Tango Skiff 14 Building Log Date 6/24/2009 6/26/2009 6/27/2009 6/28/2009 7/1/2009 7/3/2009 7/3/2009 7/4/2009 7/5/2009 7/9/2009 7/12/2009 7/13/2009 7/14/2009 7/16/2009 9/17/2009 9/18/2009 9/22/2009 9/25/2009 9/29/2009 10/5/2009 10/11/2009 10/17/2009 10/18/2009 10/20/2009 10/21/2009 10/22/2009 10/23/2009 10/24/2009 10/25/2009 10/28/2009 10/29/2009 11/1/2009 11/2/2009 11/3/2009 11/5/2009 11/7/2009 11/8/2009 11/9/2009 11/10/2009 11/11/2009 11/12/2009 11/15/2009 11/18/2009 11/19/2009

Task Cut out and laminated Transom Cut out and scarfed sides together Cut out hull bottoms and scarfed / sanded transom Sanded scarf joints Stitched hull together Cut out bulkheads and seats Cut out parts to build jig Setup boat in jig Spot glued 80% of hull Finished spot gluing Installed Bulkheads and Transom Finished gluing Bulkheads Filleting hull Filleting hull Started Fiberglass Taping Continued Taping Continued Taping Continued Taping Continued Taping Continued Taping Sanded inside of hull Filled around seams with thickened epoxy Sanded tape seams Epoxied entire inside of hull Started fitting and gluing inside rails Finished gluing inside rails Scraped / sanded inside of hull Made from and rear brackets Sanded inside of hull Faired inside of hull Marked and cut out holes for seat hatches Worked on rear of transom Worked on rear of transom Worked on rear of transom Sanded inside of hull and fit seats Faired inside of hull and started sealing seats Sealed seats Worked on installing rear seat Worked on installing middle seat Worked on installing front seat Filleted seats Sanding Sanding / taping seats Blended in seat tape lines

Hours 1.5 3.5 3 1 6.5 3.5 1 2 4 1 4 2 2 1 1 1.5 1.5 1 3 1 1 2.5 1.5 2 1.5 1 2 4 2 2 2 1.5 1 1 6.5 1.5 1 1.5 1.5 2 1 2 3 3

11/28/2009 11/29/2009 11/30/2009 12/1/2009 12/3/2009 12/5/2009 12/8/2009 12/10/2009 12/14/2009 12/15/2009 12/29/2009 12/30/2009 12/31/2009 1/1/2010 1/2/2010 1/3/2010 1/4/2010 1/5/2010 1/7/2010 1/9/2010 1/10/2010 1/11/2010 1/12/2010 1/13/2010 1/14/2010 1/16/2010 2/7/2009 2/14/2010 2/20/2010 2/22/2010 2/23/2009 2/25/2010 2/26/2010 3/4/2010 3/6/2010 3/7/2010 3/10/2010 3/11/2010 3/13/2010 3/17/2010 3/18/2010 3/23/2010 3/25/2010 3/26/2010 3/27/2010 3/28/2010 3/29/2010

Flipped hull / faired outside of hull Sanding and fairing outside of hull Finished getting hull ready for glass Glassed outside of hull Taped under seats and filleted compartments Scraped hull Sanded hull and under seats / faired hull Sanding and refairing of hull Sanded outside of hull Faired under seats Sanded under seats Sanded hull / flipped boat / laminated 1 outside rail Laminated second outside rail Sanded / shaped / filled rails Sanded / filled rails Finished rails / glassed bow and transom brackets Glassed transom 2nd coat epoxy on transom Sanded brackets at bow and transom Sanding Drilled drain hole / fabricated gas tank bracket Cut out and installed motor mounts Finished motor mounts Sanded inside of hull and hung motor Rounded transom and fit motor Faired inside of hull again Sanded interior and transom Sanded interior Sanded interior Sanded interior Washed for primer Primed rails and interior Primed interior Sanded primer Washed primer to get ready for spot putty Spot puttied rails and inside / sanded / reprimed Sanded primer for final interior paint Washed primer / taped boat for 1st topcoat 1st topcoat of white on rails and interior Sanded topcoat for 2nd coat 2nd topcoat on rails and interior Flipped hull / primed outside of hull Sanded / washed / painted outside of hull Touch-up hull paint from tape lines Sanded for 2nd topcoat on outside of hull 2nd topcoat on outside of hull Removed tape cleaned some bleed through

2 1 1 5.5 3 1 5 2.5 3 1 3 1.5 1 2 1 2 2 1 2 1.5 1 2 1 3 0.5 1 4 1.5 1.5 1 2 3 1 1 1 2 1 2 3 1 3 1.5 2 1.5 2 3 1

3/31/2010 4/6/2010 4/8/2010 4/9/2010 4/10/2010 4/11/2010 4/16/2010

Touch-up paint on rails Hull on trailer / installed cleats / 1st seat varnish Motor mounted / 2nd coat of varnish on seats 3rd coat of varnish on seats 4th coat of varnish on seats Installed compartments and rod holders Installed boat numbers

1 5 2 1 1 2 0.5

TOTAL HOURS:

195