Shincon Industrial Pte Ltd Risk Assessment Form Project : HDB CONTRACT

WHSO:

Francis Wong (Safety Officer)

Contractor: Shincon Industrial Pte Ltd Work Activity: Preparation of side formwork and steel work.

RA leader :

Rajmohan Vijay (Safety Supervisor)

RA member 1 :

Shaiful Hamli Bin Moktar(Project Co-ordinator)

RA member 2 :

Balasubramanian Karthikeyan (Site Engineer)

Signature :

Original Assessment date : 15 December 2012

RA member 3 :

Andrew Kiang (Site Supervisor)

Name :

Koh Teck Lee

Last review date

:-

RA member 4 :

Thangavel Thangaraj (Foreman)

Designation :

Project Manager

Next review date

: 15 June 2013

RA member 5 :

Date :

15/12/2012

Additional Risk Control

Severity

Likelihood

Risk Level

Preparation of side formwork

Implementation Person

Slipped and fall on the Pallet table

Bodily injury/ Fracture

Control of Oil application/ housekeeping/TBM/PPE

3

3

9

-

3

3

9

Supervisor/ Foreman

Hand hit by side formwork

Physical injury

proper arrangement of side formwork and provision of access/ housekeeping / /PPE

2

2

2

-

1

2

2

Supervisor/ Foreman

removal / bending of nails and rebars / Illumination/ housekeeping/TBM/PPE

2

1

2

-

2

1

2

Supervisor/ Foreman

Proper housekeeping/stacking, provision of adequate access/ TBM/PPE

3

1

3

-

3

1

3

Supervisor/ Foreman

Use of proper Ppe - protective gloves

2

2

4

-

2

2

4

Supervisor/ Foreman

1

2

2

-

1

2

2

Supervisor/ Foreman

4

3

12

3

2

6

Supervisor/ Foreman

2

1

2

Supervisor/ Safety Supervisor

Hazard

Step on hazard (protruding nails/rabars) 2

Risk Control Risk Level

1

Work Activity

Risk Evaluation

Rev. No. -

Likelihood

No

Ref. No. HDB/12/2012/R1

Severity

Hazard Identification

Approved by :

Possible Injury/ ill-health

Lower limbs injury

Erection and Tripped over reinforcement/ steel Physical injury fabrication of steel mesh reinforcement/ steel mesh Sharp cutting edges of rebar Minor cuts Caught in between bars

minor fracture / laceration cuts

Worker finger cut by bar bending Physical injury machine Electrical hazards

Injury to person/property

Existing Control Measure

Use of proper Ppe - protective gloves Guarding at all dangerous parts of machine must be provided Proper connection and distribution board shall be provided for tapping of electricity. Ensure that proper earthing is provided for the generator used on site.

Use of proper Ppe - protective gloves Using industrial socket, avoid cable from moisture

4

2

8

Due Date

Remark

Shincon Industrial Pte Ltd Risk Assessment Form Project : HDB CONTRACT

WHSO:

Francis Wong (Safety Officer)

Contractor: Shincon Industrial Pte Ltd Work Activity: Concreting works

RA leader :

Rajmohan Vijay (Safety Supervisor)

Approved by :

RA member 1 :

Shaiful Hamli Bin Moktar(Project Co-ordinator)

Ref. No. HDB/12/2012/R1

RA member 2 :

Balasubramanian Karthikeyan (Site Engineer)

Signature :

Original Assessment date : 15 December 2012

RA member 3 :

Andrew Kiang (Site Supervisor)

Name :

Koh Teck Lee

Last review date

:-

RA member 4 :

Thangavel Thangaraj (Foreman)

Designation :

Project Manager

Next review date

: 15 June 2013

RA member 5 :

Date :

15/12/2012

3

2

6

Use of qualified worker.

2

1

Equipment without guard must be kept in store Inspection on opening mechanism of concrete bucket before concreting.

3

Walking on steel reinforcement (tripping hazard) Hit against objects

Designated access/ housekeeping/Toolbox meeting /PPE Use trained workers / TBM / PPE

Truck topping

Falling/physical injury bodily injury

Existing Control Measure

Risk Level

Ground condition check by engineer

Possible Injury/ ill-health

Likelihood

Concreting works

Damage to property/ injury to people Poor coordination between truck Damage to property/ operator, signalman and injury to people workers. Hazard arising from unguarded Iinjury to people pull start disc. Accidental opening of concrete Injury to people bucket.

Hazard

Severity

4

Preparation works before concreting

Risk Level

3

Work Activity

Risk Control Likelihood

No

Risk Evaluation Severity

Hazard Identification

Rev. No. -

3

2

6

2

2

1

2

1

3

3

1

3

3

3

9

3

3

9

3

3

9

3

3

9

Supervisor

1

3

3

1

3

3

Foreman

Additional Risk Control

Sinnalman to communiate with driver

Close supervision by experience supervisor/ Provide shoring system. Provide walking platform on the reinforcement

Implementati on Person

Due Date

Site Supervisor

-

Site Supervisor Site Supervisor

-

-

-

Remark

Shincon Industrial Pte Ltd Risk Assessment Form Project : HDB CONTRACT

WHSO:

Francis Wong (Safety Officer)

Contractor: Shincon Industrial Pte Ltd Work Activity:Pre-cast Component Handling

RA leader :

Rajmohan Vijay (Safety Supervisor)

Approved by :

RA member 1 :

Shaiful Hamli Bin Moktar(Project Co-ordinator)

Ref. No. HDB/12/2012/R1

RA member 2 :

Balasubramanian Karthikeyan (Site Engineer)

Signature :

Original Assessment date : 15 December 2012

RA member 3 :

Andrew Kiang (Site Supervisor)

Name :

Koh Teck Lee

Last review date

:-

RA member 4 :

G Subani (Lifting Supervisor)

Designation :

Project Manager

Next review date

: 15 June 2013

RA member 5 :

Thangavel Thangaraj (Foreman)

Date :

15/12/2012

Human body injury/ill-health

Struck by dropped pre-cast components due to defective lifting gears

Human body injury/ill-health

Daily operator visual inspection on crane components - hoistrope, hook block, slings & lifting gears & operational checks on limit switches and various brakes.

5

3

15

Periodic examination of the cranes lifting gears by authorised examiners

5

3

15

5

3

15

4

2

8

Struck by dropped pre-cast Human body injury/ill-health components due to failure of lifting lug of the pre-cast components Entanglement of slings with other Human body injury/ill-health materials

Implement control over the lifting lug design & its fabrication

Struck by dropped pre-cast components due to overloading

Provide details of the pre-cast components in terms of weight, lifting locations, rigging method and concrete strength

Human body injury/ill-health

Trapped between suspended pre- Human body injury/ Damage to cast and other fixed structure or pre-cast elements other material

Adequate supervision by lifting supervisor & implement safe lifting procedures.

Adequate supervision by lifting supervisor & implement safe lifting procedures.

4

3

12

4

3

12

Additional Risk Control

Conduct risk assessment to mitigate risks associated with the lifting operation

Plan for the lifting operations & document the plan and procedure Select suitable equipment which is properly maintained & in good working condition Clarify the roles/responsibility of personnel involved in the lifting operation Provide suitable training and select the appropriate and experienced lifting team

-

Risk Level

Pre-cast Component Struck by dropped pre-cast Handling components due to failure of Lifting machines

Existing Control Measure

Likelihood

Possible Injury/ ill-health

Risk Level

Hazard

Severity

5

Work Activity

Risk Control Likelihood

No

Risk Evaluation Severity

Hazard Identification

Rev. No. -

Implementation Person

5

1

5

Crane Operator/ Lifting Supervisor

5

1

5

Crane Operator/ Lifting Supervisor

5

1

5

Crane Operator/ Lifting Supervisor

4

1

4

Crane Operator/ Lifting Supervisor

4

1

4

Crane Operator/ Lifting Supervisor

4

1

4

Crane Operator/ Lifting Supervisor

Due Date

Remark

Shincon Industrial Pte Ltd Risk Assessment Form Project : HDB CONTRACT

WHSO:

Francis Wong (Safety Officer)

Contractor: Shincon Industrial Pte Ltd Work Activity: Storage of Pre-cast Components

RA leader :

Rajmohan Vijay (Safety Supervisor)

Approved by :

RA member 1 :

Shaiful Hamli Bin Moktar(Project Co-ordinator)

Ref. No. HDB/12/2012/R1

RA member 2 :

Balasubramanian Karthikeyan (Site Engineer)

Signature :

Original Assessment date : 15 December 2012

RA member 3 :

Andrew Kiang (Site Supervisor)

Name :

Koh Teck Lee

Last review date

:-

RA member 4 :

G Subani (Lifting Supervisor)

Designation :

Project Manager

Next review date

: 15 June 2013

RA member 5 :

Thangavel Thangaraj (Foreman)

Date :

15/12/2012

Overloading due to inadequate design of supporting structures for supporting racks/frames

Damage to pre-cast elements

Damage to pre-cast elements

Storage area should be large enough for pre-cast components to be stored properly with adequate room for lifting equipment and for manoeuvring trucks, cranes and other relevant vehicles. Pre-cast components should not be stored directly on the ground. Generally, two discrete support points should be provided. Timber supports raised above the ground or dedicated racking systems should be used in all cases

Additional Risk Control

2

2

4

-

2

2

4

2

2

4

The area should be reasonably level and hard surfaced with adequate drainage to ensure that a safe workplace can be maintained. Pre-cast components should be stored in such a manner that each component supports only its own weight without any load being imposed by other components.

Risk Level

Unstable pre-cast panels due to inadequate supports

Damage to pre-cast elements

Existing Control Measure

Likelihood

Lack of storage planning

Possible Injury/ ill-health

Severity

Storage of Pre-cast Components

Hazard

Risk Level

6

Work Activity

Risk Control Likelihood

No

Risk Evaluation Severity

Hazard Identification

Rev. No. -

Implementation Person

2

1

2

Supervisor

2

1

2

Supervisor

2

1

2

Supervisor

Due Date

Remark

Shincon Industrial Pte Ltd Risk Assessment Form Project : HDB CONTRACT

WHSO:

Francis Wong (Safety Officer)

Contractor: Shincon Industrial Pte Ltd Work Activity: Unloading materials

RA leader :

Rajmohan Vijay (Safety Supervisor)

Approved by :

RA member 1 :

Shaiful Hamli Bin Moktar(Project Co-ordinator)

Ref. No. HDB/12/2012/R1

RA member 2 :

Balasubramanian Karthikeyan (Site Engineer)

Signature :

Original Assessment date : 15 December 2012

RA member 3 :

Andrew Kiang (Site Supervisor)

Name :

Koh Teck Lee

Last review date

:-

RA member 4 :

G Subani (Lifting Supervisor)

Designation :

Project Manager

Next review date

: 15 June 2013

RA member 5 :

Thangavel Thangaraj (Foreman)

Date :

15/12/2012

1

2

2

Caught in-between materials

Physical injury

Wear Proper PPE/ Protective gloves

2

2

4

Inproper manual lifting

Damage to property/ injury to people Injury to people

Use of proper PPE - protective gloves

3

1

3

Drivers must brief to reduce speed and activate filter signal early to inform behind vehicles about his intention.

3

2

6

Drivers must be briefed to give way to fast moving traffic and also to ensure it’s the right time for him to drive on.

3

2

6

Vehicle using site Road accident while entering access, transporting site during loading & unloading of material in and out of excavator from trailer of site. Road accident while moving out Injury to people / of site Damage to property

Existing Control Measure

Risk Level

Wear Proper PPE

Unloading materials Contact with sharp/ protruding parts

Possible Injury/ ill-health

Likelihood

Physical injury

Hazard

Severity

8

Risk Level

7

Work Activity

Risk Control Likelihood

No

Risk Evaluation Severity

Hazard Identification

Rev. No. -

1

2

2

Site Supervisor

-

2

2

4

Site Supervisor

-

3

1

3

-

Signalman to communiate with driver

3

2

6

Site Supervisor Site Supervisor/ Signalman

Signalman to communiate with driver

3

2

6

Site Supervisor/ Signalman

-

Additional Risk Control

Signalman to communiate with driver & use of tagline for bulky items

Implementati on Person

Due Date

-

Remark

Shincon Industrial Pte Ltd Risk Assessment Form Project : HDB CONTRACT

WHSO:

Francis Wong (Safety Officer)

Contractor: Shincon Industrial Pte Ltd Work Activity: Liifting by Lorry crane/ Mobile crane

RA leader :

Rajmohan Vijay (Safety Supervisor)

Approved by :

RA member 1 :

Shaiful Hamli Bin Moktar(Project Co-ordinator)

Ref. No. HDB/12/2012/R1

RA member 2 :

Balasubramanian Karthikeyan (Site Engineer)

Signature :

Original Assessment date : 15 December 2012

RA member 3 :

Andrew Kiang (Site Supervisor)

Name :

Koh Teck Lee

Last review date

:-

RA member 4 :

G Subani (Lifting Supervisor)

Designation :

Project Manager

Next review date

: 15 June 2013

RA member 5 :

Thangavel Thangaraj (Foreman)

Date :

15/12/2012

Ground Guides are deployed to guide vehicles in efficient manner with congested road Adhere vehicle travelling speed limit of 15 km/hr within site

4

Damage to , pre-cast culvert, drains, human body and property

Qualified lifting supervisor, rigger and signaller for lifting operation must be certified by MOM and underwent proper lifting training Crane is parked at designated location in accordance to the site requirement Ground condition must be even surface and rigid. All outriggers are fully extended and rested fully on steel plates

4

Crane is levelled after outrigger extension Crane is inspected by lifting supervisor prior to lifting Hoisting load is within SWL of the crane.

Risk Level

Toppling of crane

Damage to pre-cast culvert, drains, human body and property

Existing Control Measure

Likelihood

10 Setting up of lorry crane

Collision of Lorry Crane

Possible Injury/ ill-health

Severity

Lorry / Mobile Crane

Hazard

Risk Level

9

Work Activity

Risk Control Likelihood

No

Risk Evaluation Severity

Hazard Identification

Rev. No. -

3

12 Ground guide to warm vehicles or passersby of incoming lorry crane

4

3

12

12 All lifting related certificates (LM, LG & lifting personel) are inorder and within validity period

4

3

Additional Risk Control

Implementation Person

Ground Guide

Due Date

-

Crane Operator 3

12 Crane Operator Lifting Supervisor

-

Remark

Shincon Industrial Pte Ltd Risk Assessment Form Project : HDB CONTRACT

WHSO:

Francis Wong (Safety Officer)

Contractor: Shincon Industrial Pte Ltd Work Activity: Liifting by Lorry crane/ Mobile crane

RA leader :

Rajmohan Vijay (Safety Supervisor)

Approved by :

RA member 1 :

Shaiful Hamli Bin Moktar(Project Co-ordinator)

Ref. No. HDB/12/2012/R1

RA member 2 :

Balasubramanian Karthikeyan (Site Engineer)

Signature :

Original Assessment date : 15 December 2012

RA member 3 :

Andrew Kiang (Supervisor)

Name :

Koh Teck Lee

Last review date

:-

RA member 4 :

G Subani (Lifting Supervisor)

Designation :

Project Manager

Next review date

: 15 June 2013

RA member 5 :

Thangavel Thangaraj (Foreman)

Date :

15/12/2012

Hazard Identification 11 Lifting of Toppling of load commodities via lorry crane

Failure of lifting gears

Tripping over objects

Severity scoring

1-2 3-4 5-9

Very Low Risk Low Risk Medium Risk

Damage to pre-cast culvert, drains, human body and property

Damage to pre-cast culvert, drains, and property

Human body injury

Risk Evaluation Load is rigged by qualified rigger only

3

3

9

Tag line with sufficient length (at least 6m) is tied on the load to better control during lifting All lifting signals to be instructed strictly by signaller during entire lifting operation No person are allowed to stand near or below suspended load All lifting crew and crane operator to stay within sight at all times during entire lifting operation All loads shall be predetermined to ascertain lifting capability of crane No person are allowed to stand below suspended load Safety latch of lifting block is in good condition and operational requirement Non operational personnel are to stay away from lifting zone at all time during entire lifting Area is clear from obstruction prior the lifting operation Proper and sufficient passage way in case of emergecy

Likelihood scoring

5

2

2

3

Lifting supervisors is to overseees the lifting operation and empower to stop work shall there by any unsafe circumstances such as climate change

3

10 All lifting gears shall be physically checked prior the lifting operation to ensure consistency with valid certificates submitted and existing physical condition

5

6

2

Maintain proper housekeeping through the entire lifting operation

3

2

Risk Control 9 Lifting Supervisor

10

Lifting Supervisor

Rev. No. -

-

-

Crane Operator

3

6

Recommended 5x5 Risk Matrix with numeric ratings

10 - 16 High Risk 17 - 25 Very High Risk Note: The "Very Hight Risk" and "High Risk" must have additional control to bring below the "Medium Risk".

5x5 Risk Matrix with numeric ratings Likelihood Rare (1)

Remote (2)

Occasional (3)

Frequent (4)

Almost Certain (5)

Catastrophic (5)

5

10

15

20

25

Major (4)

4

8

12

16

20

Moderate (3)

3

6

9

12

15

Minor (2)

2

4

6

8

10

Negligible (1)

1

2

3

4

5

Severity

Low Risk

(1 - 3)

- Acceptable

Medium Risk

(4 - 14)

- Tolerable

High Risk

(15 - 25)

- Not acceptable

Low Risk

Acceptable

Medium Risk

Acceptable

No additional risk control measures may be needed. Frequent review and monitoring of hazards are required to ensure that the risk level assigned is accurate and does not increase over time. No additional risk control measures may be needed. Frequent review and monitoring of hazards are required to ensure that the risk level assigned is accurate and does not increase over time.