O
O
O
#
O
O
XIV
Phase -3 Review
O
O
O
#
#
#
O
O
O
O
#
O
O
O
#
O
O
O
O
O
#
#
O
O
#
O
O
#
#
O
4
Phase 4 : Product & Process Validation
I
Supplier PPAP (if required)
III
Production Trial Run(HVPT) (customer specific) Process capability study CpK or Part accuracy
IV
Packaging Approval
O
O
O
V
Product validation testing(performance) test
O
O
O
VI
Production part approval from customer for PP trial
O
O
O
II
#
O
#
O
IV
VII
#
# O
VIII
XI
#
#
#
#
REMARKS Document Refrence
APQP ACTIVITIES MATRIX Development Category:
B - Type
PART NAME
PEDAL ASSY BRAKE
PART NUMBER
DATE
24-08-2016
49600-79M20
MODEL AA
DOCUMENT NO: F/DEV/03
YL1-MC
Absolutely new component : no Experience of production so far .
A
Expience in previous model / Experience in similar type Parts : For new model
B
In case of ECN/Minor Change
C
In case of Process Change.
S.NO
Description
Development AA
A
B
VII
Production part approval from customer for MPP trial
O
O
O
VIII
Production control plan (internal)
O
O
O
IX
Quality Planning sign-off and Management support
O
O
O
X
Phase -4 Review
O
O
O
Responsibility C
MKT ENGG&DEV QA PROD MATLS PLANT HEAD
O #
#
#
O
#
#
O
#
#
O
#
#
#
#
#
REMARKS Document Refrence
APQP ACTIVITIES MATRIX Development Category:
B - Type
PART NAME
PEDAL ASSY BRAKE
PART NUMBER
DATE
24-08-2016
49600-79M20
MODEL AA
DOCUMENT NO: F/DEV/03
YL1-MC
Absolutely new component : no Experience of production so far .
A
Expience in previous model / Experience in similar type Parts : For new model
B
In case of ECN/Minor Change
C
In case of Process Change.
S.NO
Description
Development
Responsibility
AA
A
B
C
MKT ENGG&DEV QA PROD MATLS PLANT HEAD
5
Phase 5 : Feedback Assessment & Corrective Action
I
PCS(PRODUCTION)
O
O
O
O
#
O
O
II
PFMEA
O
O
O
O
#
O
O
III
MISP
O
O
O
O
#
O
O
IV
Project handover to production
O
O
O
#
#
O
V
O
Initial Control Period Initiation
O
O
O
O
#
VI
Initial control trmination signoff
O
O
O
O
#
VII
Production, Defect & Dispatch Monitoring
O
O
O
O
#
#
VIII
Management Review
O
O
O
#
O
O
Phase -5 Review
O
O
O
#
#
#
IX
LEGENDS : Legend O (Blank) No Mark Legend # O
O #
#
REMARKS Document Refrence
#
Definitopn Point to be implemented . Review required /important from discussion point of view . Point which are not to be implemented but plan is to produce which could verify as to why they are not require to be implemented . For Responsibility Definition Prime Responsibility CO-Responsibility 01 00' Rev. No.
Point Revised New Issue Description
10/3/2017 1/2/2016 Date
APQP ACTIVITIES MATRIX
DOCUMENT NO: F/DEV/03
Development Category: PART NAME
DATE
STOPPER BRKT ASSY
PART NUMBER
1 L0081-13
MODEL
BRIO
AA
Absolutely new component : no Experience of production so far .
A
Expience in previous model / Experience in similar type Parts : For new model
B
in case of ECN/Minor Change
C
Operator Training plan
S.NO
Description
Development AA
A
1
Phase 1 : Plan & Define the Programme
I
CFT Formation
O
O
B
Responsibility C
II
Review Customer drawing/SOR(Akka-pen)
O
O
O
O
III
Feasibility Study and Risk Assesment
O
O
O
O
IV
PFD Preliminary
O
O
V
Bill of material Preliminary
O
O
O
VI
MKT
ENGG&DEV
QA
PROD
MATLS
O
#
O
O
O
O
O
#
O
O
#
O
O
#
O
#
O
O O
Define Critical Parameters
O
O
O
O
O
#
O
O
O
VII
Phase -1 Review
O
O
O
O
#
#
#
#
#
2
Phase 2 : Product Design & Development
I
DFMEA (if reqd)
#
O
O
#
O
II
Drawing approval from Collaborator(if reqd)
O
III
Line feasibility review (Capacity Planning)
O
O
O
O
O
#
O
IV
New Equipment & Facilities required (List to be made)
O
O
O
O
#
#
O
V
Sourcing of Raw material/BOPs
O
O
O
O
#
O
O
O
#
O
VI
Gauge / testing equipment requirements (List to be made)
O
O
O
O
#
#
O
VII
Team Feasibility commitment & Mgmt. Support
O
O
O
O
#
#
O
O
VIII
O
Past Defect Data Review
O
O
#
O
IX
Prototype Control Plan (if reqd)
O
O
#
O
X
Phase -2 Review
O
O
O
O
#
#
3
Phase 3 : Process Design & Development
I
PFMEA
O
O
O
O
#
O
II
Floor plan layout
O
O
#
#
#
O
III
New Equipment & Facilities procurement
O
O
O
O
#
O
IV
New Tooling procurement/Manufacturing
O
O
O
O
#
O
O
O
V
Gauge / testing equipment procurement/manufacturing
O
O
O
O
#
O
O
O
O
O
#
O
O
O
O
O
#
O
O
VIII
Product / Process development review Insp. Std , Visual aids (Receiving,in-process,final) Define Packaging standards
O
O
O
O
#
#
#
IX
Process Sheet,Work Instructions
O
O
O
O
#
O
O
O
VI VII
X
Procurement of Material (BOP)
O
O
XI
Manpower requirment
O
O
XII
#
#
O
O
#
#
O
O
O
#
Operator Training plan
O
O
O
O
#
O
O
XIII
Sample Submission to Customer
O
O
O
O
#
O
O
XIV
Phase -3 Review
O
O
O
#
#
#
O
#
4
Phase 4 : Product & Process Validation
I
O
O
O
O
O
O
IV
Supplier PPAP Production Trial Run(HVPT) (customer specific) Process capability study (CpK (Customer Specific) or Part accuracy. Packaging Approval
O
O
O O
II III
V
Product validation testing(performance) test
O
O
VI
Production part approval from customer for PP trial
O
O
VII
#
O
Production part approval from customer for MPP trial
O
O
VIII
Production control plan (internal)
O
O
O
IX
Quality Planning sign-off and Management support
O
O
O
O
O
#
O
O
#
#
#
O
O
#
O
O
#
#
O
#
#
O
#
#
O
#
#
O
#
REMARKS
Document Refrence
APQP ACTIVITIES MATRIX
DOCUMENT NO: F/DEV/03
Development Category: PART NAME PART NUMBER
1 L0081-13
MODEL
BRIO
AA
Absolutely new component : no Experience of production so far .
A
Expience in previous model / Experience in similar type Parts : For new model
B
in case of ECN/Minor Change
C
Operator Training plan
S.NO X
DATE
STOPPER BRKT ASSY
Description Phase -4 Review
Development AA
A
B
O
O
O
Responsibility C
MKT
ENGG&DEV
QA
PROD
MATLS
#
#
#
#
#
REMARKS
Document Refrence
APQP ACTIVITIES MATRIX
DOCUMENT NO: F/DEV/03
Development Category: PART NAME
DATE
STOPPER BRKT ASSY
PART NUMBER
1 L0081-13
MODEL
BRIO
AA
Absolutely new component : no Experience of production so far .
A
Expience in previous model / Experience in similar type Parts : For new model
B
in case of ECN/Minor Change
C
Operator Training plan
S.NO
Description
Development
Responsibility
AA
A
B
C
MKT
ENGG&DEV
QA
PROD
5
Phase 5 : Documantation Submission to Customer
I
PCS(PRODUCTION)
O
O
O
O
#
O
O
II
PFMEA
O
O
O
O
#
O
O
III
MISP
O
O
O
O
#
O
O
IV
O
#
O
O
#
#
#
O
Management Review
O
O
O
V
Phase -5 Review
O
O
O
#
6
Phase 6 : Feedback Assessment & Corrective Action
I
O
project handover to production
O
O
O
#
#
II
Initial Control Period Initiation
O
O
O
O
#
III
initial control trmination signoff
O
O
O
O
#
IV
Production, Defect & Dispatch Monitoring
O
O
O
O
#
#
V
Phase -6 Review
O
O
O
#
#
#
#
MATLS
REMARKS
#
#
LEGENDS : Legend O (Blank) No Mark Legend # O
Definitopn Point to be implemented . Review required /important from discussion point of view . Point which are not to be implemented but plan is to produce which could verify as to why they are not require to be implemented . For Responsibility Definition Prime Responsibility CO-Responsibility
00' Rev. No.
New Issue Description
Date
Document Refrence
APQP ACTIVITIES MATRIX Development Category:
A - Type
PART NAME
TANK OIL CATCH
PART NUMBER
DATE
240-10-2015
24813-56R00
MODEL AA
DOCUMENT NO: F/DEV/03
YL1-MC
Absolutely new component : no Experience of production so far .
A
Expience in previous model / Experience in similar type Parts : For new model
B
In case of ECN/Minor Change
C
In case of Process Change.
S.NO
Description
Development
Responsibility
AA
A
B
C
1
Phase 1 : Plan & Define the Programme
I
CFT Formation
O
O
O
O
II
Review Customer drawing/SOR(Akka-pen)
O
O
O
O
III
Feasibility Study and Risk Assesment
O
O
O
O
IV
PFD Preliminary
O
O
V
MKT ENGG&DEV QA PROD MATLS PLANT HEAD
O
#
O
#
O
O
#
O
O
#
O
O
O
O
O
Bill of material Preliminary
O
O
O
O
#
O
VI
Define Critical Parameters
O
O
O
O
O
#
O
O
O
VII
Phase -1 Review
O
O
O
O
#
#
#
#
#
2
Phase 2 : Product Design & Development
I
DFMEA (if reqd)
#
O
O
#
O
II
Drawing approval from Collaborator(if reqd)
O
III
Line feasibility review (Capacity Planning)
O
O
O
O
O
#
O
IV
#
New Equipment & Facilities required (List to be made)
O
O
O
O
#
O
V
Sourcing of Raw material/BOPs
O
O
O
O
#
O
VI
New Tooling required
O
O
O
O
#
O
VII
O
O
O
Gauge / testing equipment requirements (List to be made)
O
O
O
O
#
#
O
Team Feasibility commitment & Mgmt. Support
O
O
O
O
#
#
O
O
IX
Past Defect Data Review
O
O
O
#
O
O
X
#
O
#
#
#
O
Prototype Control Plan (if reqd)
O
O
Phase -2 Review
O
O
O
O
3
Phase 3 : Process Design & Development
I
PFMEA
O
O
O
O
II
Floor plan layout
O
O
#
#
#
O
#
III
New Equipment & Facilities procurement
O
O
O
O
#
O
New Tooling procurement/Manufacturing
O
O
O
O
#
O
O
O
V
Gauge / testing equipment procurement/manufacturing
O
O
O
O
#
O
O
O
VI
O
O
O
#
O
O
O
O
O
#
O
O
VIII
Product / Process development review Insp. Std , Visual aids (Receiving,in-process,final) Define Packaging standards
O
O
O
#
#
#
IX
#
O
#
#
O
O
O
#
O
Process Sheet,Work Instructions
O
O
O
O
X
Procurement of Material (BOP/RM)
O
O
O
O
XI
Manpower requirment
O
O
XII
O
Operator Training plan
O
O
O
O
#
O
O
XIII
Sample Submission to Customer
O
O
O
O
#
O
O
XIV
Phase -3 Review
O
O
O
#
#
#
O
O
O
O
#
O
O
O
#
O
O
O
O
O
#
#
O
O
#
O
O
#
#
O
4
Phase 4 : Product & Process Validation
I
Supplier PPAP (if required)
III
Production Trial Run(HVPT) (customer specific) Process capability study CpK or Part accuracy
IV
Packaging Approval
O
O
O
V
Product validation testing(performance) test
O
O
O
VI
Production part approval from customer for PP trial
O
O
O
II
#
O
#
O
IV
VII
#
# O
VIII
XI
#
#
#
#
REMARKS Document Refrence
APQP ACTIVITIES MATRIX Development Category:
A - Type
PART NAME
TANK OIL CATCH
PART NUMBER
DATE
240-10-2015
24813-56R00
MODEL AA
DOCUMENT NO: F/DEV/03
YL1-MC
Absolutely new component : no Experience of production so far .
A
Expience in previous model / Experience in similar type Parts : For new model
B
In case of ECN/Minor Change
C
In case of Process Change.
S.NO
Description
Development AA
A
B
VII
Production part approval from customer for MPP trial
O
O
O
VIII
Production control plan (internal)
O
O
O
IX
Quality Planning sign-off and Management support
O
O
O
X
Phase -4 Review
O
O
O
Responsibility C
MKT ENGG&DEV QA PROD MATLS PLANT HEAD
O #
#
#
O
#
#
O
#
#
O
#
#
#
#
#
REMARKS Document Refrence
APQP ACTIVITIES MATRIX Development Category:
A - Type
PART NAME
TANK OIL CATCH
PART NUMBER
DATE
240-10-2015
24813-56R00
MODEL AA
DOCUMENT NO: F/DEV/03
YL1-MC
Absolutely new component : no Experience of production so far .
A
Expience in previous model / Experience in similar type Parts : For new model
B
In case of ECN/Minor Change
C
In case of Process Change.
S.NO
Description
Development
Responsibility
AA
A
B
C
MKT ENGG&DEV QA PROD MATLS PLANT HEAD
5
Phase 5 : Feedback Assessment & Corrective Action
I
PCS(PRODUCTION)
O
O
O
O
#
O
O
II
PFMEA
O
O
O
O
#
O
O
III
MISP
O
O
O
O
#
O
O
IV
Project handover to production
O
O
O
#
#
O
V
O
Initial Control Period Initiation
O
O
O
O
#
VI
Initial control trmination signoff
O
O
O
O
#
VII
Production, Defect & Dispatch Monitoring
O
O
O
O
#
#
VIII
Management Review
O
O
O
#
O
O
Phase -5 Review
O
O
O
#
#
#
IX
LEGENDS : Legend O (Blank) No Mark Legend # O
O #
#
REMARKS Document Refrence
#
Definitopn Point to be implemented . Review required /important from discussion point of view . Point which are not to be implemented but plan is to produce which could verify as to why they are not require to be implemented . For Responsibility Definition Prime Responsibility CO-Responsibility 01 00' Rev. No.
Point Revised New Issue Description
10/3/2017 1/2/2016 Date
APQP ACTIVITIES MATRIX
DOCUMENT NO: F/DEV/03
Development Category: PART NAME
PEDAL ASSY BRAKE
PART NUMBER
49600-55R00/10/30/40/50/60
MODEL AA
YSD Absolutely new component : no Experience of production so far .
A
Expience in previous model : For new model.
B
in case of ECN
C
In case of Process Change.
S.NO
Description
AA
Development A B
C
MKT
Responsibility ENGG&DEV QA PROD
1
Receipst of drawing along with spec drg /ref . Sample
O
O
O
O
O
#
2
Pre -Feasibility .
O
O
O
O
#
O
3
Clarification fromcustomer for incomplete info .
O
O
O
O
O
#
4
Technical feasibility.
O
O
O
O
#
5
Cost estimation
O
O
O
O
#
O
6
Reciept of LOI from customer .
O
O
O
O
#
O
7
Preparation of PFD
O
O
O
O
O
#
8
Preparation of Timing chart
O
O
O
O
O
#
O
9
BOM
O
O
#
O
10
Past history study
O
O
#
O
11
Component drawing
O
O
#
O
12
Drawing review
O
O
#
O
13
Review of process flow chart
O
O
O
O
#
O
14
Listing of special characteristics
O
O
O
O
#
O
15
Proccess FMEA
O
O
O
#
16
Control Plan (prototype)
O
O
O
O
#
O
17
Tool Design/Drawing
O
O
O
O
#
O
18
Tool manufacturing
O
O
O
O
#
O
19
Guage Testing Equipment
O
O
O
O
#
O
20
Sourcing raw material/BOPs
O
O
O
O
#
O
21
Sample trial run
O
O
O
O
#
O
22
Follow -up results during product development
O
O
O
O
#
O
23
Review with customer
O
O
O
O
#
O
24
Layout plan
O
O
25
BOP procurement
O
O
26
PART ACCUARACY
O
O
O
27
Operator training
O
O
O
28
Packaging specification
O
O
O
O
29
Pre -launch control plan
O
O
O
O
30
MSA plan
O
O
31
Production trail run,pilot lot
O
O
32
Process product validation
O
O
33
Process capability evaluation
O
O
34
MSA study
O
O
35
PPAP
O
O
36
Customer approval
O
O
37
Feedback analysis & corrective action
O
O
38
Production control plan
O
O
39
Production handover
O
O
40
management Review
O
O
O
O
# O
O
O
O
O
O
O
O
O
• • •
O
• O
O
•
O O #
•
O • O
O
O
O
#
O
#
O
O
#
O
O
#
#
#
O
#
#
O
O
#
#
O
O
#
O
#
O
#
O
O
•
#
#
O
O
•
O
#
O
O
O
#
#
O
#
#
#
O O
O
O
O
O
O
REMARKS
•
#
O
MATLS
O
O O
#
#
O
•
LEGENDS : Legend O (Blank) No Mark
Definitopn Point to be implemented . Review required /important from discussion point of view . Point which are not to be implemented but plan is to produce which could verify as to why they are not require to be implemented . For Responsibility
Document Refrence
Legend # O
Definition Prime Responsibility CO-Responsibility
00' Rev. No.
New Issue Description
Date