ADVANCE PRODUCT QUALITY PLANNING - MATRIX CATEGORY FOR APQP *** Critical Activities - requires micro level timing chart @ Involves Management's Review
X
Primary Responsibility
O
Supporting Responsibility
Y
Applicable
TYPE OF DEVELOPMENT
1.PLAN AND DEFINE PROGRAM
Phases
S.No.
DESCRIPTION
Doc. Informatio n No Issue No
LEGEND
NPD
ECN
PCN
Rev.No Rev.Date
RESPONSIBLE DEPARTMENT Custom MGT er
MKT
NPD
1.01
Receipt review of enquiry, Engineering drawing and Engg specfication and material specification
Y
X
1.02
Feasibility study
Y
X
1.03
Identification of special characteristics
Y
X
1.04
Review of customer specific requirement check list
Y
X
1.05
Quotation
Y
1.06
Receipt of conformation from the customer
Y
1.07
Contract review
Y
1.08
Preparation of project development team
Y
1.09
Past history study & Quality information
Y
1.10
Joint review of QMS
Y
1.11
Project planning
Y
1.12
List of special charactristics
Y
X
1.13
Preliminary process flow chart
Y
X
X
O
QA
PUR
MFG
DOCUMENTS
Feasibility Review O
O
X
O
O
X
X
X
O
O X
O
O
COMMTRADE METALS
X
O
X
Past History Report
O X
X Process Flow Chart
1.PLAN AND DEFINE PRO
2 of 6
ADVANCE PRODUCT QUALITY PLANNING - MATRIX CATEGORY FOR APQP *** Critical Activities - requires micro level timing chart @ Involves Management's Review
X
Primary Responsibility
O
Supporting Responsibility
Y
Applicable
TYPE OF DEVELOPMENT
2.Preliminary Manufacturing Process Design & Development
1.PLAN AND DEFINE PROGRAM
Phases
S.No.
DESCRIPTION
Doc. Informatio n No Issue No
LEGEND
NPD
ECN
PCN
Rev.No Rev.Date
RESPONSIBLE DEPARTMENT Custom MGT er
MKT
NPD
QA
X
X
PUR
MFG
DOCUMENTS
1.14
Realiability and quality goals
Y
1.15
Preliminary BOM
Y
1.16
Training
Y
1.17
Lesson learnt
Y
1.18
Manpower Allocation
1.19
Capital Requirement
Y
X
1.20
Area location
Y
X
1.21
Raw material development and procurement
Y
O
1.22
Team feasibility commitment
Y
X
O
O
O
1.23
Top Management Review
Y
O
X
O
O
O
MOM
1.24
CFT Review
Y
O
X
O
O
O
MOM
2.01
Key Characteristics
Y
X
O
2.02
Process Flow Diagram
Y
X
O
X Y
O
COMMTRADE METALS
O
O
O
Prelimiary BOM
O
O
X
Training Records
X
X
O
Lesson Learnt Sheet
O
O
X
O O
O O
O X
O Process Flow diagram
3 of 6
ADVANCE PRODUCT QUALITY PLANNING - MATRIX CATEGORY FOR APQP *** Critical Activities - requires micro level timing chart 2.Preliminary Manufacturing Process Design & Development
@ Involves Management's Review
2.Preliminary Manufacturing Process Design & Development
Phases
Doc. Informatio n No Issue No
LEGEND X
Primary Responsibility
O
Supporting Responsibility
Y
Applicable
TYPE OF DEVELOPMENT
Rev.No Rev.Date
RESPONSIBLE DEPARTMENT
S.No.
DESCRIPTION
2.03
Process FMEA, control plan & SOP
Y
X
2.04
Supervisor & Operator Training
Y
X
O
2.05
Tool,Mould, Fixture,Gauges & Measuring Equipment list
Y
X
O
2.06
Release of purchase order
Y
2.07
FTG Requirments
NPD
ECN
PCN
Custom MGT er
MKT
NPD
QA
PUR
MFG
DOCUMENTS
O
Reports
O
Training Records
X
2.07.01 Die Development
Y
X
O
2.07.02 Machine Requirement
Y
X
O
2.07.03 Design study for fixture
Y
X
O
2.07.04 Gauges
Y
X
2.07.05 Operator Training
Y
X
O
O Training Records
2.08
Die Trail & Layout Inspection
Y
X
O
2.09
Fixture & Tool Installation
Y
X
O
O
2.10
Machining Trail & Layout Inspection
Y
X
O
O
2.11
Packing Standard
Y
X
COMMTRADE METALS
Inspection Reports
Inspection Reports Packing Standard
2.Preliminary Manufacturing Process Design & Develo
4 of 6
ADVANCE PRODUCT QUALITY PLANNING - MATRIX CATEGORY FOR APQP *** Critical Activities - requires micro level timing chart
ing Process,product validation and mass production
3.Final Manufacturing Process
Phases
@ Involves Management's Review
X
Primary Responsibility
O
Supporting Responsibility
Y
Applicable
TYPE OF DEVELOPMENT S.No.
DESCRIPTION
Doc. Informatio n No Issue No
LEGEND
NPD
ECN
PCN
Rev.No Rev.Date
RESPONSIBLE DEPARTMENT Custom MGT er
MKT
NPD
QA
PUR
MFG
X
O
O
O
X
O
2.12
Project Review
Y
2.13
Top Management Review
Y
2.14
Submission of proto sample/PP sample
Y
2.15
Customer Approval/Feed back
Y
3.01
Final Process Flow chart
Y
X
3.02
Review of PFMEA
Y
X
3.03
Review of Control Plan
Y
X
3.04
SOP
Y
X
3.05
Operator Training
Y
X
3.06
MSA & Process capability analysis plan
Y
O
3.07
Project Review
Y
X
4.01
Initial Production run
Y
X
O
4.02
MSA report
Y
O
X
4.03
Operator Training
Y
X
4.04
Process capability
Y
O
X
4.05
Supplier PPAP Approval Y
X
O
4.05.01 Review of Process FMEA, Control plan, SOP
DOCUMENTS
X O
O
X
COMMTRADE METALS
Process flow chart O
PFMEA Report
O
Training Records
X
O MSA Report O
Training Records
5 of 6
4.Manufacturing Process,product validation and mass production
ADVANCE PRODUCT QUALITY PLANNING - MATRIX CATEGORY FOR APQP *** Critical Activities - requires micro level timing chart
5.FEEDBACK ASSESSMENT AND CORRECTIVE ACTION
Phases
Rev No.
@ Involves Management's Review
X
Primary Responsibility
O
Supporting Responsibility
Y
Applicable
TYPE OF DEVELOPMENT S.No.
DESCRIPTION
Doc. Informatio n No Issue No
LEGEND
NPD
ECN
PCN
Rev.No Rev.Date
RESPONSIBLE DEPARTMENT Custom MGT er
MKT
NPD
QA
4.05.02 Production run for PPAP
Y
X
O
4.05.03 Project Review
Y
X
O
4.05.04 Quality Planning & signoff
Y
X
O
4.06
Release of Control plan, drawing, SOP & Tooling List
Y
X
O
4.07
SOP Signoff
Y
X
O
Y
X
O
4.07.01 SOP-Mass Production
PUR
MFG
MOM
APQP Problem summary sheet
5.01
Customer Feedback
Y
X
O
O
5.02
Corrective Action
Y
X
O
O
5.03
Leasson Learned
Y
X
O
O
5.04
Project Handover
Y
X
Description
Date
COMMTRADE METALS
Prepared by
DOCUMENTS
O
6 of 6
ADVANCE PRODUCT QUALITY PLANNING - MATRIX CATEGORY FOR APQP *** Critical Activities - requires micro level timing chart @ Involves Management's Review
X
Primary Responsibility
O
Supporting Responsibility
Y
Applicable
TYPE OF DEVELOPMENT Phases
S.No.
DESCRIPTION
Doc. Informatio n No Issue No
LEGEND
NPD
ECN
PCN
Rev.No Rev.Date
RESPONSIBLE DEPARTMENT Custom MGT er
COMMTRADE METALS
MKT
NPD
QA
PUR
MFG
DOCUMENTS