32 0 168KB
Shincon Industrial Pte Ltd Risk Assessment Form Project : HDB CONTRACT
WHSO:
Francis Wong (Safety Officer)
Contractor: Shincon Industrial Pte Ltd Work Activity: Preparation of side formwork and steel work.
RA leader :
Rajmohan Vijay (Safety Supervisor)
RA member 1 :
Shaiful Hamli Bin Moktar(Project Co-ordinator)
RA member 2 :
Balasubramanian Karthikeyan (Site Engineer)
Signature :
Original Assessment date : 15 December 2012
RA member 3 :
Andrew Kiang (Site Supervisor)
Name :
Koh Teck Lee
Last review date
:-
RA member 4 :
Thangavel Thangaraj (Foreman)
Designation :
Project Manager
Next review date
: 15 June 2013
RA member 5 :
Date :
15/12/2012
Additional Risk Control
Severity
Likelihood
Risk Level
Preparation of side formwork
Implementation Person
Slipped and fall on the Pallet table
Bodily injury/ Fracture
Control of Oil application/ housekeeping/TBM/PPE
3
3
9
-
3
3
9
Supervisor/ Foreman
Hand hit by side formwork
Physical injury
proper arrangement of side formwork and provision of access/ housekeeping / /PPE
2
2
2
-
1
2
2
Supervisor/ Foreman
removal / bending of nails and rebars / Illumination/ housekeeping/TBM/PPE
2
1
2
-
2
1
2
Supervisor/ Foreman
Proper housekeeping/stacking, provision of adequate access/ TBM/PPE
3
1
3
-
3
1
3
Supervisor/ Foreman
Use of proper Ppe - protective gloves
2
2
4
-
2
2
4
Supervisor/ Foreman
1
2
2
-
1
2
2
Supervisor/ Foreman
4
3
12
3
2
6
Supervisor/ Foreman
2
1
2
Supervisor/ Safety Supervisor
Hazard
Step on hazard (protruding nails/rabars) 2
Risk Control Risk Level
1
Work Activity
Risk Evaluation
Rev. No. -
Likelihood
No
Ref. No. HDB/12/2012/R1
Severity
Hazard Identification
Approved by :
Possible Injury/ ill-health
Lower limbs injury
Erection and Tripped over reinforcement/ steel Physical injury fabrication of steel mesh reinforcement/ steel mesh Sharp cutting edges of rebar Minor cuts Caught in between bars
minor fracture / laceration cuts
Worker finger cut by bar bending Physical injury machine Electrical hazards
Injury to person/property
Existing Control Measure
Use of proper Ppe - protective gloves Guarding at all dangerous parts of machine must be provided Proper connection and distribution board shall be provided for tapping of electricity. Ensure that proper earthing is provided for the generator used on site.
Use of proper Ppe - protective gloves Using industrial socket, avoid cable from moisture
4
2
8
Due Date
Remark
Shincon Industrial Pte Ltd Risk Assessment Form Project : HDB CONTRACT
WHSO:
Francis Wong (Safety Officer)
Contractor: Shincon Industrial Pte Ltd Work Activity: Concreting works
RA leader :
Rajmohan Vijay (Safety Supervisor)
Approved by :
RA member 1 :
Shaiful Hamli Bin Moktar(Project Co-ordinator)
Ref. No. HDB/12/2012/R1
RA member 2 :
Balasubramanian Karthikeyan (Site Engineer)
Signature :
Original Assessment date : 15 December 2012
RA member 3 :
Andrew Kiang (Site Supervisor)
Name :
Koh Teck Lee
Last review date
:-
RA member 4 :
Thangavel Thangaraj (Foreman)
Designation :
Project Manager
Next review date
: 15 June 2013
RA member 5 :
Date :
15/12/2012
3
2
6
Use of qualified worker.
2
1
Equipment without guard must be kept in store Inspection on opening mechanism of concrete bucket before concreting.
3
Walking on steel reinforcement (tripping hazard) Hit against objects
Designated access/ housekeeping/Toolbox meeting /PPE Use trained workers / TBM / PPE
Truck topping
Falling/physical injury bodily injury
Existing Control Measure
Risk Level
Ground condition check by engineer
Possible Injury/ ill-health
Likelihood
Concreting works
Damage to property/ injury to people Poor coordination between truck Damage to property/ operator, signalman and injury to people workers. Hazard arising from unguarded Iinjury to people pull start disc. Accidental opening of concrete Injury to people bucket.
Hazard
Severity
4
Preparation works before concreting
Risk Level
3
Work Activity
Risk Control Likelihood
No
Risk Evaluation Severity
Hazard Identification
Rev. No. -
3
2
6
2
2
1
2
1
3
3
1
3
3
3
9
3
3
9
3
3
9
3
3
9
Supervisor
1
3
3
1
3
3
Foreman
Additional Risk Control
Sinnalman to communiate with driver
Close supervision by experience supervisor/ Provide shoring system. Provide walking platform on the reinforcement
Implementati on Person
Due Date
Site Supervisor
-
Site Supervisor Site Supervisor
-
-
-
Remark
Shincon Industrial Pte Ltd Risk Assessment Form Project : HDB CONTRACT
WHSO:
Francis Wong (Safety Officer)
Contractor: Shincon Industrial Pte Ltd Work Activity:Pre-cast Component Handling
RA leader :
Rajmohan Vijay (Safety Supervisor)
Approved by :
RA member 1 :
Shaiful Hamli Bin Moktar(Project Co-ordinator)
Ref. No. HDB/12/2012/R1
RA member 2 :
Balasubramanian Karthikeyan (Site Engineer)
Signature :
Original Assessment date : 15 December 2012
RA member 3 :
Andrew Kiang (Site Supervisor)
Name :
Koh Teck Lee
Last review date
:-
RA member 4 :
G Subani (Lifting Supervisor)
Designation :
Project Manager
Next review date
: 15 June 2013
RA member 5 :
Thangavel Thangaraj (Foreman)
Date :
15/12/2012
Human body injury/ill-health
Struck by dropped pre-cast components due to defective lifting gears
Human body injury/ill-health
Daily operator visual inspection on crane components - hoistrope, hook block, slings & lifting gears & operational checks on limit switches and various brakes.
5
3
15
Periodic examination of the cranes lifting gears by authorised examiners
5
3
15
5
3
15
4
2
8
Struck by dropped pre-cast Human body injury/ill-health components due to failure of lifting lug of the pre-cast components Entanglement of slings with other Human body injury/ill-health materials
Implement control over the lifting lug design & its fabrication
Struck by dropped pre-cast components due to overloading
Provide details of the pre-cast components in terms of weight, lifting locations, rigging method and concrete strength
Human body injury/ill-health
Trapped between suspended pre- Human body injury/ Damage to cast and other fixed structure or pre-cast elements other material
Adequate supervision by lifting supervisor & implement safe lifting procedures.
Adequate supervision by lifting supervisor & implement safe lifting procedures.
4
3
12
4
3
12
Additional Risk Control
Conduct risk assessment to mitigate risks associated with the lifting operation
Plan for the lifting operations & document the plan and procedure Select suitable equipment which is properly maintained & in good working condition Clarify the roles/responsibility of personnel involved in the lifting operation Provide suitable training and select the appropriate and experienced lifting team
-
Risk Level
Pre-cast Component Struck by dropped pre-cast Handling components due to failure of Lifting machines
Existing Control Measure
Likelihood
Possible Injury/ ill-health
Risk Level
Hazard
Severity
5
Work Activity
Risk Control Likelihood
No
Risk Evaluation Severity
Hazard Identification
Rev. No. -
Implementation Person
5
1
5
Crane Operator/ Lifting Supervisor
5
1
5
Crane Operator/ Lifting Supervisor
5
1
5
Crane Operator/ Lifting Supervisor
4
1
4
Crane Operator/ Lifting Supervisor
4
1
4
Crane Operator/ Lifting Supervisor
4
1
4
Crane Operator/ Lifting Supervisor
Due Date
Remark
Shincon Industrial Pte Ltd Risk Assessment Form Project : HDB CONTRACT
WHSO:
Francis Wong (Safety Officer)
Contractor: Shincon Industrial Pte Ltd Work Activity: Storage of Pre-cast Components
RA leader :
Rajmohan Vijay (Safety Supervisor)
Approved by :
RA member 1 :
Shaiful Hamli Bin Moktar(Project Co-ordinator)
Ref. No. HDB/12/2012/R1
RA member 2 :
Balasubramanian Karthikeyan (Site Engineer)
Signature :
Original Assessment date : 15 December 2012
RA member 3 :
Andrew Kiang (Site Supervisor)
Name :
Koh Teck Lee
Last review date
:-
RA member 4 :
G Subani (Lifting Supervisor)
Designation :
Project Manager
Next review date
: 15 June 2013
RA member 5 :
Thangavel Thangaraj (Foreman)
Date :
15/12/2012
Overloading due to inadequate design of supporting structures for supporting racks/frames
Damage to pre-cast elements
Damage to pre-cast elements
Storage area should be large enough for pre-cast components to be stored properly with adequate room for lifting equipment and for manoeuvring trucks, cranes and other relevant vehicles. Pre-cast components should not be stored directly on the ground. Generally, two discrete support points should be provided. Timber supports raised above the ground or dedicated racking systems should be used in all cases
Additional Risk Control
2
2
4
-
2
2
4
2
2
4
The area should be reasonably level and hard surfaced with adequate drainage to ensure that a safe workplace can be maintained. Pre-cast components should be stored in such a manner that each component supports only its own weight without any load being imposed by other components.
Risk Level
Unstable pre-cast panels due to inadequate supports
Damage to pre-cast elements
Existing Control Measure
Likelihood
Lack of storage planning
Possible Injury/ ill-health
Severity
Storage of Pre-cast Components
Hazard
Risk Level
6
Work Activity
Risk Control Likelihood
No
Risk Evaluation Severity
Hazard Identification
Rev. No. -
Implementation Person
2
1
2
Supervisor
2
1
2
Supervisor
2
1
2
Supervisor
Due Date
Remark
Shincon Industrial Pte Ltd Risk Assessment Form Project : HDB CONTRACT
WHSO:
Francis Wong (Safety Officer)
Contractor: Shincon Industrial Pte Ltd Work Activity: Unloading materials
RA leader :
Rajmohan Vijay (Safety Supervisor)
Approved by :
RA member 1 :
Shaiful Hamli Bin Moktar(Project Co-ordinator)
Ref. No. HDB/12/2012/R1
RA member 2 :
Balasubramanian Karthikeyan (Site Engineer)
Signature :
Original Assessment date : 15 December 2012
RA member 3 :
Andrew Kiang (Site Supervisor)
Name :
Koh Teck Lee
Last review date
:-
RA member 4 :
G Subani (Lifting Supervisor)
Designation :
Project Manager
Next review date
: 15 June 2013
RA member 5 :
Thangavel Thangaraj (Foreman)
Date :
15/12/2012
1
2
2
Caught in-between materials
Physical injury
Wear Proper PPE/ Protective gloves
2
2
4
Inproper manual lifting
Damage to property/ injury to people Injury to people
Use of proper PPE - protective gloves
3
1
3
Drivers must brief to reduce speed and activate filter signal early to inform behind vehicles about his intention.
3
2
6
Drivers must be briefed to give way to fast moving traffic and also to ensure it’s the right time for him to drive on.
3
2
6
Vehicle using site Road accident while entering access, transporting site during loading & unloading of material in and out of excavator from trailer of site. Road accident while moving out Injury to people / of site Damage to property
Existing Control Measure
Risk Level
Wear Proper PPE
Unloading materials Contact with sharp/ protruding parts
Possible Injury/ ill-health
Likelihood
Physical injury
Hazard
Severity
8
Risk Level
7
Work Activity
Risk Control Likelihood
No
Risk Evaluation Severity
Hazard Identification
Rev. No. -
1
2
2
Site Supervisor
-
2
2
4
Site Supervisor
-
3
1
3
-
Signalman to communiate with driver
3
2
6
Site Supervisor Site Supervisor/ Signalman
Signalman to communiate with driver
3
2
6
Site Supervisor/ Signalman
-
Additional Risk Control
Signalman to communiate with driver & use of tagline for bulky items
Implementati on Person
Due Date
-
Remark
Shincon Industrial Pte Ltd Risk Assessment Form Project : HDB CONTRACT
WHSO:
Francis Wong (Safety Officer)
Contractor: Shincon Industrial Pte Ltd Work Activity: Liifting by Lorry crane/ Mobile crane
RA leader :
Rajmohan Vijay (Safety Supervisor)
Approved by :
RA member 1 :
Shaiful Hamli Bin Moktar(Project Co-ordinator)
Ref. No. HDB/12/2012/R1
RA member 2 :
Balasubramanian Karthikeyan (Site Engineer)
Signature :
Original Assessment date : 15 December 2012
RA member 3 :
Andrew Kiang (Site Supervisor)
Name :
Koh Teck Lee
Last review date
:-
RA member 4 :
G Subani (Lifting Supervisor)
Designation :
Project Manager
Next review date
: 15 June 2013
RA member 5 :
Thangavel Thangaraj (Foreman)
Date :
15/12/2012
Ground Guides are deployed to guide vehicles in efficient manner with congested road Adhere vehicle travelling speed limit of 15 km/hr within site
4
Damage to , pre-cast culvert, drains, human body and property
Qualified lifting supervisor, rigger and signaller for lifting operation must be certified by MOM and underwent proper lifting training Crane is parked at designated location in accordance to the site requirement Ground condition must be even surface and rigid. All outriggers are fully extended and rested fully on steel plates
4
Crane is levelled after outrigger extension Crane is inspected by lifting supervisor prior to lifting Hoisting load is within SWL of the crane.
Risk Level
Toppling of crane
Damage to pre-cast culvert, drains, human body and property
Existing Control Measure
Likelihood
10 Setting up of lorry crane
Collision of Lorry Crane
Possible Injury/ ill-health
Severity
Lorry / Mobile Crane
Hazard
Risk Level
9
Work Activity
Risk Control Likelihood
No
Risk Evaluation Severity
Hazard Identification
Rev. No. -
3
12 Ground guide to warm vehicles or passersby of incoming lorry crane
4
3
12
12 All lifting related certificates (LM, LG & lifting personel) are inorder and within validity period
4
3
Additional Risk Control
Implementation Person
Ground Guide
Due Date
-
Crane Operator 3
12 Crane Operator Lifting Supervisor
-
Remark
Shincon Industrial Pte Ltd Risk Assessment Form Project : HDB CONTRACT
WHSO:
Francis Wong (Safety Officer)
Contractor: Shincon Industrial Pte Ltd Work Activity: Liifting by Lorry crane/ Mobile crane
RA leader :
Rajmohan Vijay (Safety Supervisor)
Approved by :
RA member 1 :
Shaiful Hamli Bin Moktar(Project Co-ordinator)
Ref. No. HDB/12/2012/R1
RA member 2 :
Balasubramanian Karthikeyan (Site Engineer)
Signature :
Original Assessment date : 15 December 2012
RA member 3 :
Andrew Kiang (Supervisor)
Name :
Koh Teck Lee
Last review date
:-
RA member 4 :
G Subani (Lifting Supervisor)
Designation :
Project Manager
Next review date
: 15 June 2013
RA member 5 :
Thangavel Thangaraj (Foreman)
Date :
15/12/2012
Hazard Identification 11 Lifting of Toppling of load commodities via lorry crane
Failure of lifting gears
Tripping over objects
Severity scoring
1-2 3-4 5-9
Very Low Risk Low Risk Medium Risk
Damage to pre-cast culvert, drains, human body and property
Damage to pre-cast culvert, drains, and property
Human body injury
Risk Evaluation Load is rigged by qualified rigger only
3
3
9
Tag line with sufficient length (at least 6m) is tied on the load to better control during lifting All lifting signals to be instructed strictly by signaller during entire lifting operation No person are allowed to stand near or below suspended load All lifting crew and crane operator to stay within sight at all times during entire lifting operation All loads shall be predetermined to ascertain lifting capability of crane No person are allowed to stand below suspended load Safety latch of lifting block is in good condition and operational requirement Non operational personnel are to stay away from lifting zone at all time during entire lifting Area is clear from obstruction prior the lifting operation Proper and sufficient passage way in case of emergecy
Likelihood scoring
5
2
2
3
Lifting supervisors is to overseees the lifting operation and empower to stop work shall there by any unsafe circumstances such as climate change
3
10 All lifting gears shall be physically checked prior the lifting operation to ensure consistency with valid certificates submitted and existing physical condition
5
6
2
Maintain proper housekeeping through the entire lifting operation
3
2
Risk Control 9 Lifting Supervisor
10
Lifting Supervisor
Rev. No. -
-
-
Crane Operator
3
6
Recommended 5x5 Risk Matrix with numeric ratings
10 - 16 High Risk 17 - 25 Very High Risk Note: The "Very Hight Risk" and "High Risk" must have additional control to bring below the "Medium Risk".
5x5 Risk Matrix with numeric ratings Likelihood Rare (1)
Remote (2)
Occasional (3)
Frequent (4)
Almost Certain (5)
Catastrophic (5)
5
10
15
20
25
Major (4)
4
8
12
16
20
Moderate (3)
3
6
9
12
15
Minor (2)
2
4
6
8
10
Negligible (1)
1
2
3
4
5
Severity
Low Risk
(1 - 3)
- Acceptable
Medium Risk
(4 - 14)
- Tolerable
High Risk
(15 - 25)
- Not acceptable
Low Risk
Acceptable
Medium Risk
Acceptable
No additional risk control measures may be needed. Frequent review and monitoring of hazards are required to ensure that the risk level assigned is accurate and does not increase over time. No additional risk control measures may be needed. Frequent review and monitoring of hazards are required to ensure that the risk level assigned is accurate and does not increase over time.