48 1 11KB
MECHANICAL COMPLETION TURNOVER FLOWCHART
SYSTEM APPROACHING TO MECHANICAL COMPLETION A
Contractor completes cat A items
Contractor submits System Ready for Walkdown Notice
Fluor confirms that system is ready for walkdown
Fluor/SPCC verifies items closure
Contractor completes deficiences
NO Ready?
NO
YES
Punchlist items cat A complete?
YES
Contractor submits Mechanical Completion Certificate (System Turned Over)
Contractor submits Mechanical Completion Checklists Punch list cat B &C items?
Fluor submits to SPCC a System Walkdown Notice
YES Contractor completes cat B & C items
Fluor/SPCC verifies items closure
Walkdown by Fluor/SPCC
Punch list cat A items?
NO
NO
NO
Punchlist items cat B &C complete?
YES YES
FINAL ACCEPTANCE NOTICE
A REV 1 30/09/05