PROJECT PROCEDURE WORK METHOD STATEMENT FOR TANK HYDROSTATIC TEST DOC. NO. : IONE-AA00-MS-MS-0018 KARBALA REFINERY PROJECT
Rev. 0
Page
1/26
Ref. FEED DOC. No. : N/A
WORK METHOD STATEMENT FOR TANK HYDROSTATIC TEST
PROJECT
:
KARBALA REFINERY PROJECT
LOCATION
:
KARBALA, IRAQ
EMPLOYER
:
STATE COMPANY FOR OIL PROJECTS (SCOP)
0
20 DEC. ‘18
ISSUED FOR CONSTRUCTION
B.Y.KIM
C.E.Ryu
Y.S.Kim
Y.B.Lim
H.S.HWANG
A
10 NOV. ‘18
ISSUED FOR APPROVAL
B.Y.KIM
C.E.Ryu
Y.S.Kim
Y.B.Lim
H.S.HWANG
REV.
DATE
DESCRIPTION
PRPD
CHKD
CHKD (PQM)
REVD (PM)
APPRD (PD)
CONFD (SCOP)
Joint Venture of Hyundai Engineering & Construction Co., Ltd., GS Engineering & Construction Co., Ltd., SK Engineering & Construction Co., Ltd., and Hyundai Engineering Co., Ltd., Note : a) Revision bar(vertical line) shall be placed in the right hand margin to indicate where the changes has been made b) PRPD = Prepared by, CHKD = Checked by, REVD = Reviewed by, APPRD = Approved by, CONFD = Confirmed by
HDGSK JV - Gran Seoul Tower 1, 33, Jong-ro, Jongno-gu, Seoul, Korea
PROJECT PROCEDURE WORK METHOD STATEMENT FOR TANK HYDROSTATIC TEST DOC. NO. : IONE-AA00-MS-MS-0018 Rev. 0
KARBALA REFINERY PROJECT
Page
Ref. FEED DOC. No. : N/A
REVISION HISTORY Rev.
Date
Description
Page
A
10 NOV. ‘18
Issued for Approval
ALL
0
20 DEC. ‘18
Issued for Construction
ALL
HDGSK JV - Gran Seoul Tower 1, 33, Jong-ro, Jongno-gu, Seoul, Korea
2/27
PROJECT PROCEDURE WORK METHOD STATEMENT FOR TANK HYDROSTATIC TEST DOC. NO. : IONE-AA00-MS-MS-0018 Rev. 0
KARBALA REFINERY PROJECT
Page
Ref. FEED DOC. No. : N/A
CONTENTS 1.
PURPOSE
2.
SCOPE
3.
DEFINITIONS
4.
REPERENCE STANDARD
5.
WORKS 5.1 PRELMINARY WORKS 5.2 TEST MEDIUM 5.3 TESTING OF FIXED ROOF TANK 5.4 TESTING OF FIXED ROOF 5.5 TESTING OF EXTERNAL FLOATING ROOF TANK 5.6 TESTING OF INTERNAL FLOATING TANK 5.7 SETTLEMENT NEASUREMENT 5.8 DRAIN AND DRY AFTER TEST
ATTACHMENT
>> FIGURE 1 – SETTLEMENT MEASUREMENT DIAGRAM >> FIGURE 2 – CONE ROOF TANK >> FIGURE 3 – DOME ROOF TANK (INCLUDE INTERNAL FLOATING ROOF) >> FIGURE 4 – FROATING ROOF TANK >> TABLE 1 – APPLICATION ITEMS >> TABLE 2 – HYDROSTATIC TEST FOR VERTICAL STORAGE TANKS >> ORGANIZATION FOR TANK HYDROSTATIC TEST >> DIAGRAM OF FLOW WATER 1 – TANKS OF 5D 51AREA >> DIAGRAM OF FLOW WATER 2 – TANKS OF 5D 30 & 34AREA >> DIAGRAM OF FLOW WATER 3 – TANKS OF 4B 52AREA >> DIAGRAM OF FLOW WATER 4 – TANKS OF 4A 52, 3A 31, 3A 35 AND 3B 37AREA >> DIAGRAM OF FLOW WATER 5 – TANKS of 4C 52AREA >> DIAGRAM OF FLOW WATER 6 – TANKS of 4D 52AREA >> DIAGRAM OF FLOW WATER 7 – TANKS of 1F 08, 1G 07, 1H 16&17&18&19&20 AND 5A 44AREA >> DIAGRAM OF FLOW WATER 8 – TANKS of 4C 52&53 AREA
HDGSK JV - Gran Seoul Tower 1, 33, Jong-ro, Jongno-gu, Seoul, Korea
3/27
PROJECT PROCEDURE WORK METHOD STATEMENT FOR TANK HYDROSTATIC TEST DOC. NO. : IONE-AA00-MS-MS-0018 Rev. 0
KARBALA REFINERY PROJECT
Ref. FEED DOC. No. : N/A >> DIAGRAM OF FLOW WATER 9 – TANKS of 6D 90AREA >> SPECIFICATION SHEET OF WATER PUMP >> OUTLINE DRAWING OF WATER PUMP
HDGSK JV - Gran Seoul Tower 1, 33, Jong-ro, Jongno-gu, Seoul, Korea
Page
4/27
PROJECT PROCEDURE WORK METHOD STATEMENT FOR TANK HYDROSTATIC TEST DOC. NO. : IONE-AA00-MS-MS-0018 Rev. 0
KARBALA REFINERY PROJECT
Page
5/27
Ref. FEED DOC. No. : N/A
1.0 PURPOSE
This purpose of this work method statement is to establish a procedure for the hydrostatic test of all tanks as guideline for the Subcontractor, EPC contractor and Company representative. This document will serve as guide for the Construction management, HSE, Quality and field personal for the planning, control, installation and inspection in completing the work in accordance to project requirements
2.0 SCOPE
This method statement provides the instruction for hydrostatic test of all Tank on the Karbala Refinery Project.
3.0 DEFINITIONS
The following definitions shall be applied throughout the this work method statement; Owner is defined as State Company for oil project (SCOP)
Contractor is defined as the laws of the Republic of Korea Hyundai Engineering & Construction Company Limited, GS Engineering & Construction Corporation, SK Engineering & Construction Company Limited and Hyundai Engineering Company Limited (HDGSK JV) Vendor or Subcontractor is a Manufacturer’s collaborator which performs one or more Processes on contract basis and behalf of the Manufacturer such as nondestructive Examination, post-weld heat treatment and painting, etc. Ø Ø Ø Ø Ø
Company Contractor PPE KRP HSE
: State Company for Oil Project (SCOP) : HDGSK JV : Personal Protective Equipment :Karbala Refinery Project (Karbala City) :Health, Safety and Environment
4.0 REPERENCE STANDARD 4.1 STANDARD AND CODES th 1) API Standard 650 12 Ed., 2013 Welded Tanks for Oil Storage 2) API Standard 620 12th Ed., 2013 Design and Construction of Large, Welded, Low-pressure Storage Tank 3) ASME Section V, 2013 Ed. Nondestructive Examination 4) ASME Section IX, 2013 Ed. Welding and Brazing Qualification
HDGSK JV - Gran Seoul Tower 1, 33, Jong-ro, Jongno-gu, Seoul, Korea
PROJECT PROCEDURE WORK METHOD STATEMENT FOR TANK HYDROSTATIC TEST DOC. NO. : IONE-AA00-MS-MS-0018 Rev. 0
KARBALA REFINERY PROJECT
Page
6/27
Ref. FEED DOC. No. : N/A 4.2 PROJECT SPECIFICATION 1) 2342-AA00-JSS-2520-01_0 General Supply Rules for Fixed Floating Roof Tank 2) 2342-AA00-JSS-6300-04_0 Job Specification for Supply Positive Alloy Material Identification of Equipment and Piping 3) 2342-AA00-JSS-2520-05_0 Job Specification for welding and NDE Storage Tanks 4) 2342-AA00-JSM-501_0 Quality Management Requirement for EPC Contractor 5) 2342-AA00-MS-1320-51_0 Construction Specification for Piping Prefabrication, Erection and NDE 6) 2342-AA00-JSM-701_0 HSE Requirements 4.3 PROCEDURE 1) IONE-AA00-PE-QA-0026 2) IONE-AA00-PE-QA-0029 3) IONE-AA00-ITP-MS-0002 4) IONE-AA00-ITP-MS-0004 5) IONE-AA00-WPS-QA-0003
Shop Inspection and Test Procedure for Field Storage Tank Field Inspection & Test Procedure at site for Field fabrication tank Inspection & Test Plan at Site for Storage Tanks Inspection & Test Plan at Shop for Field Fabrication Tank Welding Procedure Specification (Tank)
5.0 WORKS Unless otherwise agreed between the Contractor and Manufacturer, the Manufacturer shall be responsible for those defined in the clause 7.3.6.2 of API 650. Unless otherwise agreed between the Contractor and Manufacturer, the Contractor shall be responsible for those defined in the clause 7.3.6.3 of API 650. 5.1 PRELIMINARY WORKS Prior to the hydrostatic testing, it shall be confirmed that all specified nondestructive examinations of welds and all inspection have been completed according to applicable standards and shall be conducted before permanent external piping is connected to the tank. The inside of tank shall be cleaned out with broom. Before the tank is filled with test water, the reference points for settlement measurement shall be marked on the tank shell or on the ring wall and initial level reading shall be taken and recorded. A clear tube will be installed on the tank with one end connected to one of the lowest openings and the other run up to the top of the shell along the stairway to monitor water level during the test. Be sure that at least one roof manhole shall be kept open while filling or empting a fixed roof tank for test purpose to prevent damages to tank caused by expressive pressure or vacuum.
HDGSK JV - Gran Seoul Tower 1, 33, Jong-ro, Jongno-gu, Seoul, Korea
PROJECT PROCEDURE WORK METHOD STATEMENT FOR TANK HYDROSTATIC TEST DOC. NO. : IONE-AA00-MS-MS-0018 Rev. 0
KARBALA REFINERY PROJECT
Page
Ref. FEED DOC. No. : N/A Internal bottom elevation measurements shall be made before and after hydro-testing in accordance with the applicable paragraph.
5.2 TEST MEDIUM Water shall be substantially clean and clear and no objectionable odor In addition, the quality of test water shall be supplied in accordance with the related codes and specifications. For carbon and low alloy steel tanks, the tank metal temperature shall not be colder than the design metal temperature per Figure 4-1 of API 650 as long as the water is prevented from freezing. In exceptional circumstances when test water temperature falls below this value, then filling shall not proceed without approval of the Company. The temperature of water used for testing shall be at least 7°C. After completion of hydrostatic test, any standing water, silt or dirt left in the tank shall be cleaned out by proper methods and totally dried, and this one is apply to all tanks. 5.3 TESTING OF FIXED ROOF TANK After the entire tank is completed but before any permanent external piping is connected to the tank, the tank shall be tested by the following methods; The shell of fixed roof tanks shall be tested after completion of the roof. Maximum filling rate to consider a settlement of the tank shall be as per drawing. The tank may be half-filled with test water as quickly as practicable, having regard to size, the pumping facilities and water supply available. Further water filling shall not proceed until levels have been taken and checked against the readings when empty to ensure that no uneven settlement is occurring, in which case water filling can be proceed until the tank is three-quarters full, and level readings shall be taken again. Provided the tank remains level with only slight settlement due to load, filling can proceed until the tank is fully filled with test water to the maximum design liquid level given in Table 2 of this work method statement. After the tank is filled with water, the shell and the anchorage shall be visually inspected for tightness. The tank shall be inspected frequently during the filling operation, and any welded joints above the test water level shall be examined for leakage.
HDGSK JV - Gran Seoul Tower 1, 33, Jong-ro, Jongno-gu, Seoul, Korea
7/27
PROJECT PROCEDURE WORK METHOD STATEMENT FOR TANK HYDROSTATIC TEST DOC. NO. : IONE-AA00-MS-MS-0018 Rev. 0
KARBALA REFINERY PROJECT
Page
Ref. FEED DOC. No. : N/A The full water load shall be held for 24 hours with no leaks. A level reading shall be taken after holding time, respectively to check the stability of the foundation prior to dewatering. During holding of test water, all welds below the water filling level including the corner weld between the shell and the bottom shall be visually checked, especially those which are close to the welded seams of shell side. Before test water is drained out, the roof manhole covers shall be opened to prevent damages to tank caused by vacuum. If no leakage was found on all welds and connections, the hydrostatic test is accepted. 5.4 TESTING OF FIXED ROOF - Roof of a tank designed to be gas-tight Upon completion, the roof of a tank designed to be gas-tight (except for roofs designed under F.4.4 and E.7.5 of API Std. 650) shall be tested by one of the following methods; a.
Applying internal air pressure not exceeding the weight of the roof plates and applying to the weld joints a bubble (soap) solution or other material suitable for the detection of leaks.
b.
Vacuum testing weld joints in accordance with 8.6 of API Std. 650 to detect any leaks.
When the entire tank governed by Appendix F of API standard 650 is completed, it shall be tested as per standard and code. - Roof of a tank not designed to be gas-tight Upon completion, the roof of a tank not designed to be gas-tight, such as a tank with peripheral circulation vents or a tank with free or open vents, shall receive only visual examination of its weld joints, unless otherwise specified by the Company. 5.5 TESTING OF EXTERNAL FLOATING ROOF TANK After the entire tank is completed but before any permanent external piping is connected to the tank, the tank shall be tested by the following methods. For the shell testing of a floating roof tank, the weather seal shall not be installed. The test level shall be to a height such the secondary seal is just retained within the shell. Maximum filling rate to consider a settlement of the tank shall be as per drawing.
HDGSK JV - Gran Seoul Tower 1, 33, Jong-ro, Jongno-gu, Seoul, Korea
8/27
PROJECT PROCEDURE WORK METHOD STATEMENT FOR TANK HYDROSTATIC TEST DOC. NO. : IONE-AA00-MS-MS-0018 Rev. 0
KARBALA REFINERY PROJECT
Page
Ref. FEED DOC. No. : N/A The tank may be half-filled with test water as quickly as practicable, having regard to size, the pumping facilities and water supply available. Further water filling shall not proceed until levels have been taken and checked against the readings when empty to ensure that no uneven settlement is occurring, in which case water filling can proceed until the tank is three-quarters full, and level readings shall be taken again. Provided the tank remains level with only slight settlement due to load, filling can proceed until the tank is fully filled with test water to the maximum design liquid level given in Table 1 of this work method statement. The tank shall be inspected frequently during the filling operation, and any welded joints above the test water level shall be examined for leakage. During water filling, the difference in space between the shell and the periphery of the deck shall be recorded. During the hydro-test, the roof drain valves shall be kept open and observed for leakage of the tank contents into the drain lines. The hydrostatic test water load as defined on the drawing shall be held for 24 hours with no leaks. A level reading shall be taken after holding time, respectively to check the stability of the foundation prior to dewatering. During holding of test water, all welds below the water filling level including the corner weld between the shell and the bottom shall be visually checked especially those which are close to the welded seams of shell side. If no leakage was found on all welds and connections, the hydrostatic test is accepted. Single-deck pontoon-type and double-deck-type floating roofs shall be tested by the following methods. The hydrostatic test of floating roof tanks shall include examinations for water leaks inside pontoon and double deck compartments and through the single deck. The examination for roof leaks may be conducted at any convenient flotation level but not when it is wet or raining. The maximum and minimum annular space between the shell plate and the roof rim plate prior to initial flotation and at the maximum test fill height shall be measured and recorded.
HDGSK JV - Gran Seoul Tower 1, 33, Jong-ro, Jongno-gu, Seoul, Korea
9/27
PROJECT PROCEDURE WORK METHOD STATEMENT FOR TANK HYDROSTATIC TEST DOC. NO. : IONE-AA00-MS-MS-0018 Rev. 0
KARBALA REFINERY PROJECT
Page
Ref. FEED DOC. No. : N/A The floating roof shall be given a flotation test while the tank is being filled with water and emptied. During this test, the upper side of the lower deck shall be examined for leaks visually. The appearance of a damp spot on the upper side of the lower deck shall be considered evidence of leakage. During filling and emptying of the tank, the roof shall be monitored for even flotation. A half-full and full, the shell shall be checked for circularity and measurements recorded. The upper side of the upper decks of pontoon and double deck roofs shall be visually inspected for pinholes and defective welding. Roof drain system shall have been pre-tested to 350kPa (50 psi) gauge prior to filling the tank. During the floating test, the roof drain valve shall be kept open and observed for leakage of the contents into the drain lines. 5.6 TESTING OF INTERNAL FLOATING ROOF If internal floating roof is required to the tank, the requirements for testing shall be in accordance with Appendix H-internal Floating Roofs of API Std. 650. For aluminum or stainless steel floating roofs, the quality of test water shall be in accordance with S.4.10 of API Std. 650. 5.7 SETTLEMENT MEASUREMENT The tank settlement shall be measured in accordance with the following: The maximum filling rates shall be as follows. Water Filling Rate Bottom Course Thickness Less than 22 mm 22 mm and thicker
Tank Portion Top course Below top course Top third of tank Middle third of tank Bottom third of tank
Maximum Filling rate 300 mm/hr 460 mm/hr 230 mm/hr 300 mm/hr 460 mm/hr
Filling may continue while elevation measurements are being made as long as the change in water elevation for a set of readings does not exceed 300 mm. Shell elevation measurements shall be made at equally-spaced intervals around the tank circumference not exceeding 10 m. The minimum number of shell measurement points shall be eight.
HDGSK JV - Gran Seoul Tower 1, 33, Jong-ro, Jongno-gu, Seoul, Korea
10/27
PROJECT PROCEDURE WORK METHOD STATEMENT FOR TANK HYDROSTATIC TEST DOC. NO. : IONE-AA00-MS-MS-0018 Rev. 0
KARBALA REFINERY PROJECT
Page
Ref. FEED DOC. No. : N/A
Observed elevation shall be referred to a permanent benchmark. The level instrument shall be set up at least 1½ times tank diameter away from the tank when tank elevation readings are taken. Six set of settlement readings are required. 1) 2) 3) 4) 5) 6)
Before start of the hydrostatic test With tank filled to ¼ test height (± 600 mm) With tank filled to ½ test height (± 600 mm) With tank filled to ¾ test height (± 600 mm) At least 24 hours after the tank has been filled to the maximum test height After tank has been emptied of test water
Note: The three sets of settlement readings described in paragraph 2), 3), and 4) above may be omitted if specified by the Company. Graphical diagram of the hydrostatic test and the settlement measurement is as shown below. (Water Level) Full filling 3/4 filling
Leak Check (At least 24 hours)
1/2 filling 1/4 filling
(Time) : Settlement Reading Points
Figure 1 - Settlement Measurement Diagram * Measurement time and holding period will be decided by considering actual settlement of tank.
HDGSK JV - Gran Seoul Tower 1, 33, Jong-ro, Jongno-gu, Seoul, Korea
11/27
PROJECT PROCEDURE WORK METHOD STATEMENT FOR TANK HYDROSTATIC TEST DOC. NO. : IONE-AA00-MS-MS-0018 Rev. 0
KARBALA REFINERY PROJECT
Page
Ref. FEED DOC. No. : N/A
Any differential settlement greater than 13mm per 10m of circumference or a uniform settlement over 50mm shall be reported to the Company for evaluation. Filling of the tank shall be stopped until cleared by the Company.
MANOMETER
TEST WATER LEVEL
AIR LEVEL GAUGE HOSE
SUPPLY
WATER IN / OUTLET
PUMP
Figure 2 - CONE ROOF TANK
TEST WATER LEVEL LEVEL GAUGE (MANO-METER)
PUMP (WATER IN/OUTLET)
PUMP
Figure 3 - DOME ROOF TANK (INCLUDE INTERNAL FLOATING ROOF)
HDGSK JV - Gran Seoul Tower 1, 33, Jong-ro, Jongno-gu, Seoul, Korea
12/27
PROJECT PROCEDURE WORK METHOD STATEMENT FOR TANK HYDROSTATIC TEST DOC. NO. : IONE-AA00-MS-MS-0018 Rev. 0
KARBALA REFINERY PROJECT
Page
Ref. FEED DOC. No. : N/A
TEST WATER LEVEL LEVEL GAUGE WATER
HOSE
IN / OUTLET
PUMP
Figure 4 - FLOATING ROOF TANK 5.7 DRAIN AND DRY AFTER TEST
Tested tank shall be emptied and dried by proper method after hydrostatic test. And test water can be transferred to other tank or discharged to pond as per site condition or test sequence.
HDGSK JV - Gran Seoul Tower 1, 33, Jong-ro, Jongno-gu, Seoul, Korea
13/27
PROJECT PROCEDURE WORK METHOD STATEMENT FOR TANK HYDROSTATIC TEST DOC. NO. : IONE-AA00-MS-MS-0018 Rev. 0
KARBALA REFINERY PROJECT
Page
14/27
Ref. FEED DOC. No. : N/A
>> Table 1- Applicable Items
Area
Item No.
Q’ty
Roof Type
Tank size ID x H (mm)
31-TK-001
1
CRT
ID27000x19200
Fire Water Tank
35-TK-001
1
CRT
ID13800x13300
Condensate Tank
37-TK-001
1
CRT
ID16500x14800
Liquid Fuel Storage Tank
52-TK-101ABCDEF
6
FRT
ID54100x17800
Crude Oil Storage Tank
30-TK-001AB
2
CRT
ID17300x15350
Filtered Water Storage Tank
30-TK-002AB
2
CRT
ID11000x11760
UF Water Storage Tank
30-TK-003AB
2
DRT
ID20650x17100
First Ro Permeate Storage Tank
30-TK-004AB
2
CRT
ID10360x7580
Second Ro Permeate Storage Tank
30-TK-005AB
2
DRT
ID18800x14940
Demineralized Water Tank
30-TK-006AB
2
CRT
ID11600x10973
Storm Water Storage Tank
30-TK-009AB
2
DRT
ID37500x16150
River Water Storage Tank
34-TK-001AB
2
CRT
ID14500x14600
Drinking Water Storage Tank
51-TK-002AB
2
DRT
ID20000x16300
Equalization Tanks
51-TK-005AB
2
CRT
ID7000x11250
First Concentrate Tank
51-TK-006AB
2
CRT
ID5700x7740
Second Concentrate Tank
51-TK-007AB
2
DRT
ID17000x13680
Permeate Storage Tank
51-TK-008AB
2
DRT
ID16900x15170
Treatment Waste Hold Up Tank
51-TK-009AB
2
CRT
ID4600x6400
Spent Caustic Storage Tank
51-TK-010
1
CRT
ID4500x4700
Sulphuric Acid Storage Tank
52-TK-001AB
2
SDFRT ID24300x18400
52-TK-201AB
2
DIFRT
ID33200x18000
NHT Feed Tanks
52-TK-202AB
2
DIFRT
ID18500x19000
Light Naphtha Tanks
52-TK-203AB
2
DIFRT
ID27200x18000
Heavy Naphtha Tanks
52-TK-204AB
2
SDFRT ID24000x18400
KHT Feed Tanks
52-TK-205AB
2
SDFRT ID28600x18400
DHT Feed Tanks
52-TK-206AB
2
DRT
ID32800x18000
VGO HDT Feed Tanks
52-TK-207AB
2
DRT
ID30500x18000
FCC Feed Tanks
52-TK-210AB
2
CRT
ID14400x14400
S.R Heavy Diesel Tanks
Item Name
A-1
A–2
Light Slop Oil Tanks
HDGSK JV - Gran Seoul Tower 1, 33, Jong-ro, Jongno-gu, Seoul, Korea
PROJECT PROCEDURE WORK METHOD STATEMENT FOR TANK HYDROSTATIC TEST DOC. NO. : IONE-AA00-MS-MS-0018 Rev. 0
KARBALA REFINERY PROJECT
Page
Ref. FEED DOC. No. : N/A
Area
Q’ty
Roof Type
Tank size ID x H (mm)
52-TK-303AB
2
DIFRT
ID25500x18000
Cracked Gasoline Tanks
52-TK-304AB
2
DIFRT
ID13800x13700
Polynaphta Tanks
52-TK-305AB
2
DIFRT
ID24500x18000
Desulphurized Kerosene Tanks
52-TK-306AB
2
CRT
ID27800x18000
Desulphurized Diesel Tanks
52-TK-307AB
2
CRT
ID12900x12800
Cycle Oil Tanks
52-TK-308AB
2
DRT
ID42700x18000
Reduced Crude Tanks
52-TK-311AB
2
CRT
ID8900x8900
Clarified Slurry Oil Tank
52-TK-312AB
2
CRT
ID12900x12900
VGO HDT Diesel Tanks
52-TK-403ABC
3
CRT
ID24600x18000
Kerosene Product Tanks
52-TK-404ABC
3
DIFRT
ID25700x18000
ATK Product Tank
60-TK-001AB
2
CRT
ID17000x14900
Break Tanks
60-TK-002
1
CRT
ID4000x4450
Potable Water Tank
52-TK-003
1
CRT
ID18100x18000
Flushing Oil Tank
52-TK-301AB
2
DIFRT
ID18800x19000
Isomerate Tank
52-TK-302AB
2
FRT
ID27100x18600
Reformate Tank
52-TK-401ABC
3
FRT
ID31200x18400
Regulator Gasoline Tank
52-TK-402ABC
3
FRT
ID31200x18400
Premium Gasoline Tank
52-TK-405ABC
3
DRT
ID35300x18000
Diesel Tank
52-TK-406AB
2
CRT
ID16900x17000
Heavy Diesel Tank
52-TK-408ABC
3
DRT
ID53100x18000
Heavy Fuel Oil Tank
07-TK-001
1
CRT
ID9300x10000
Neutralization Storage Tank
08-TK-301
1
CRT
ID3300x3000
COS Solvent Storage Tank
16-TK-001
1
CRT
ID14000x14600
Amine Storage Tank
17-TK-101/201
2
DRT
ID20000x18600
Sour Water Stripper FEED Tank
18/19-TK-001
2
CRT
ID10700x9150
Sulphur Storage Tank
20-TK-001
1
CRT
ID4600x7300
Amine Storage Tank
44-TK-001
1
CRT
ID18000x17500
Refinery Fuel Oil for Gas Turbines
44-TK-002
1
CRT
ID18000x17500
Clarified Slurry Oil Tank
52-TK-209A/B
2
DRT
ID34000x18000
Vacuum Residue Tank
Item No.
B–1
B–2
C
Item Name
HDGSK JV - Gran Seoul Tower 1, 33, Jong-ro, Jongno-gu, Seoul, Korea
15/27
PROJECT PROCEDURE WORK METHOD STATEMENT FOR TANK HYDROSTATIC TEST DOC. NO. : IONE-AA00-MS-MS-0018 Rev. 0
KARBALA REFINERY PROJECT
Ref. FEED DOC. No. : N/A
Area
Q’ty
Roof Type
Tank size ID x H(mm)
53-TK-001A~E
5
CRT
ID12000x12000
Paving Asphalt Tank
53-TK-002A~E
5
CRT
ID6000x6600
Blown Asphalt Tank
90-TK-001ABC
3
FRT
ID34400x18900
Regular Gasoline Tank
90-TK-002ABC
3
FRT
ID34400x18900
Premium Gasoline Tank
90-TK-003ABC
3
CRT
ID25300x18000
Kerosene Tank
90-TK-004ABC
3
DIFRT
ID25900x18000
ATK Tank
90-TK-005ABC
3
DRT
ID42000x18000
Diesel Tank
90-TK-006AB
2
CRT
ID16900x17000
Heavy Diesel Tank
90-TK-010AB
2
FRT
ID12000x8400
Light Slop Tank
90-TK-100
1
CRT
ID27000x19500
Firewater Tank
Item No.
C
Item Name
HDGSK JV - Gran Seoul Tower 1, 33, Jong-ro, Jongno-gu, Seoul, Korea
Page
16/27
PROJECT PROCEDURE WORK METHOD STATEMENT FOR TANK HYDROSTATIC TEST DOC. NO. : IONE-AA00-MS-MS-0018 Rev. 0
KARBALA REFINERY PROJECT
Page
17/27
Ref. FEED DOC. No. : N/A >> Table 2- Hydrostatic Test Tables for Vertical Storage Tanks
Area
A-1
A–2
Max. Design Test Water Liquid Level Level (mm) (mm)
Water Volume (m3)
Test Pressure (kg/cm2)
Roof Type
CODE
31-TK-001
CRT
API650
18040
18040
11451 As per standard
35-TK-001
CRT
API650
12300
12300
2094 As per standard
37-TK-001
CRT
API650
14100
14100
3207 As per standard
52-TK101ABCDEF
FRT
API650
16000
16000
220674 As per standard
30-TK-001AB
CRT
API650
14950
14950
6136 As per standard
30-TK-002AB
CRT
API650
11360
11360
2256 As per standard
30-TK-003AB
DRT
API650
16700
16700
11454 As per standard
30-TK-004AB
CRT
API650
7260
7260
1278 As per standard
30-TK-005AB
DRT
API650
14550
14940
8294 As per standard
30-TK-006AB
CRT
API650
7820
7820
2320 As per standard
30-TK-009AB
DRT
API650
15750
15750
34756 As per standard
34-TK-001AB
CRT
API650
14100
14100
4822 As per standard
51-TK-002AB
DRT
API650
15300
15300
10242 As per standard
51-TK-005AB
CRT
API650
10750
10750
866 As per standard
51-TK-006AB
CRT
API650
7440
7440
396 As per standard
51-TK-007AB
DRT
API650
12920
12920
6210 As per standard
51-TK-008AB
DRT
API650
14450
14450
6816 As per standard
51-TK-009AB
CRT
API650
5900
5900
212 As per standard
51-TK-010
CRT
API650
3880
4700
75 As per standard
52-TK-001AB SDFRT API650
16500
16500
15186 As per standard
52-TK-201AB
DIFRT API650
16600
16600
31166 As per standard
52-TK-202AB
DIFRT API620
17500
17500
10214 As per standard
52-TK-203AB
DIFRT API650
16500
16500
20918 As per standard
52-TK-204AB SDFRT API650
16500
16500
14814 As per standard
52-TK-205AB SDFRT API650
16500
16500
21046 As per standard
Tank No.
52-TK-206AB
DRT
API650
17500
18000
30418 As per standard
52-TK-207AB
DRT
API650
17500
18000
26302 As per standard
52-TK-210AB
CRT
API650
13900
14400
4690 As per standard
HDGSK JV - Gran Seoul Tower 1, 33, Jong-ro, Jongno-gu, Seoul, Korea
Remark
PROJECT PROCEDURE WORK METHOD STATEMENT FOR TANK HYDROSTATIC TEST DOC. NO. : IONE-AA00-MS-MS-0018 Rev. 0
KARBALA REFINERY PROJECT
Page
18/27
Ref. FEED DOC. No. : N/A
Area
B–1
Tank No.
C
CODE
Max. Design Test Water Liquid Level Level (mm) (mm)
Water Volume (m3)
Test Pressure (kg/cm2)
52-TK-303AB
DIFRT API650
16500
16500
8427 As per standard
52-TK-304AB
DIFRT API650
12300
12300
1840 As per standard
52-TK-305AB
DIFRT API650
16500
16500
7779 As per standard
52-TK-306AB
CRT
API650
17500
18000
10926 As per standard
52-TK-307AB
CRT
API650
12300
12800
1673 As per standard
52-TK-308AB
DRT
API650
17500
18000
25776 As per standard
52-TK-311AB
CRT
API650
8400
8900
554 As per standard
52-TK-312AB
CRT
API650
12400
12900
1686 As per standard
52-TK-403ABC
CRT
API650
17500
18000
8555 As per standard
52-TK-404ABC DIFRT API650
16500
16500
8559 As per standard
60-TK-001AB
CRT
API650
14200
14900
3382 As per standard
60-TK-002
CRT
API650
4030
4450
56 As per standard
52-TK-003
CRT
API650
17500
18000
4631 As per standard
DIFRT API650
17500
18000
4997 As per standard
52-TK-301AB
B–2
Roof Type
52-TK-302AB
FRT
API650
16700
16700
9633 As per standard
52-TK-401ABC
FRT
API650
16500
16500
12615 As per standard
52-TK-402ABC
FRT
API650
16500
16500
12615 As per standard
52-TK-405ABC
DRT
API650
17500
18000
17618 As per standard
52-TK-406AB
CRT
API650
16500
17000
3814 As per standard
52-TK-408ABC
DRT
API650
17500
17500
38759 As per standard
07-TK-001
CRT
API650
9580
10000
680 As per standard
08-TK-301
CRT
API650
2800
3000
26 As per standard
16-TK-001
CRT
API650
14100
14600
2248 As per standard
17-TK-101/201
DRT
API650
18100
18600
5844 As per standard
18/19-TK-001
CRT
API650
8450
9150
818 As per standard
20-TK-001
CRT
API650
6000
7320
121 As per standard
44-TK-001
CRT
API650
17000
17500
4454 As per standard
44-TK-002
CRT
API650
17000
17500
4454 As per standard
52-TK-209A/B
DRT
API650
17500
18000
16343 As per standard
HDGSK JV - Gran Seoul Tower 1, 33, Jong-ro, Jongno-gu, Seoul, Korea
Remark
PROJECT PROCEDURE WORK METHOD STATEMENT FOR TANK HYDROSTATIC TEST DOC. NO. : IONE-AA00-MS-MS-0018 Rev. 0
KARBALA REFINERY PROJECT
Page
19/27
Ref. FEED DOC. No. : N/A
Area
C
Max. Design Test Water Liquid Level Level (mm) (mm)
Water Volume (m3)
Test Pressure 2 (kg/cm )
Roof Type
CODE
53-TK-001A~E CRT
API650
11400
12000
1358 As per standard
53-TK-002A~E CRT
API650
6110
6600
187 As per standard
90-TK-001ABC
FRT
API650
17000
18900
17566 As per standard
90-TK-002ABC
FRT
API650
17000
18900
17566 As per standard
90-TK-003ABC
CRT
API650
17500
18000
9050 As per standard
90-TK-004ABC DIFRT API650
16500
18000
9484 As per standard
Tank No.
90-TK-005ABC
DRT
API650
17500
18000
24938 As per standard
90-TK-006AB
CRT
API650
16500
17000
3814 As per standard
90-TK-010AB
FRT
API650
6500
8400
951 As per standard
90-TK-100
CRT
API650
18570
19570
11188 As per standard
LEGEND; - F.W : Full water up to test water level - A.P : Air Pressure (kg/cm 2)
HDGSK JV - Gran Seoul Tower 1, 33, Jong-ro, Jongno-gu, Seoul, Korea
Remark
PROJECT PROCEDURE WORK METHOD STATEMENT FOR TANK HYDROSTATIC TEST DOC. NO. : IONE-AA00-MS-MS-0018 Rev. 0
KARBALA REFINERY PROJECT
Ref. FEED DOC. No. : N/A >> Organization for tank hydrostatic test
Organization for Tank Hydrostatic Test
QA/QC(Kor)
Comander(Kor)
M/G
QA/QC(Kor)
C/M
M/G
Day work
Night work QA/QC(TCN)
S/V
Superintendent(Kor)
QA/QC(TCN)
F/M
S/V
Day Work Position
Name
Night Work M.P No.
Position
F/M
F/M
Fitter
Fitter
Helper
Helper
Electrician
Electrician
Name
HDGSK JV - Gran Seoul Tower 1, 33, Jong-ro, Jongno-gu, Seoul, Korea
M.P No.
Page
20/27
PROJECT PROCEDURE WORK METHOD STATEMENT FOR TANK HYDROSTATIC TEST DOC. NO. : IONE-AA00-MS-MS-0018 Rev. 0
KARBALA REFINERY PROJECT
Ref. FEED DOC. No. : N/A >> Diagram of Flow Water 1 – Tanks of 5D 51 Area
>> Diagram of Flow Water 2 – Tanks of 5D 30&34 Area
HDGSK JV - Gran Seoul Tower 1, 33, Jong-ro, Jongno-gu, Seoul, Korea
Page
21/27
PROJECT PROCEDURE WORK METHOD STATEMENT FOR TANK HYDROSTATIC TEST DOC. NO. : IONE-AA00-MS-MS-0018 Rev. 0
KARBALA REFINERY PROJECT
Ref. FEED DOC. No. : N/A >> Diagram of Flow Water 3 – Tanks of 4B 52 Area
>> Diagram of Flow Water 4 – Tanks of 4A 52, 3A 31, 3A 35, and 3B 37 Area
HDGSK JV - Gran Seoul Tower 1, 33, Jong-ro, Jongno-gu, Seoul, Korea
Page
22/27
PROJECT PROCEDURE WORK METHOD STATEMENT FOR TANK HYDROSTATIC TEST DOC. NO. : IONE-AA00-MS-MS-0018 Rev. 0
KARBALA REFINERY PROJECT
Ref. FEED DOC. No. : N/A >> Diagram of Flow Water 5 – Tanks of 4C 52 Area
52TK401C 52TK401B
52TK401A
52TK405C
52TK405C
52TK405A 52TK003
Inlet Water
52TK406B outlet Water
52TK401C
52TK401B
52TK401A
52TK406A
Water Flow
52-TK-401C
52-TK-401B
52-TK-401A
52-TK-405C
52-TK-405B
52-TK-405A
52-TK-402A
52-TK-402B
52-TK-402C
52-TK-406A
52-TK-406B
52-TK-003
Water Hydrostatic Test Sequence of 4C 52 Area
>> Diagram of Flow Water 6 – Tanks of 4D 52 Area
52TK401C 52TK401B
52TK401A
52TK405C
52TK405C
52TK405A 52TK003
Inlet Water
52TK406B outlet Water
52TK401C
52TK401B
52TK401A
52TK406A
Water Flow
52-TK-401C
52-TK-401B
52-TK-401A
52-TK-405C
52-TK-405B
52-TK-405A
52-TK-402A
52-TK-402B
52-TK-402C
52-TK-406A
52-TK-406B
52-TK-003
Water Hydrostatic Test Sequence of 4C 52 Area
HDGSK JV - Gran Seoul Tower 1, 33, Jong-ro, Jongno-gu, Seoul, Korea
Page
23/27
PROJECT PROCEDURE WORK METHOD STATEMENT FOR TANK HYDROSTATIC TEST DOC. NO. : IONE-AA00-MS-MS-0018 Rev. 0
KARBALA REFINERY PROJECT
Ref. FEED DOC. No. : N/A >> Diagram of Flow Water 7 – Tanks of 1F 08, 1G 07, 1H 16&17&18&19&20 and 5A 44 Area
>> Diagram of Flow Water 8 – Tanks of 4C 52 & 53 Area
HDGSK JV - Gran Seoul Tower 1, 33, Jong-ro, Jongno-gu, Seoul, Korea
Page
24/27
PROJECT PROCEDURE WORK METHOD STATEMENT FOR TANK HYDROSTATIC TEST DOC. NO. : IONE-AA00-MS-MS-0018 Rev. 0
KARBALA REFINERY PROJECT
Ref. FEED DOC. No. : N/A >> Diagram of Flow Water 9 – Tanks of 6D Area
HDGSK JV - Gran Seoul Tower 1, 33, Jong-ro, Jongno-gu, Seoul, Korea
Page
25/27
PROJECT PROCEDURE WORK METHOD STATEMENT FOR TANK HYDROSTATIC TEST DOC. NO. : IONE-AA00-MS-MS-0018 Rev. 0
KARBALA REFINERY PROJECT
Ref. FEED DOC. No. : N/A >> Specification Sheet of Pump
HDGSK JV - Gran Seoul Tower 1, 33, Jong-ro, Jongno-gu, Seoul, Korea
Page
26/27
PROJECT PROCEDURE WORK METHOD STATEMENT FOR TANK HYDROSTATIC TEST DOC. NO. : IONE-AA00-MS-MS-0018 Rev. 0
KARBALA REFINERY PROJECT
Ref. FEED DOC. No. : N/A >> Outline Drawing of Pump
HDGSK JV - Gran Seoul Tower 1, 33, Jong-ro, Jongno-gu, Seoul, Korea
Page
27/27