MATERIAL CONTROL PROCEDURE
Revision: 0.1 Document Type : PRC
System/Subsystem : N/A
Discipline: QUA
Status : IFC
Date : 12 – 08 - 2021
Originator Document No : N/A
Page 1 of 23
PT PERTAMINA HULU MAHAKAM BEKAPAI 3 SURFACE FACILITIES MODIFICATION AND DOGLEG INSTALLATION (EPCIC)
MATERIAL CONTROL PROCEDURE
CLASS : 1
0.1
12-Aug-2021
IFC
Issued for Comment
WHY
IP / AU
SG
Rev
Date
Status
Revision memo
Issued
Checked
Approved
COMPANY
This document is the property of PT Pertamina Hulu Mahakam and shall not be disclosed to third parties or reproduced without permission of the COMPANY. Electronic Filename: ID-BKP-SOME-2009-509007_rev0.1.pdf
Contract : 4500010835
Document Number ID-BKP-SOME-2009- 509007
MATERIAL CONTROL PROCEDURE
Revision: 0.1 Document Type : PRC
System/Subsystem : N/A
Discipline: QUA
Status : IFC
Date : 12 – 08 - 2021
Originator Document No : N/A
Page 2 of 23
TABULATION OF REVIEW PAGES REVISION
REVISION
SHEET
SHEET 0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
0.1
1
X
31
2
X
32
3
X
33
4
X
34
5
X
35
6
X
36
7
X
37
8
X
38
9
X
39
10
X
40
11
X
41
12
X
42
13
X
43
14
X
44
15
X
45
16
X
46
17
X
47
18
X
48
19
X
49
20
X
50
21
X
51
22
X
52
23
X
53
24
54
25
55
26
56
27
57
28
58
29
59
30
60
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
This document is the property of PT Pertamina Hulu Mahakam and shall not be disclosed to third parties or reproduced without permission of the COMPANY. Electronic Filename: ID-BKP-SOME-2009-509007_rev0.1.pdf
Contract : 4500010835
Document Number
MATERIAL CONTROL PROCEDURE
ID-BKP-SOME-2009- 509007 Revision: 0.1
Document Type : PRC
System/Subsystem : N/A
Discipline: QUA
Originator Document No : N/A
Status : IFC
Date : 12 – 08 - 2021 Page 3 of 23
COMMENT TABULATION No
PHM COMMENT
CONTRACTOR RESPONSE
This document is the property of PT Pertamina Hulu Mahakam and shall not be disclosed to third parties or reproduced without permission of the COMPANY. Electronic Filename: ID-BKP-SOME-2009-509007_rev0.1.pdf
Contract : 4500010835
Document Number
MATERIAL CONTROL PROCEDURE
ID-BKP-SOME-2009- 509007 Revision: 0.1
Document Type : PRC
System/Subsystem : N/A
Discipline: QUA
Originator Document No : N/A
Status : IFC
Date : 12 – 08 - 2021 Page 4 of 23
TABLE OF CONTENTS 1.
INTRODUCTION............................................................................................................................. 5 1.1 Plant Description ................................................................................................................... 5 1.2 Project General Description and Purpose .......................................................................... 5
2.
DOCUMENT SCOPE ...................................................................................................................... 7
3.
REFERENCE DOCUMENT ............................................................................................................ 7 3.1 Company Specification......................................................................................................... 7 3.2 International Code and Standard ......................................................................................... 7 3.3 COMPANY Supplied Document ........................................................................................... 7 3.4 Project Document.................................................................................................................. 8
4.
ABBREVIATIONS .......................................................................................................................... 8
5.
RESPONSIBILTIES ........................................................................................................................ 8 a. b. c. d. e. f.
Fabrication Coordinator ...................................................................................................... 8 QA/QC Coordinator .............................................................................................................. 8 QC Inspector ......................................................................................................................... 8 Material Man .......................................................................................................................... 8 Warehouse Supervisor ........................................................................................................ 8 Fabrication Supervisor ........................................................................................................ 9
6.
MATERIAL RECEIVING ................................................................................................................. 9
7.
STORAGE MATERIAL MANAGEMENT ........................................................................................ 9
8.
MATERIAL IDENTIFICATION ...................................................................................................... 10
9.
MATERIAL INSPECTION............................................................................................................. 11
10.
MATERIAL SUBSTITUTION ........................................................................................................ 11
11.
TRANSFERRING OF MATERIAL HEAT NUMBER .................................................................... 11 11.1 Marking Identifications ...................................................................................................... 11 11.2 Marking Verification ........................................................................................................... 11
12.
MATERIAL TRACEABILITY ........................................................................................................ 12
13.
APPENDICES ............................................................................................................................... 13 Appendix – 1 : Material Receiving Flowchart ........................................................................ 14 Appendix – 2 : Material Receiving Inspection Report (MRIR) .............................................. 15 Appendix – 3 : Material Verification Report (MVR) ................................................................ 16 Appendix – 4 : Over, Shortage and Damage Report (OSDR) ............................................... 17 Appendix – 5 : Non-Conformance Report (NCR) ................................................................... 18 Appendix – 6 : Material Traceability Form ............................................................................. 19 Appendix – 7 : Material Subtitution Record Form ................................................................. 20 Appendix – 8 : Surplus Material Report Form ....................................................................... 21 Appendix – 9 : Waste Material Report .................................................................................... 22 Appendix – 10 : Material issue slip............................................................................................ 23
This document is the property of PT Pertamina Hulu Mahakam and shall not be disclosed to third parties or reproduced without permission of the COMPANY. Electronic Filename: ID-BKP-SOME-2009-509007_rev0.1.pdf
Contract : 4500010835
Document Number
MATERIAL CONTROL PROCEDURE
ID-BKP-SOME-2009- 509007 Revision: 0.1
Document Type : PRC
System/Subsystem : N/A
Discipline: QUA
Originator Document No : N/A
1.
INTRODUCTION
1.1
Plant Description
Status : IFC
Date : 12 – 08 - 2021 Page 5 of 23
Bekapai is a COMPANY’s oil field located at offshore area in the Mahakam delta (East Kalimantan) with water depths 30 – 40 meters and located about 40 kilometers south east of the Senipah terminal. COMPANY continues to develop of mature Bekapai offshore oil filed which was discovered in 1972 and start to production in 1974, with current facilities are:
Nine (9) satellite wellhead platforms & inter-platform pipelines;
Production (BP) & LQ platforms;
12” export pipeline to Senipah Terminal (BP1-SNP);
12” export pipeline to Peciko field SWP-K (BA-SWPK).
All effluents from satellite platforms are transported to BP1 and BA in order to have gas-oilwater processing unit (separation, pumping, compression, and oily water treatment). Production fluid from Bekapai field is routed to two (2) locations; multiphase production (mostly gas and oil) is exported to Senipah Terminal (TPA) via 12” BP1-SNP pipeline and gas production is exported to Peciko Field via 12” BA-SWPK Pipeline. The network of BEKAPAI Platforms is shown in figure below.
1.2
Project General Description and Purpose General Description Bekapai development phase 3 covers modifcation of existing production facilities in order to accommodate drilling program of several new wells with potential oil and gas reserve from Bekapai filed. Modification and intervention of the existing offshore production facilities are for:
BE and BH as the main platforms;
BG and BA as host platforms;
Reutilization of existing 6” inter-platform pipelines between BH to BG and BE to BA.
This document is the property of PT Pertamina Hulu Mahakam and shall not be disclosed to third parties or reproduced without permission of the COMPANY. Electronic Filename: ID-BKP-SOME-2009-509007_rev0.1.pdf
Contract : 4500010835
Document Number
MATERIAL CONTROL PROCEDURE
ID-BKP-SOME-2009- 509007 Revision: 0.1
Document Type : PRC
System/Subsystem : N/A
Discipline: QUA
Originator Document No : N/A
Status : IFC
Date : 12 – 08 - 2021 Page 6 of 23
With the current conditions:
BH and BE as satellite wellhead platform, located at eastern of Bekapai field, with minimum production and safety system without pressure relief system, where each platform is hosting three (3) wells: -
One (1) BH well is still in production
-
All BE wells are not in production
BG is still in operating, latest development phase 2B was completed in 2015 with additional production wells
BA is a hub platform, gas export point to Peciko SWP-K without any wells in production
6” pipeline from platform BE to BA are being preserved. The exsiting pipeline is not equipped with dogleg
6” pipeline from platform BH to BG is still in operating
In general, the new equipment under Bekapai 3 is illustrated below:
BE & BH Platform Project Purpose
Increase oil and gas reserves recovery by Reserve: 22.1 BcfGas & 2.8 MbblOil + Condensate
Drilling of 5 new wells from existing BE & BH platforms, with : -
Modification of the existing BE & BH
-
Reuse of existing 6" pipeline from BE to BG (3.6 km) & 6" pipeline from BH to BG (1.9 km)
-
Modification and integration work at the BA, BG & BP platforms
This document is the property of PT Pertamina Hulu Mahakam and shall not be disclosed to third parties or reproduced without permission of the COMPANY. Electronic Filename: ID-BKP-SOME-2009-509007_rev0.1.pdf
Contract : 4500010835
Document Number ID-BKP-SOME-2009- 509007
MATERIAL CONTROL PROCEDURE
Revision: 0.1 Document Type : PRC
System/Subsystem : N/A
Discipline: QUA
Date : 12 – 08 - 2021
Originator Document No : N/A
2.
Status : IFC
Page 7 of 23
DOCUMENT SCOPE Purpose of this document is to describe the required Material Control procedure work to deliver the Bekapai 3 Surface Facilities Modification and Dogleg Installation (EPCIC) project. This is required in order to prove that the work is carried out properly accordingly to the applicable Code / Specification.
3.
REFERENCE DOCUMENT
3.1
Company Specification No
3.2
Document Title
1
MHK-COMP-SPE-EP-PVV-0142 Rev. 0
Valve
2
MHK-COMP-SPE-EP-PVV-0143 Rev. 0
Pipes
3
MHK-COMP-SPE-EP-PVV-0144 Rev. 0
Fittings
4
MHK-COMP-SPE-EP-PVV-0145 Rev. 1
Flanges
5
MHK-COMP-SPE-EP-PVV-0146 Rev. 1
Bolting for Piping
6
MHK-COMP-SPE-EP-PVV-0147 Rev. 0
Gasket for Piping
7
MHK-COMP-SPE-EP-PVV-0171 Rev. 1
Steel Piping Fabrication
8
MHK-COMP-SPE-EP-STR-0201 Rev. 0
Material for Offshore Steel Structures
International Code and Standard No
3.3
Document Number
Document Number
Document Title
1
API 5L Rev. 2012
Specification for Line Pipe
2
ASME II Part A Rev. 2017
Ferrous Material Specification
3
ASME B31.3 Rev. 2016
Process Piping
4
ASME B36.19 Rev. 2004
Stainless Steel Pipe
5
AWS D1.1 Rev. 2015
Structure Welding Code-Steel
COMPANY Supplied Document No 1
Document Number Exhibit A
Document Title Scope of Work; Minimum Contractor Document Requirement Schedule
This document is the property of PT Pertamina Hulu Mahakam and shall not be disclosed to third parties or reproduced without permission of the COMPANY. Electronic Filename: ID-BKP-SOME-2009-509007_rev0.1.pdf
Contract : 4500010835
Document Number ID-BKP-SOME-2009- 509007
MATERIAL CONTROL PROCEDURE
Revision: 0.1 Document Type : PRC
System/Subsystem : N/A
Discipline: QUA
Date : 12 – 08 - 2021
Originator Document No : N/A
3.4
Page 8 of 23
Project Document No
4.
Status : IFC
Document Number
Document Title
1
ID-BKP-SOME-2009-503001
Project Execution Plan
2
ID-BKP-SOME-2009-503005
Project Quality Plan
ABBREVIATIONS MDR MRIR MVR NCR OSDR SWP-G HSE DAN
5.
: Master Document Register : Material Receiving Inspection Report : Material Verification Report : Non-Conformance Report : Over, Shortage and Damage Report : Satellite Wellhead Platform G : Health Safety & Environment : Dispatch Advice Note
RESPONSIBILTIES a.
Fabrication Coordinator Responsible for all fabrication activities in yard including work planning and ensure all the works are in line with HSE manual, project work plan and COMPANY specification. He is also responsible to implement health, safety and environment management plan. Related with Material Management he is Contractor's Focal Point with COMPANY representative Ensure this procedure is implemented. Responsible with company's material delivered/stored at his site.
b.
QA/QC Coordinator Responsible to make sure that the corresponding filing system is clear, accurate and that is no case original traceability report are removed from such file.
c.
QC Inspector Responsible to carry out inspection and verification of all the received material and record it in Material Verification Report (MVR) and welding traceability. Non-Conformity Report (NCR) shall be carried out when receiving material does not comply with project requirement.
d.
Material Man Responsible to monitor and record the outgoing / incoming material and to update the status of material stock.
e.
Warehouse Supervisor Responsible issue the material against the appropriate requisition and maintain material or equipment as per site material controller instruction. - Prepare the location storage in accordance with the specifications, grades, and the size of the material to be store - Checks in accordance with Delivery Order/Packing List. Make a report when there are material conditions were found over, shortage or damage
This document is the property of PT Pertamina Hulu Mahakam and shall not be disclosed to third parties or reproduced without permission of the COMPANY. Electronic Filename: ID-BKP-SOME-2009-509007_rev0.1.pdf
Contract : 4500010835
Document Number
MATERIAL CONTROL PROCEDURE
ID-BKP-SOME-2009- 509007 Revision: 0.1
Document Type : PRC
System/Subsystem : N/A
Originator Document No : N/A
f.
Discipline: QUA
Status : IFC
Date : 12 – 08 - 2021 Page 9 of 23
Fabrication Supervisor Responsible to request the material for construction purpose as per approved as per approved drawing which have stamp "APPROVED FOR CONSTRUCTION" from engineering and ensure that material which should be used is meet with the requirement.
6.
7.
MATERIAL RECEIVING
Before material arrives at warehouse, Warehouse Supervisor prepare detail storage location by each material category specification, classification, size as well as area to be stored. These activities shall be planned prior to commencement warehousing operation. And when material arrives, he is fully responsible for material allocation and under authority of Project Manager / Construction Manager.
Based on complete shipping documents and or shipping schedule from forwarding / delivery Coordinator, Warehouse Supervisor shall prepare or anticipate for allocation of material storage arrival.
Material man, Warehouse Supervisor, QA/QC Inspector shall check package total quantity based on forwarding / delivery order information or Bill of Loading/ Master List/ Packing List.
All actual received materials and equipment shall be checked against packing list and package number and ensure that receiving material shall comply with Purchase Order or Bill of Material
All actual received materials and equipment shall be recorded in Material Receiving Inspection Report (MRIR) by Material man and Material Verification Report (MVR) by QC Inspector.
All actual received materials shall have supporting document such as material certificates, purchase order and packing list. Calibration Certificate, Test instrumentation and functional test shall be attached for electrical and instrument material.
When material arrives at warehouse, QC Inspector verify all documents of material, such as Purchase Order, Packing list, etc.
All COMPANY supplied materials which arrives at warehouse will be checked together with Contractor inspector according to the delivery order note and to be recorded at separated material receiving report. COMPANY should provide to Contractor with the necessary documents such as mill certificates, etc.
If the received materials were found to be over quantity, shortage, or damaged, Warehouse Supervisor shall make report on the Over, Shortage and Damage Report (OSDR) form.
STORAGE MATERIAL MANAGEMENT
Material man must control and monitor the outgoing / incoming material and to up-date the status of stock or computerized system as per discipline scope of work.
Request material by Fabrication supervisor shall follow bill of material (BOM) in construction drawing (isometric drawing or shop drawing which have stamp ("APPROVED FOR CONSTRUCTION/GOOD FOR CONSTRUCTION") to avoid double issuance.
All materials which stored on pallets or timber box must be stored above water and also don’t store near blasting and painting area to avoid contamination with painting material.
This document is the property of PT Pertamina Hulu Mahakam and shall not be disclosed to third parties or reproduced without permission of the COMPANY. Electronic Filename: ID-BKP-SOME-2009-509007_rev0.1.pdf
Contract : 4500010835
Document Number
MATERIAL CONTROL PROCEDURE
ID-BKP-SOME-2009- 509007 Revision: 0.1
Document Type : PRC
System/Subsystem : N/A
Discipline: QUA
Date : 12 – 08 - 2021
Originator Document No : N/A
8.
Status : IFC
Page 10 of 23
All material shall be segregated between Carbon steel, Stainless steel and other special material (If any).
All stainless-steel material shall be protected against the risk of saline corrosion during cleaning, transport, fabrication and storage.
Damage material shall be stored separately or in quarantine area warehouse shall prepare bonded.
Special material, flammable or hazardous materials such as painting, chemical agent, gases, etc. shall be stored in special indoor or outdoor storage with roof, the location shall be separated from other material.
Painting material such as paint and thinner shall be stored in optimal condition and delivered in their original packaging.
All materials or consumables which require protection from moisture shall be stored indoor with controlled temperature & humidity (ex. welding electrodes and rod).
Equipment for Instrumentation shall be suitable in a humid, salt laden and corrosive atmosphere.
All the equipment for Electrical and Instrumentation shall have enclosure protection degrees based on project Specification.
MATERIAL IDENTIFICATION
All material (including surplus and scrap) should have clear markings.
Upon receipt of goods, QC Inspector shall verify the items for its conformance to specifications.
Non-conforming products shall be segregated where feasible, in designated quarantine areas under HOLD status. The HOLD status shall be prominently displayed on the nonconformity item.
To ensure the control of non-conforming items, the following steps need to be done:
MVR shall be submitted to COMPANY after material Inspection by QC Inspector.
Non-conforming product or service are identified, marked, segregated and put in specific area to prevent them from being used for construction. The marking is using tags, marking ink, paint, tape, or any other specified way to identify.
The entities concerned shall be notified.
Before non-conformity or deviation is accepted by COMPANY, the material will be put HOLD status.
The result of the dispositions of non-conformities (repair, use as is and reject) shall be documented.
The Non-Conformance Report shall be closed – out. NCR follows the NCR procedure as mentioned in the document number ID-BKP-SOME-2009-504005 ( NCR Procedure )
If there is similar case of non-conformance which happen several times, it should be recorded.
This document is the property of PT Pertamina Hulu Mahakam and shall not be disclosed to third parties or reproduced without permission of the COMPANY. Electronic Filename: ID-BKP-SOME-2009-509007_rev0.1.pdf
Contract : 4500010835
Document Number
MATERIAL CONTROL PROCEDURE
ID-BKP-SOME-2009- 509007 Revision: 0.1
Document Type : PRC
System/Subsystem : N/A
Discipline: QUA
Originator Document No : N/A
9.
10.
Date : 12 – 08 - 2021 Page 11 of 23
MATERIAL INSPECTION
QC Inspector will check the conformity of material markings against material certificates based on drawing and or Project Specification.
The inspection also covers a visual and dimensional check to the material in actual condition and PMI inspection for low alloy steel and high alloy steel (if necessary).
If there is any material which is arrived not comply with project specification, QC Inspector shall identify it as HOLD and shall be stored separately and raise NCR.
MATERIAL SUBSTITUTION
Any substitution of materials shall require COMPANY written approval.
Request to COMPANY for substitution of material is the responsibility of Contractor Engineering.
Material Inspector shall be notified of all such changes and shall checks the accurate conformity of substituted material based on client specification.
All unusable & surplus materials shall be clearly identified by Fabrication Supervisor and returned to store.
11.
TRANSFERRING OF MATERIAL HEAT NUMBER
11.1
Marking Identifications Each piece of steel used for fabrication is detailed on a specific shop drawing and identified by a TAG number. The shop drawings are referring to engineering drawing (G.A, layout, etc.) and associated with a cutting plan where each TAG number is positioned on one item raw material.
11.2
Status : IFC
Marking Verification While marking the moment will be deducted. Permanent marking the moment checked QC and reported at will. Shop drawing cutting plan, fabrication team will temporarily mark each piece to be cut out (pipe) using paint marking stick and for Stainless Steel using marking Halogen type.
For piece having a TAG number: TAG reference Heat number For remaining steel or scrap and uncut:
-
-
Contractor name Project name Steel Designation Heat number
When above marking is completed and upon verification and approval of QC inspector, the fabrication team will permanently transfer to each marked piece (including uncut / scrap) the approved marking. The marking of above information can be done using hard stamping or a paint metal marking. Upon completion of marking, marked information will be reported on the corresponding shop drawing and on the traceability form. Marking and identification shall be clear and recognized to all parties involved, includes CONTRACTOR and COMPANY Inspector This document is the property of PT Pertamina Hulu Mahakam and shall not be disclosed to third parties or reproduced without permission of the COMPANY. Electronic Filename: ID-BKP-SOME-2009-509007_rev0.1.pdf
Contract : 4500010835
Document Number
MATERIAL CONTROL PROCEDURE
ID-BKP-SOME-2009- 509007 Revision: 0.1
Document Type : PRC
System/Subsystem : N/A
Discipline: QUA
Originator Document No : N/A
12.
Status : IFC
Date : 12 – 08 - 2021 Page 12 of 23
MATERIAL TRACEABILITY
The traceability form of material, i.e. Material Verification Report shall be approved by Contractor QC Inspector and reviewed by Company QA QC Inspector. It is only when the form is fully signed that fabrication is authorized to proceed with cutting and other fabrication activities.
Each original of traceability form, after QC approval, kept by Contractor QC together with the marked shop drawing.
Contractor QA/QC Coordinator is responsible to make sure that the corresponding filing system is clear, accurate and that is no case original traceability report are removed from such file.
Contractor QA/QC will maintain a Traceability Form register.
Traceability report will be part of M.D.R (Manufacturer Data Report) to be handed over to COMPANY.
Untraceable material is non-conformance; Contractor shall maintain heat number transfer to material after cutting for avoid un-identification of material.
Company supplied material shall be traced / monitor & recorded separately.
All remaining material already fixed as redundant material by Contractor to be reported on return balance material report.
Material Transportation of reconciliation materials and surplus material to COMPANY’s assigned warehouse
The basic scheme for material receiving and issuance as detailed below: Based on COMPANY Detail drawing (to be noted, detail engineering for Piping & Structure are by COMPANY); Contractor verify and assess the required material based on Contract Document. Most of piping and structure material are supplied by COMPANY Then, the MTO submitted to COMPANY for agreement between both parties COMPANY inform the material reservation to Contractor Contractor expedite to COMPANY Warehouse for further follow up of releasing Material When material ready for delivered to Contractor premise area, Contractor will arrange for material pick up Material delivered to Contractor premise, and checking based on DAN Contractor material control will checking and verify the technical data; any discrepancy will be inform to COMPANY for further rectification For material supplied by Contractor, similar process will be performed accordin -
This document is the property of PT Pertamina Hulu Mahakam and shall not be disclosed to third parties or reproduced without permission of the COMPANY. Electronic Filename: ID-BKP-SOME-2009-509007_rev0.1.pdf
Contract : 4500010835
Document Number
MATERIAL CONTROL PROCEDURE
ID-BKP-SOME-2009- 509007 Revision: 0.1
Document Type : PRC
System/Subsystem : N/A
Discipline: QUA
Originator Document No : N/A
13.
Status : IFC
Date : 12 – 08 - 2021 Page 13 of 23
APPENDICES Appendix – 1 : Material Receiving Flowchart Appendix – 2 : Material Receiving Inspection Report (MRIR) Appendix – 3 : Material Verification Report (MVR) Appendix – 4 : Over, Shortage and Damage Report (OSDR) Appendix – 5 : Non-Conformance Report (NCR) Appendix – 6 : Material Traceability Appendix – 7 : Material Subtitution Record Appendix – 8 : Surplus Material Report Appendix – 9 : Waste Material Report Appendix – 10 : Material issue slip
This document is the property of PT Pertamina Hulu Mahakam and shall not be disclosed to third parties or reproduced without permission of the COMPANY. Electronic Filename: ID-BKP-SOME-2009-509007_rev0.1.pdf
Contract : 4500010835
Document Number
MATERIAL CONTROL PROCEDURE
ID-BKP-SOME-2009- 509007 Revision: 0.1
Document Type : PRC
System/Subsystem : N/A
Discipline: QUA
Originator Document No : N/A
Status : IFC
Date : 12 – 08 - 2021 Page 14 of 23
Appendix – 1 : Material Receiving Flowchart
This document is the property of PT Pertamina Hulu Mahakam and shall not be disclosed to third parties or reproduced without permission of the COMPANY. Electronic Filename: ID-BKP-SOME-2009-509007_rev0.1.pdf
RESPONSIBILITY
ACTIVITY
Warehouse Supervisor
Receipt of Material
Warehouse Supervisor
Segregate to Inspection Area*
INTERFACE DAN / Packing list
Replacement
OSDR
Warehouse Supervisor
Apply Identification
Required Identification
Warehouse Supervisor
Prepare MRR
MRR
Material Inspector / QC Inspector
Pre – Inspection ByMaterial Control
Accepted
No
Yes Material Inspector / QC Inspector
Inspection Report OSDR MVR
Rectification
Inspection Report OSDR MVR Inspection Report OSDR MVR
Inspection with Client
Accepted
Raise OSDR
No
Yes Material Inspector / QC Inspector
QC Department
Prepare MVR
Issue for Construction
MVR
Contract : 4500010835
Document Number
MATERIAL CONTROL PROCEDURE
ID-BKP-SOME-2009- 509007 Revision: 0.1
Document Type : PRC
System/Subsystem : N/A
Originator Document No : N/A
Discipline: QUA
Status : IFC
Date : 12 – 08 - 2021 Page 15 of 23
Appendix – 2 : Material Receiving Inspection Report (MRIR)
This document is the property of PT Pertamina Hulu Mahakam and shall not be disclosed to third parties or reproduced without permission of the COMPANY. Electronic Filename: ID-BKP-SOME-2009-509007_rev0.1.pdf
BEKAPAI - 3 Surface Facilities Modification and Dogleg Installation (EPCIC) Contract No. 4500010835
MATERIAL CONTROL PROCEDURE
Revision Index Rev
Status
0.1
IFC
MATERIAL RECEIVING INSPECTION REPORT MRR. No. : 00/MRIR-
/SSTI/ARUNG/WHS/ /2020
TRANSPORT
:
ARRIVAL DATE
:
PURCHASE ORDER NO
:
RECEPTION DATE
:
D/O No.:
:
DAMAGE : Yes No
Material description, the following materials have been checked againts the mill certificates delivery order and meet requirement for which they are intended details are below. MATERIAL SUPPLIED ITEM No.
Remarks
DESCRIPTION
BY CTR (Cert. No.)
BY CPY (Cert. No.)
Material Grade/ Spec
QTY
UNIT
:
Prepared by, Warehouse
CONTRACTOR
Warehouse Supervisor
Checked by,
Inspected by, QA/QC Inspector
CONTRACTOR
CONTRACTOR
VISUAL
Contract : 4500010835
Document Number
MATERIAL CONTROL PROCEDURE
ID-BKP-SOME-2009- 509007 Revision: 0.1
Document Type : PRC
System/Subsystem : N/A
Discipline: QUA
Status : IFC
Date : 12 – 08 - 2021
Originator Document No : N/A
Page 16 of 23
Appendix – 3 : Material Verification Report (MVR)
This document is the property of PT Pertamina Hulu Mahakam and shall not be disclosed to third parties or reproduced without permission of the COMPANY. Electronic Filename: ID-BKP-SOME-2009-509007_rev0.1.pdf
BEKAPAI - 3 Surface Facilities Modification and Dogleg Installation (EPCIC) Contract No. 4500010835
Revision Index
MATERIAL CONTROL PROCEDURE
Rev
Status
0.1
IFC
MATERIAL VERIFICATION REPORT MRR. No. : TRANSPORT
:
ARRIVAL DATE
:
PURCHASE ORDER NO
:
RECEPTION DATE
:
D/O No.:
:
/
PL DAMAGE : Yes No
Material description, the following materials have been checked againts the mill certificates delivery order and meet requirement for which they are intended details are below. MATERIAL
MATERIAL REQUIRED No
SIZE Dia
TYPE
(inch)
Remarks
Sch/ Thks. (mm)
Rating
By
By
CTR
CPY
MATERIAL VERIFICATION AND IDENTIFICATION
MATERIAL MILL CERTIFICATE
SUPPLIED Type
Sch
Lot / MIRC
Heat No.
Tensile Strength
RESULT Visual
Dimension
Remarks
Indentifcation
:
SCOPE of INSPECTION : H / W Sign :
SCOPE of INSPECTION : H / W / M / R / I
SCOPE of INSPECTION : H / W / M / R / I Date :
Sign :
Sign :
MATERIAL INSPECTOR
ECP / QSE / OPS
ECP / PJC /
PT. ASTA REKAYASA UNGGUL
PT PERTAMINA HULU MAHAKAM
PT PERTAMINA HULU MAHAKAM
Date :
AR-QC-MVR-02/18
Contract : 4500010835
Document Number
MATERIAL CONTROL PROCEDURE
ID-BKP-SOME-2009- 509007 Revision: 0.1
Document Type : PRC
System/Subsystem : N/A
Originator Document No : N/A
Discipline: QUA
Status : IFC
Date : 12 – 08 - 2021 Page 17 of 23
Appendix – 4 : Over, Shortage and Damage Report (OSDR)
This document is the property of PT Pertamina Hulu Mahakam and shall not be disclosed to third parties or reproduced without permission of the COMPANY. Electronic Filename: ID-BKP-SOME-2009-509007_rev0.1.pdf
Revision Index
BEKAPAI - 3 Surface Facilities Modification and Dogleg Installation (EPCIC) Contract No. 4500010835
Rev
Status
MATERIAL CONTROL PROCEDURE
0.1
IFC
MATERIAL OVER, SHORTAGE & DAMAGE REPORT OSDR Report No. : 00 Report Date
:
PO Number
:-
MRIR Number
Supplier
:
Origin
:-
Destinatination
Carrier Number
:
Receive Date
Carrier Name :
THE ABOVE SHIPMENT RECEIVED IN FOLLOWING CONDITION Over
Substitute
Acceptable
Shortage in Packing, Package in Apparent Good but Content Short
Damage - Visible Damage to Equipment or Material
Shortage in Delivery, SEE DETAIL BELOW
Damage - Concealed Damage - Package in Apparent Good Order
Shortage in Shipment, Package Damage, Appears Opened or Repacked,
Other :
Content Short
GIVE DETAILS OF OVER, SHORTAGE OR DAMAGE ITEMS No.
QUANTITY
MRIR ITEM No.
UNIT
Delivery
Material Description
Balance
Remarks
1 2 3 4 5 6 7 8 9 10 11 NOTE : Recomendation
:
Report to Police
Exception Taken on Delivery Document
:
Report to PM/CM YES
NO
Carrier Notified On
:
Shipment Inspected On
:
Insurance Notified On
:
Copy Inspection / Survey Report Attached
:
YES
NO
Photos Attached
:
YES
NO
Original Frt. Bill Attached
:
YES
NO
Delivery Document Attached
:
YES
NO
Explanation :
Inspected / Reviewed by : PT. ASTA REKAYASA UNGGUL
Witnessed / Reviewed by PT PERTAMINA HULU MAHAKAM
Acknowledge by : PT PERTAMINA HULU MAHAKM
Material Man / Material Inspector
AR-QC-OSDR-02/18
Contract : 4500010835
Document Number
MATERIAL CONTROL PROCEDURE
ID-BKP-SOME-2009- 509007 Revision: 0.1
Document Type : PRC
System/Subsystem : N/A
Discipline: QUA
Originator Document No : N/A
Status : IFC
Date : 12 – 08 - 2021 Page 18 of 23
Appendix – 5 : Non-Conformance Report (NCR)
This document is the property of PT Pertamina Hulu Mahakam and shall not be disclosed to third parties or reproduced without permission of the COMPANY. Electronic Filename: ID-BKP-SOME-2009-509007_rev0.1.pdf
BEKAPAI - 3 Surface Facilities Modification and Dogleg Installation (EPCIC) Contract No. 4500010835 MATERIAL CONTROL PROCEDURE
Revision Index Rev
Status
0.1
IFC
NON CONFORMANCE REPORT ( NCR ) Laporan Ketidaksesuaian Project
:
Report No
:
Contract
:
Report Date
:
Client
:
Location
:
Reference Document Document yang relevan
Non Conformance Description Uraian Ketidaksesuaian
:
Root Cause Masalah Utama
:
Corrective Action : Tindakan Perbaikan
Corrective Action By :
:
Verification By :
Verification By
Date :
Signature :
Preventive Action : Tindakan Pencegahan
Final Disposition :
Use as is
Re‐work
Repair
Reject
Other Closing of NCR
Sign
:
:
Date
:
AR-QC-NCR-02/18
Contract : 4500010835
Document Number
MATERIAL CONTROL PROCEDURE
ID-BKP-SOME-2009- 509007 Revision: 0.1
Document Type : PRC
System/Subsystem : N/A
Discipline: QUA
Originator Document No : N/A
Status : IFC
Date : 12 – 08 - 2021 Page 19 of 23
Appendix – 6 : Material Traceability Form
This document is the property of PT Pertamina Hulu Mahakam and shall not be disclosed to third parties or reproduced without permission of the COMPANY. Electronic Filename: ID-BKP-SOME-2009-509007_rev0.1.pdf
MATERIAL TRACEABILITY RECORD AND NDE CLEAREANCE
Prepared By,
Checked / Reviewed By,
Reviewed / Approved By,
PT.ASTA REKAYASA UNGGUL
PT.ASTA REKAYASA UNGGUL
PT.PERTAMINA HULU MAHAKAM
QA/QC
QA/QC Coordinator / QA/QC Manager
ECP / QSE / PJC
Remarks Result
NO. Report
DATE
PT Result
MT NO. Report
Batch / Lot No.
UT DATE
AWS Class
RT
Result
MIRC or L No
NON DESTRUCTIVE TEST (NDT)
( VISUAL )
NO. Report
Heat No.
INSPECTION REPORT
DATE
Dia Ø
:
Result
SPEC.
WPS NO.
Result
Type of Material
Sch/Thk/ Rating (mm)
NO. Report
Type Joint
INSPECTION REPORT ( FIT-UP )
DATE
Joint No
WELDING CONSUMABLE
Brand Name
No.
Join Legend
MATERIAL WELDED
MODULE
NO. Report
REPORT NO. :
DATE
:
Result
CONTRACTOR
SHEET/ FOLIO :
NO. Report
CODE / SPEC :
DATE
DRAWING No :
:
WELDER STAMP
:
CLIENT
WELDING PROCESS
:
CONTRACT NO.
Dimentional Length (mm)
PROJECT NAME
Contract : 4500010835
Document Number
MATERIAL CONTROL PROCEDURE
ID-BKP-SOME-2009- 509007 Revision: 0.1
Document Type : PRC
System/Subsystem : N/A
Discipline: QUA
Status : IFC
Date : 12 – 08 - 2021
Originator Document No : N/A
Page 20 of 23
Appendix – 7 : Material Subtitution Record Form
This document is the property of PT Pertamina Hulu Mahakam and shall not be disclosed to third parties or reproduced without permission of the COMPANY. Electronic Filename: ID-BKP-SOME-2009-509007_rev0.1.pdf
BEKAPAI - 3 Surface Facilities Modification and Dogleg Installation (EPCIC) Contract No. 4500010835
Rev.
Status
MATERIAL CONTROL PROCEDURE
0.1
IFC
Revision Index
MATERIAL SUBTITUTION RECORD Project
:
Company
:
Contractor
:
Location
:
Date : Item / Material Description
No.
TQ NUMBER
DATE
Prepared by. PT. ASTA REKAYASA UNGGUL
WARE HOUSE
Initial Item / Material
Substitution Item / Material
Reason for substitution
Reviewed/Check by. PT. ASTA REKAYASA UNGGUL
QC/Material Inspector
Drawing / Isometric No. Related
Remark
Acknowled by, PT.PERTAMINA HULU MAHAKAM
ECP / PJC
Contract : 4500010835
Document Number
MATERIAL CONTROL PROCEDURE
ID-BKP-SOME-2009- 509007 Revision: 0.1
Document Type : PRC
System/Subsystem : N/A
Discipline: QUA
Originator Document No : N/A
Status : IFC
Date : 12 – 08 - 2021 Page 21 of 23
Appendix – 8 : Surplus Material Report Form
This document is the property of PT Pertamina Hulu Mahakam and shall not be disclosed to third parties or reproduced without permission of the COMPANY. Electronic Filename: ID-BKP-SOME-2009-509007_rev0.1.pdf
Revision Index
BEKAPAI - 3 Surface Facilities Modification and Dogleg Installation (EPCIC) Contract No. 4500010835
Rev.
Status
0.1
IFC
SURPLUS MATERIAL REPORT Project Company Contractor Location
NO.
: : : :
Date :
DESCRIPTION
HEAD NUMBER MIRC / MAT.NO
SUB TOTAL
Prepared by, PT. ASTA REKAYASA UNGGUL
Inspected by, PT.ASTA REKAYASA UNGGUL
WARE HOUSE
QC INSPECTOR
TOTAL QTY
EX STOCK
REMARKS
Acknowled by, PT.PERTAMINA HULU MAHAKAM
ENG / PJC
Contract : 4500010835
Document Number
MATERIAL CONTROL PROCEDURE
ID-BKP-SOME-2009- 509007 Revision: 0.1
Document Type : PRC
System/Subsystem : N/A
Discipline: QUA
Originator Document No : N/A
Status : IFC
Date : 12 – 08 - 2021 Page 22 of 23
Appendix – 9 : Waste Material Report
This document is the property of PT Pertamina Hulu Mahakam and shall not be disclosed to third parties or reproduced without permission of the COMPANY. Electronic Filename: ID-BKP-SOME-2009-509007_rev0.1.pdf
Revision Index BEKAPAI - 3 Surface Facilities Modification and Dogleg Installation (EPCIC) Contract No. 4500010835
Rev
Status
0.1
IFC
WASTE MATERIAL REPORT Project
:
Company
:
Contractor
:
Location
:
No.
Date : DESCRIPTION
TOTAL QTY
DATE OF DELIVERY
( D.A.N ) NUMBER
Prepared by :
Reviewed by :
Approved by :
Name : Date : MATERIAL CONTROLER
Name : Date : QC INSPECTOR
Name : Date : ECP / PJC
REMARKS
Contract : 4500010835
Document Number
MATERIAL CONTROL PROCEDURE
ID-BKP-SOME-2009- 509007 Revision: 0.1
Document Type : PRC
System/Subsystem : N/A
Discipline: QUA
Originator Document No : N/A
Status : IFC
Date : 12 – 08 - 2021 Page 23 of 23
Appendix – 10 : Material issue slip
This document is the property of PT Pertamina Hulu Mahakam and shall not be disclosed to third parties or reproduced without permission of the COMPANY. Electronic Filename: ID-BKP-SOME-2009-509007_rev0.1.pdf
BEKAPAI - 3 Surface Facilities Modification and Dogleg Installation (EPCIC) Contract No. 4500010835
Rev.
Status
MATERIAL CONTROL PROCEDURE
0.1
IFC
Revision Index
MATERIAL ISSUE SLIP Project
:
MIS No
:
Company
:
Rev of Drawing
:
Contractor
:
Class
: Piping/Pipeline/Str/E&I
Location
:
Date Requested
:
No.
Mat'l no.
Item Description
Warehouse,
Req'd
Issued
Qty
Qty
Issued Date
Received,
Drawing No.
Folio
Service line
Approved,
Name
:
Name
:
Name
:
Date
:
Date
:
Date
:
Remarks
Location