30 0 166KB
PROJECT PROPOSAL IN FISH 40
Submitted by: Lisly P. Dizon
Submitted to: Ms. Reizel L. Asaytuno
1st SEMESTER
PROJECT PROPOSAL
I. Description
A. Project Title
Rehabilitation of Water System
B. Project Location
Bote, Bato, Catanduanes
C. Brief Summary of the Project
The project primarily intends to decrease the poverty incidence in the barangay, in line with the thrust of the National Government which is directed towards poverty reduction. It will provide 221 HHs in the barangay an access to clean and safe water. It also seeks to eliminate the incidence of water-borne diseases in the barangay which was recorded at 55 cases of skin diseases during the preceding year.
As the more serious sickness which may be brought about by unsafe water will drain the budget of the family, availability of safe drinking water is a must to every household. Easy access to safe water will also result to savings in time of family members which will pave way for the accomplishment of other profitable undertakings.
Although 90.5% percent of the households have water connections provided by the barangay, it failed to provide them with sufficient supply of clean and potable water. As such, there is a necessity to tap the appropriate water source in the barangay through the SALINTUBIG program of the DILG.
The project will augment LGU’s undertaking in improving the water system of the barangay through its Economic Development Fund. Barangay Bote has also spent part of its development fund for the said water system, accomplishing the construction of the
existing water tank that has a capacity of 21.6 cu. m and laying of the existing pipelines of the barangay water system.
D. Project Goals and Objectives
In general, the project is aimed at reducing the poverty threshold of the barangay from 80% to 65%. Specifically, it will provide the 1,105 individuals in 221 households in the barangay an access to safe drinking water. It will also promote good health and cause the eradication of water-borne diseases; and will reduce the time allotted by family members in fetching water, thus savings in time would provide for the accomplishment of other lucrative activities.
E. Total Project Cost
Table 1. Total Project Cost and percentage of contribution Source of Fund
Amount
% Share
Department of the Interior and Local 900,000.00
85.5%
Government Municipal
Government
Catanduanes
of
Bato, 90,000.00
12.5%
(direct counterpart) 41,500.00 (fund
provision
to
other
activities) Beneficiaries
21,000.00
2%
(in-kind)
F. Target Beneficiaries
The beneficiaries of the project are the whole residence of Barangay Bote. With proper management, it will give them abundant supply of safe and clean water which will also prevent them from being afflicted by diseases caused by contaminated water. The easy access to a potable water supply will also result to savings in time in fetching
drinking water, therefore, would give time to residents to accomplish other profitable tasks.
G. Project Partners
In the barangay level, the direct partner during the construction phase is the Barangay Council. Other organizations in the barangay such as the purok, youth and women’s organization will contribute to labor component of project construction. Once operational, the Barangay Bote Water and Sanitation Association with the assistance of the Barangay Council and the Municipal Government will take charge in the operation and maintenance of the project.
H. Technical Evaluation
The proposed water tank will be constructed within the mountainous terrain having an elevation of 73.24 meters and distance of 3.069 kilometers from the service area. With slopes ranging from 8-15 percent and soil components primarily made of Luciana clay, the site is not susceptible to landslide and erosion. Also, the proposed site is not susceptible to excessive surface run-off or flooding, not located near an active fault line, and will not disturb any historical and monumental markers.
II. Project Components and Implementation Schedule
Table 2. Time table of Activities Activities
Date
Responsible
Agency
/
Office 1. Creation Water
of and
Municipal April 10, 2014
Office of the Mayor
Sanitation
(WATSAN) Council and Water
and
(WATSAN)
Sanitation Team
or
Project Management Unit 2. Authorization
of
the April 14, 2014
Office of the Sangguniang
Mayor to enter into a MOA
through
Bayan
SB
Resolution 3. Conduct
of
community April 21, 2014
consultation
WATSAN,
Barangay
Council
4. Water sources inventory
April-May, 2014
WATSAN,
Barangay
Council,
Municipal
Engineering Office 5. Organization/Reactivation
April, 2014
of Barangay Bote Water
WATSAN,
Barangay
Council
and Sanitation Association 6. Preparation, and
submission April – September, 2014
approval
of
the
required documents and
WATSAN,
DILG
Provincial Office, DILG Regional Office No. 5
other necessary materials 7. MOA signing and transfer October, 2014 of fund
Office of the Mayor, DILG Provincial Office, DILG Regional Office No. 5, WATSAN
8. Project Implementation a. Procurement
and October, 2014
BAC, GSO
Delivery of Supplies and Materials b. Construction of Water October-December, 2014 Tank and Pipe Laying
Municipal
Engineering
Office, Barangay Council, People’s (Purok,
Organization Youth
and
Women), WATSAN (Bote and MLGU) c. Liquidation Expenses
of December, 2014 through
WATSAN,
Municipal
Treasurer,
Municipal
preparation
and
Accountant, Auditor, DILG
submission
of
Provincial Office, DILG
Statement
of
Expenditures and
Regional Office No. 5
(SOE)
Receipt
of
Disbursement d. Inauguration Transfer
and December, 2014
of
Office
Project
of
Barangay
the Council,
Management to Bote
Water
Water and Sanitation
Association,
Association
WATSAN
e. Project Monitoring
October 2014 onwards
Mayor,
and
Bote
Sanitation LGU-
Project Management Unit / LGU-WATSAN
III. Work and Financial Plan
Table 3. Work and Financial Plan Physi cal
Project Component / Particular
Targe t
Cost
Financial Requirements
per
Beneficia
LGU-
Item
ry Equity
Bato
DILG
Total
A. Pre-Implementation Phase 1. Creation of Municipal Water and Sanitation (WATSAN) Council and
Water
and
1,000.0
1,000.00
1,000.00
3,000.00
3,000.00
12,000.
12,000.0
12,000.00
00
0
0
Sanitation
(WATSAN) Team or Project Management Unit (PMU) 2. Authorization of the Mayor to enter into a MOA through SB Resolution 3. Conduct
of
community
consultation 4. Water (including
3,000.0 0
sources
inventory
salaries/wages
of
permanent/casual employees) 5. Organization/Reactivation Barangay
Bote
of
Water
1,000.0
1,000.00
1,000.00
and
0
and
10,000.
10,000.0
00
0
5,000.0
5,000.00
5,000.00
31,000.0
32,000.00
Sanitation Association 6. Preparation, approval
submission
of
the
required
10,000.00
documents and other necessary materials
(including
water
permit) 7. MOA signing and transfer of fund
0 1,000.00
Sub-Total
0 B. Implementation Phase 1. Procurement and Delivery of Supplies and Materials 2. Construction of filtration tank, reservoir,
water
structure
and
(Materials,
impounding pipe
laying
Labor
and
20,000.0
90,000.0
900,000.
1,010,000.
0
0
00
00
(in-kind: labor)
Contigencies) 3. Liquidation of Expenses through
500.00
500.00
500.00
5,000.0
5,000.00
5,000.00
20,000.0
95,500.0
1,015,500.
0
0
00
5,000.00
5,000.00
preparation and submission of Statement of Expenditures (SOE) and Receipt of Disbursement 4. Inauguration and Transfer of Project Management to Bote
0
Water and Sanitation Association Subtotal
C. Project Monitoring / Post Implementation Phase 1. Project Monitoring
5,000.0
0 5,000.00
Sub-Total TOTAL PROJECT COST
Project Share (%)
5,000.00
21,000.0
131,500.
900,000.
1,052,500.
0
00
00
00
2%
12.5%
85.5%
IV. Project Management
The Municipal Water and Sanitation Council shall be the over-all in-charged in ensuring the sound implementation of the Project. The Municipal Water and Sanitation Team shall function as the Project Management Unit. They shall oversee the project in its construction phase and shall be directly accountable in the imposition of proper on-and-post project management scheme, internal monitoring and evaluation procedures.
V. Project Sustainability
Once completed, the project shall be turned over to the Bote Water and Sanitation Association and shall be directly responsible for the operation and management of the project. Water fee shall be imposed at the rate of P20.00 per household to cover monthly operational expenses and to cover future repair and replacement of pipes and other materials and facilities.