Lockout - Tagout (LOTO) Procedure: Equipment Service/ Maintenance Required
Expect Startup or Release of Stored Energy?
•Setup •Adjustments •Repairs •Cleaning •Lubrication •Clearing a Jam
YES LOTO Required
No Must Bypass Safety Device?
YES
No
Can place any body part where can be caught in machinery?
No
1
YES GSD FM C&P includes LOTO requirement in contract
No LOTO Not Required / Perform Work
Use a Contractor?
YES
•Contract Workers must follow OSHA LOTO requirements •C&P provides site & hazard information
Safety, 737-2315 Revised: August 2015
Lockout - Tagout (LOTO) Procedure: 1
Prepare for Shutdown
Turn Off Equipment (use Normal shutdown)
Notify Affected Employees
•Know power sources •Know hazards •Know how to control hazards
•Location •Time & Duration •Authorized Worker
Group Lockout device(s) / procedure required
YES
2 More than One employee?
No Perform Work
Can energy control be physically locked out?
No Apply lock and tag to each control point
YES Did equipment turn on / stay energized?
•See equipment on-site reference card
No
•Multi-lock hasp •Group lock box
2
3
YES
Locate all Primary & Secondary Energy Controls
Verify equipment will not operate •Use normal procedure to turn equipment On •Use test meter/equipment to confirm as deenergized
Clear people away from equipment •Install barricades, as required
Control/Make stored energy safe
Apply tag to each control point
Whether power is On/Off, energy is always present •Wear PPE •Ground electricity •Release trapped energy •Support / restrain moving parts •Purge pipes / containers Safety, 737-2315 Revised: Dec 2011
Lockout - Tagout (LOTO) Procedure:
2 YES
Need to test or reposition equipment?
3
YES
Conduct test or reposition equipment
Remove LOTO as required
Need to continue maintenance?
•Maintain as much LOTO as possible
No
No Shift change?
YES
Going-Off Crew briefs OnComing Crew of job status
On-Coming Crew installs LOTO
Going-Off Crew removes LOTO
No Residual energy build up?
YES
Control
Equipment ready for normal use
No
No
Work completed?
Make equipment safe
Notify Affected Employees
•Ensure reassembly completed •Remove all tools •Remove all blanks, blocks, supports, etc.
Remove LOTO
Reenergize equipment
Safety, 737-2315 Revised: Dec 2011