36 1 121KB
DMCI MANPOWER RATES ALL INCLUSIVE 12 HR/DAY, 6 DAYS/WEEK LABOR RATES Code
DESCRIPTION
Rate/hr
Rate/day
Rate Factor
NCR RATE hr day
12 hr rate day
1.25 All inclusive rate % day
0% Night Time/Sunday hr day
Ave. Rate (incl. Ot & hr Holidays) day
L1
0% Mark up day
Total Rate day
Out of Town day Allowance
Sub-Total Rate day
489.93
-
489.93
-
61.24
489.93
512.80 553.62 689.17
-
64.10 69.20 86.15
512.80 553.62 689.17
0
COLA day
hr
1.00
45.25
362.00
531.69
1.25
664.61
66.18
512.80 553.62 689.17
1.05 1.13 1.41
47.36 51.13 63.65
378.89 409.06 509.21
556.50 600.81 747.91
1.25 1.25 1.25
695.62 751.01 934.88
69.26 74.78 93.09
761.91 822.57 1,023.96
64.10 69.20 86.15
512.80 553.62 689.17
-
64.10 69.20 86.15
512.80 553.62 689.17
1.05 1.13 1.41
47.36 51.13 63.65
378.89 409.06 509.21
556.50 600.81 747.91
1.25 1.25 1.25
695.62 751.01 934.88
69.26 74.78 93.09
761.91 822.57 1,023.96
64.10 69.20 86.15
512.80 553.62 689.17
-
512.80 553.62 689.17
-
64.10 69.20 86.15
512.80 553.62 689.17
Steelman 1 Steelman 2 Steelman 3
64.10 67.57 84.72
512.80 540.56 677.74
1.05 1.10 1.38
47.36 49.93 62.60
378.89 399.41 500.77
556.50 586.63 735.50
1.25 1.25 1.25
695.62 733.29 919.38
69.26 73.01 91.54
761.91 803.16 1,006.98
64.10 67.57 84.72
512.80 540.56 677.74
-
512.80 540.56 677.74
-
64.10 67.57 84.72
512.80 540.56 677.74
L5.1 L5.2 L5.3
Driver 1 Driver 2 Driver 3
67.37 69.20 84.51
538.92 553.62 676.11
1.10 1.13 1.38
49.78 51.13 62.45
398.20 409.06 499.56
584.86 600.81 733.73
1.25 1.25 1.25
731.07 751.01 917.16
72.79 74.78 91.32
800.73 822.57 1,004.55
67.37 69.20 84.51
538.92 553.62 676.11
-
538.92 553.62 676.11
-
67.37 69.20 84.51
538.92 553.62 676.11
L5.4 L5.5 L5.6 L5.7
Heavy Equipment Optr 1 Heavy Equipment Optr 2 Heavy Equipment Optr 3 Heavy Equipment Optr 4
64.51 67.37 84.51 109.42
516.06 538.92 676.11 875.34
1.05 1.10 1.38 1.79
47.66 49.78 62.45 80.85
381.31 398.20 499.56 646.77
560.04 584.86 733.73 949.95
1.25 1.25 1.25 1.25
700.06 731.07 917.16 1,187.44
69.71 72.79 91.32 118.23
766.76 800.73 1,004.55 1,300.58
64.51 67.37 84.51 109.42
516.06 538.92 676.11 875.34
-
516.06 538.92 676.11 875.34
-
64.51 67.37 84.51 109.42
516.06 538.92 676.11 875.34
L6.1 L6.2 L6.3
Welder 1 Welder 2 Welder 3
67.16 83.49 101.86
537.29 667.94 814.92
1.10 1.36 1.66
49.62 61.69 75.27
396.99 493.53 602.13
583.08 724.87 884.37
1.25 1.25 1.25
728.85 906.08 1,105.47
72.57 90.22 110.07
798.30 992.42 1,210.80
67.16 83.49 101.86
537.29 667.94 814.92
-
537.29 667.94 814.92
-
67.16 83.49 101.86
537.29 667.94 814.92
Labor
61.24
L2.1 L2.2 L2.3
Carpenter 1 Carpenter 2 Carpenter 3
64.10 69.20 86.15
L3.1 L3.2 L3.3
Mason 1 Mason 2 Mason 3
L4.1 L4.2 L4.3
489.93
727.94
61.24
L7
Pipe Fitter 1
83.49
667.94
1.36
61.69
493.53
724.87
1.25
906.08
90.22
992.42
83.49
667.94
-
667.94
-
83.49
667.94
L8
Plumber 1
67.16
537.29
1.10
49.62
396.99
583.08
1.25
728.85
72.57
798.30
67.16
537.29
-
537.29
-
67.16
537.29
L9.1 L9.2 L9.3
Electrician 1 Electrician 2 Electrician 3
67.16 86.15 109.42
537.29 689.17 875.34
1.10 1.41 1.79
49.62 63.65 80.85
396.99 509.21 646.77
583.08 747.91 949.95
1.25 1.25 1.25
728.85 934.88 1,187.44
72.57 93.09 118.23
798.30 1,023.96 1,300.58
67.16 86.15 109.42
537.29 689.17 875.34
-
537.29 689.17 875.34
-
67.16 86.15 109.42
537.29 689.17 875.34
L10.1 L10.2 L10.3
Mechanic 1 Mechanic 2 Mechanic 3
67.16 86.15 109.42
537.29 689.17 875.34
1.10 1.41 1.79
49.62 63.65 80.85
396.99 509.21 646.77
583.08 747.91 949.95
1.25 1.25 1.25
728.85 934.88 1,187.44
72.57 93.09 118.23
798.30 1,023.96 1,300.58
67.16 86.15 109.42
537.29 689.17 875.34
-
537.29 689.17 875.34
-
67.16 86.15 109.42
537.29 689.17 875.34
L11.1
Rigger
64.51
516.06
1.05
47.66
381.31
560.04
1.25
700.06
69.71
766.76
64.51
516.06
-
516.06
-
64.51
516.06
L12.1
Tender
64.71
517.69
1.06
47.81
382.51
561.82
1.25
702.27
69.93
769.19
64.71
517.69
-
517.69
-
64.71
517.69
L13.1
Painter
81.25
649.98
1.33
60.03
480.25
705.37
1.25
881.72
87.79
965.73
81.25
649.98
-
649.98
-
81.25
649.98
L14.1
Skilled Labor
64.10
512.80
1.05
47.36
378.89
556.50
1.25
695.62
69.26
761.91
64.10
512.80
-
512.80
-
64.10
512.80
L15
Batching Plant Operator
89.21
713.67
1.46
65.91
527.31
774.49
1.25
968.11
96.40
1,060.36
89.21
713.67
-
713.67
-
89.21
713.67
L16
Laboratory Aide
67.16
537.29
1.10
49.62
396.99
583.08
1.25
728.85
72.57
798.30
67.16
537.29
-
537.29
-
67.16
537.29
LABOR RATES Code
Designation 0
Applicable Rate Monthly
Daily
Hourly
Rate Factor
Base Rate (NCR) Monthly
Daily
Monthly Credit
Hourly
SSS Contribution Employer Share Daily
Monthly
Monthly Credit
Hourly
PhilHealth Contribution Employer Share Daily
Monthly
Monthly Credit
Hourly
PAG-IBIG Contribution Employer Share Daily
Monthly
Allowances (Transportation / Meal / Others) Monthly Daily Hourly
Hourly
Vacation / Sick Leave Monthly
Daily
13th Month Pay Hourly
Monthly
Daily
Hourly
Monthly
(6pm - 10pm) Daily
Hourly
Overtime (10pm - 12pm) Daily
Monthly
Hourly
(Sunday/Holiday) Daily
Monthly
Hourly
PLS. DO NOT DELETE THIS ROW!
A
DIRECT LABOR & WORKERS
L1
Labor
13,258.48
505.73
63.22
1.00
9,228.27
352.00
44.00
9,000.00
646.00
24.64
3.08
9,000.00
112.50
4.29
0.54
9,000.00
180.00
6.87
0.86
541.67
20.66
2.58
769.02
29.33
3.67
769.02
29.33
3.67
660.00
25.17
3.15
-
-
-
352.00
13.43
1.68
Carpenter 1 Carpenter 2 Carpenter 3
13,911.33 14,892.86 18,461.02
530.63 568.07 704.17
66.33 71.01 88.02
1.05 1.13 1.41
9,658.92 10,427.94 12,981.10
368.43 397.76 495.15
46.05 49.72 61.89
10,000.00 10,000.00 13,000.00
716.70 716.70 928.70
27.34 27.34 35.42
3.42 3.42 4.43
10,000.00 10,000.00 13,000.00
125.00 125.00 162.50
4.77 4.77 6.20
0.60 0.60 0.77
10,000.00 10,000.00 13,000.00
200.00 200.00 260.00
7.63 7.63 9.92
0.95 0.95 1.24
541.67 541.67 541.67
20.66 20.66 20.66
2.58 2.58 2.58
804.91 869.00 1,081.76
30.70 33.15 41.26
3.84 4.14 5.16
804.91 869.00 1,081.76
30.70 33.15 41.26
3.84 4.14 5.16
690.80 745.80 928.40
26.35 28.45 35.41
3.29 3.56 4.43
-
-
-
368.43 397.76 495.15
14.05 15.17 18.89
1.76 1.90 2.36
L3.1 L3.2 L3.3
Mason 1 Mason 2 Mason 3
13,911.33 14,892.86 18,461.02
530.63 568.07 704.17
66.33 71.01 88.02
1.05 1.13 1.41
9,658.92 10,427.94 12,981.10
368.43 397.76 495.15
46.05 49.72 61.89
10,000.00 10,000.00 13,000.00
716.70 716.70 928.70
27.34 27.34 35.42
3.42 3.42 4.43
10,000.00 10,000.00 13,000.00
125.00 125.00 162.50
4.77 4.77 6.20
0.60 0.60 0.77
10,000.00 10,000.00 13,000.00
200.00 200.00 260.00
7.63 7.63 9.92
0.95 0.95 1.24
541.67 541.67 541.67
20.66 20.66 20.66
2.58 2.58 2.58
804.91 869.00 1,081.76
30.70 33.15 41.26
3.84 4.14 5.16
804.91 869.00 1,081.76
30.70 33.15 41.26
3.84 4.14 5.16
690.80 745.80 928.40
26.35 28.45 35.41
3.29 3.56 4.43
-
-
-
368.43 397.76 495.15
14.05 15.17 18.89
1.76 1.90 2.36
L4.1 L4.2 L4.3
Steelman 1 Steelman 2 Steelman 3
13,911.33 14,578.77 18,186.20
530.63 556.09 693.69
66.33 69.51 86.71
1.05 1.10 1.38
9,658.92 10,181.85 12,765.77
368.43 388.37 486.93
46.05 48.55 60.87
10,000.00 10,000.00 13,000.00
716.70 716.70 928.70
27.34 27.34 35.42
3.42 3.42 4.43
10,000.00 10,000.00 13,000.00
125.00 125.00 162.50
4.77 4.77 6.20
0.60 0.60 0.77
10,000.00 10,000.00 13,000.00
200.00 200.00 260.00
7.63 7.63 9.92
0.95 0.95 1.24
541.67 541.67 541.67
20.66 20.66 20.66
2.58 2.58 2.58
804.91 848.49 1,063.81
30.70 32.36 40.58
3.84 4.05 5.07
804.91 848.49 1,063.81
30.70 32.36 40.58
3.84 4.05 5.07
690.80 728.20 913.00
26.35 27.78 34.83
3.29 3.47 4.35
-
-
-
368.43 388.37 486.93
14.05 14.81 18.57
1.76 1.85 2.32
L5.1 L5.2 L5.3
Driver 1 Driver 2 Driver 3
14,539.51 14,892.86 18,146.94
554.59 568.07 692.19
69.32 71.01 86.52
1.10 1.13 1.38
10,151.09 10,427.94 12,735.01
387.20 397.76 485.76
48.40 49.72 60.72
10,000.00 10,000.00 13,000.00
716.70 716.70 928.70
27.34 27.34 35.42
3.42 3.42 4.43
10,000.00 10,000.00 13,000.00
125.00 125.00 162.50
4.77 4.77 6.20
0.60 0.60 0.77
10,000.00 10,000.00 13,000.00
200.00 200.00 260.00
7.63 7.63 9.92
0.95 0.95 1.24
541.67 541.67 541.67
20.66 20.66 20.66
2.58 2.58 2.58
845.92 869.00 1,061.25
32.27 33.15 40.48
4.03 4.14 5.06
845.92 869.00 1,061.25
32.27 33.15 40.48
4.03 4.14 5.06
726.00 745.80 910.80
27.69 28.45 34.74
3.46 3.56 4.34
-
-
-
387.20 397.76 485.76
14.77 15.17 18.53
1.85 1.90 2.32
L5.4 L5.5 L5.6 L5.7
Heavy Equipment Optr 1 Heavy Equipment Optr 2 Heavy Equipment Optr 3 Heavy Equipment Optr 4
13,989.85 14,539.51 18,146.94 23,195.68
533.62 554.59 692.19 884.77
66.70 69.32 86.52 110.60
1.05 1.10 1.38 1.79
9,720.44 10,151.09 12,735.01 16,487.84
370.77 387.20 485.76 628.91
46.35 48.40 60.72 78.61
10,000.00 10,000.00 13,000.00 16,000.00
716.70 716.70 928.70 1,090.10
27.34 27.34 35.42 41.58
3.42 3.42 4.43 5.20
10,000.00 10,000.00 13,000.00 16,000.00
125.00 125.00 162.50 200.00
4.77 4.77 6.20 7.63
0.60 0.60 0.77 0.95
10,000.00 10,000.00 13,000.00 16,000.00
200.00 200.00 260.00 320.00
7.63 7.63 9.92 12.21
0.95 0.95 1.24 1.53
541.67 541.67 541.67 541.67
20.66 20.66 20.66 20.66
2.58 2.58 2.58 2.58
810.04 845.92 1,061.25 1,373.99
30.90 32.27 40.48 52.41
3.86 4.03 5.06 6.55
810.04 845.92 1,061.25 1,373.99
30.90 32.27 40.48 52.41
3.86 4.03 5.06 6.55
695.20 726.00 910.80 1,179.20
26.52 27.69 34.74 44.98
3.31 3.46 4.34 5.62
-
-
-
370.77 387.20 485.76 628.91
14.14 14.77 18.53 23.99
1.77 1.85 2.32 3.00
L6.1 L6.2 L6.3
L2.1 L2.2 L2.3
Welder 1 Welder 2 Welder 3
14,500.25 17,950.63 21,710.52
553.09 684.70 828.12
69.14 85.59 103.51
1.10 1.36 1.66
10,120.33 12,581.20 15,349.68
386.03 479.89 585.49
48.25 59.99 73.19
10,000.00 13,000.00 15,000.00
716.70 928.70 1,090.10
27.34 35.42 41.58
3.42 4.43 5.20
10,000.00 13,000.00 15,000.00
125.00 162.50 187.50
4.77 6.20 7.15
0.60 0.77 0.89
10,000.00 13,000.00 15,000.00
200.00 260.00 300.00
7.63 9.92 11.44
0.95 1.24 1.43
541.67 541.67 541.67
20.66 20.66 20.66
2.58 2.58 2.58
843.36 1,048.43 1,279.14
32.17 39.99 48.79
4.02 5.00 6.10
843.36 1,048.43 1,279.14
32.17 39.99 48.79
4.02 5.00 6.10
723.80 899.80 1,097.80
27.61 34.32 41.87
3.45 4.29 5.23
-
-
-
386.03 479.89 585.49
14.72 18.30 22.33
1.84 2.29 2.79
L7
Pipe Fitter 1
17,950.63
684.70
85.59
1.36
12,581.20
479.89
59.99
13,000.00
928.70
35.42
4.43
13,000.00
162.50
6.20
0.77
13,000.00
260.00
9.92
1.24
541.67
20.66
2.58
1,048.43
39.99
5.00
1,048.43
39.99
5.00
899.80
34.32
4.29
-
-
-
479.89
18.30
2.29
L8
Plumber 1
14,500.25
553.09
69.14
1.10
10,120.33
386.03
48.25
10,000.00
716.70
27.34
3.42
10,000.00
125.00
4.77
0.60
10,000.00
200.00
7.63
0.95
541.67
20.66
2.58
843.36
32.17
4.02
843.36
32.17
4.02
723.80
27.61
3.45
-
-
-
386.03
14.72
1.84
L9.1 L9.2 L9.3
Electrician 1 Electrician 2 Electrician 3
14,500.25 18,461.02 23,195.68
553.09 704.17 884.77
69.14 88.02 110.60
1.10 1.41 1.79
10,120.33 12,981.10 16,487.84
386.03 495.15 628.91
48.25 61.89 78.61
10,000.00 13,000.00 16,000.00
716.70 928.70 1,090.10
27.34 35.42 41.58
3.42 4.43 5.20
10,000.00 13,000.00 16,000.00
125.00 162.50 200.00
4.77 6.20 7.63
0.60 0.77 0.95
10,000.00 13,000.00 16,000.00
200.00 260.00 320.00
7.63 9.92 12.21
0.95 1.24 1.53
541.67 541.67 541.67
20.66 20.66 20.66
2.58 2.58 2.58
843.36 1,081.76 1,373.99
32.17 41.26 52.41
4.02 5.16 6.55
843.36 1,081.76 1,373.99
32.17 41.26 52.41
4.02 5.16 6.55
723.80 928.40 1,179.20
27.61 35.41 44.98
3.45 4.43 5.62
-
-
-
386.03 495.15 628.91
14.72 18.89 23.99
1.84 2.36 3.00
L10.1 L10.2 L10.3
Mechanic 1 Mechanic 2 Mechanic 3
14,500.25 18,461.02 23,195.68
553.09 704.17 884.77
69.14 88.02 110.60
1.10 1.41 1.79
10,120.33 12,981.10 16,487.84
386.03 495.15 628.91
48.25 61.89 78.61
10,000.00 13,000.00 16,000.00
716.70 928.70 1,090.10
27.34 35.42 41.58
3.42 4.43 5.20
10,000.00 13,000.00 16,000.00
125.00 162.50 200.00
4.77 6.20 7.63
0.60 0.77 0.95
10,000.00 13,000.00 16,000.00
200.00 260.00 320.00
7.63 9.92 12.21
0.95 1.24 1.53
541.67 541.67 541.67
20.66 20.66 20.66
2.58 2.58 2.58
843.36 1,081.76 1,373.99
32.17 41.26 52.41
4.02 5.16 6.55
843.36 1,081.76 1,373.99
32.17 41.26 52.41
4.02 5.16 6.55
723.80 928.40 1,179.20
27.61 35.41 44.98
3.45 4.43 5.62
-
-
-
386.03 495.15 628.91
14.72 18.89 23.99
1.84 2.36 3.00
L11.1
Rigger
13,989.85
533.62
66.70
1.05
9,720.44
370.77
46.35
10,000.00
716.70
27.34
3.42
10,000.00
125.00
4.77
0.60
10,000.00
200.00
7.63
0.95
541.67
20.66
2.58
810.04
30.90
3.86
810.04
30.90
3.86
695.20
26.52
3.31
-
-
-
370.77
14.14
1.77
L12.1
Tender
14,029.12
535.12
66.89
1.06
9,751.20
371.95
46.49
10,000.00
716.70
27.34
3.42
10,000.00
125.00
4.77
0.60
10,000.00
200.00
7.63
0.95
541.67
20.66
2.58
812.60
31.00
3.87
812.60
31.00
3.87
697.40
26.60
3.33
-
-
-
371.95
14.19
1.77
L13.1
Painter
17,415.56
664.29
83.04
1.33
12,242.83
466.99
58.37
12,000.00
858.00
32.73
4.09
12,000.00
150.00
5.72
0.72
12,000.00
240.00
9.15
1.14
541.67
20.66
2.58
1,020.24
38.92
4.86
1,020.24
38.92
4.86
875.60
33.40
4.17
-
-
-
466.99
17.81
2.23
L14.1
Skilled Labor
13,911.33
530.63
66.33
1.05
9,658.92
368.43
46.05
10,000.00
716.70
27.34
3.42
10,000.00
125.00
4.77
0.60
10,000.00
200.00
7.63
0.95
541.67
20.66
2.58
804.91
30.70
3.84
804.91
30.70
3.84
690.80
26.35
3.29
-
-
-
368.43
14.05
1.76
L15.1 L15.2
QC Technician Laboratory Aide
14,500.25 14,500.25
553.09 553.09
69.14 69.14
1.10 1.10
10,120.33 10,120.33
386.03 386.03
48.25 48.25
10,000.00 10,000.00
716.70 716.70
27.34 27.34
3.42 3.42
10,000.00 10,000.00
125.00 125.00
4.77 4.77
0.60 0.60
10,000.00 10,000.00
200.00 200.00
7.63 7.63
0.95 0.95
541.67 541.67
20.66 20.66
2.58 2.58
843.36 843.36
32.17 32.17
4.02 4.02
843.36 843.36
32.17 32.17
4.02 4.02
723.80 723.80
27.61 27.61
3.45 3.45
-
-
-
386.03 386.03
14.72 14.72
1.84 1.84
L16.1 L16.2 L16.3 L16.4
Batching Plant Operator Asphalt Plant Operator Crusher Plant Operator Screening Plant Operator
19,049.94 19,049.94 19,049.94 19,049.94
726.63 726.63 726.63 726.63
90.83 90.83 90.83 90.83
1.46 1.46 1.46 1.46
13,442.51 13,442.51 13,442.51 13,442.51
512.75 512.75 512.75 512.75
64.09 64.09 64.09 64.09
13,000.00 13,000.00 13,000.00 13,000.00
928.70 928.70 928.70 928.70
35.42 35.42 35.42 35.42
4.43 4.43 4.43 4.43
13,000.00 13,000.00 13,000.00 13,000.00
162.50 162.50 162.50 162.50
6.20 6.20 6.20 6.20
0.77 0.77 0.77 0.77
13,000.00 13,000.00 13,000.00 13,000.00
260.00 260.00 260.00 260.00
9.92 9.92 9.92 9.92
1.24 1.24 1.24 1.24
541.67 541.67 541.67 541.67
20.66 20.66 20.66 20.66
2.58 2.58 2.58 2.58
1,120.21 1,120.21 1,120.21 1,120.21
42.73 42.73 42.73 42.73
5.34 5.34 5.34 5.34
1,120.21 1,120.21 1,120.21 1,120.21
42.73 42.73 42.73 42.73
5.34 5.34 5.34 5.34
961.40 961.40 961.40 961.40
36.67 36.67 36.67 36.67
4.58 4.58 4.58 4.58
-
-
-
512.75 512.75 512.75 512.75
19.56 19.56 19.56 19.56
2.44 2.44 2.44 2.44
L17.1
Special Skills
23,195.68
884.77
110.60
1.79
16,487.84
628.91
78.61
16,000.00
1,090.10
41.58
5.20
16,000.00
200.00
7.63
0.95
16,000.00
320.00
12.21
1.53
541.67
20.66
2.58
1,373.99
52.41
6.55
1,373.99
52.41
6.55
1,179.20
44.98
5.62
-
-
-
628.91
23.99
3.00
B
ENGINEERS & ARCHITECTS
E1
Engineer 1
28,183.36
1,075.02
134.38
1.00
20,000.00
762.87
95.36
20,000.00
1,090.10
41.58
5.20
20,000.00
250.00
9.54
1.19
20,000.00
400.00
15.26
1.91
916.67
34.97
4.37
1,666.67
63.57
7.95
1,666.67
63.57
7.95
1,430.39
54.56
6.82
-
-
-
762.87
29.10
3.64
E2
Engineer 2
40,127.35
1,530.60
191.33
1.00
30,000.00
1,144.31
143.04
30,000.00
1,090.10
41.58
5.20
30,000.00
375.00
14.30
1.79
30,000.00
600.00
22.89
2.86
916.67
34.97
4.37
2,500.00
95.36
11.92
2,500.00
95.36
11.92
2,145.58
81.84
10.23
-
-
-
-
-
-
E3
Engineer 3
52,884.21
2,017.20
252.15
1.00
40,000.00
1,525.75
190.72
40,000.00
1,090.10
41.58
5.20
40,000.00
750.00
28.61
3.58
40,000.00
600.00
22.89
2.86
916.67
34.97
4.37
3,333.33
127.15
15.89
3,333.33
127.15
15.89
2,860.78
109.12
13.64
-
-
-
-
-
-
E4
Engineer 4
65,266.07
2,489.49
311.19
1.00
50,000.00
1,907.18
238.40
50,000.00
1,090.10
41.58
5.20
50,000.00
750.00
28.61
3.58
50,000.00
600.00
22.89
2.86
916.67
34.97
4.37
4,166.67
158.93
19.87
4,166.67
158.93
19.87
3,575.97
136.40
17.05
-
-
-
-
-
C
SITE SUPERVISOR
S1
Foreman
31,825.04
1,213.92
151.74
2.50
23,070.67
880.00
110.00
23,000.00
1,090.10
41.58
5.20
23,000.00
287.50
10.97
1.37
23,000.00
460.00
17.55
2.19
541.67
20.66
2.58
1,922.56
73.33
9.17
1,922.56
73.33
9.17
1,650.00
62.94
7.87
-
-
-
880.00
33.57
4.20
S2
Sub-Foreman
25,773.39
983.09
122.89
2.00
18,456.53
704.00
88.00
18,000.00
1,090.10
41.58
5.20
18,000.00
225.00
8.58
1.07
18,000.00
360.00
13.73
1.72
541.67
20.66
2.58
1,538.04
58.67
7.33
1,538.04
58.67
7.33
1,320.00
50.35
6.29
-
-
-
704.00
26.85
3.36
S3
Lead Hand
23,385.23
892.00
111.50
1.80
16,610.88
633.60
79.20
17,000.00
1,090.10
41.58
5.20
17,000.00
212.50
8.11
1.01
17,000.00
340.00
12.97
1.62
541.67
20.66
2.58
1,384.24
52.80
6.60
1,384.24
52.80
6.60
1,188.00
45.31
5.66
-
-
-
633.60
24.17
3.02
D
IN CHARGE OF OPERATIONS
I1
Batching Plant In Charge
40,127.35
1,530.60
191.33
1.00
30,000.00
1,144.31
143.04
30,000.00
1,090.10
41.58
5.20
30,000.00
375.00
14.30
1.79
30,000.00
600.00
22.89
2.86
916.67
34.97
4.37
2,500.00
95.36
11.92
2,500.00
95.36
11.92
2,145.58
81.84
10.23
-
-
-
-
-
-
I2
Asphalt Plant In Charge
40,127.35
1,530.60
191.33
1.00
30,000.00
1,144.31
143.04
30,000.00
1,090.10
41.58
5.20
30,000.00
375.00
14.30
1.79
30,000.00
600.00
22.89
2.86
916.67
34.97
4.37
2,500.00
95.36
11.92
2,500.00
95.36
11.92
2,145.58
81.84
10.23
-
-
-
-
-
-
I3
Aggregates Crusher Plant In Charge
40,127.35
1,530.60
191.33
1.00
30,000.00
1,144.31
143.04
30,000.00
1,090.10
41.58
5.20
30,000.00
375.00
14.30
1.79
30,000.00
600.00
22.89
2.86
916.67
34.97
4.37
2,500.00
95.36
11.92
2,500.00
95.36
11.92
2,145.58
81.84
10.23
-
-
-
-
-
-
I4
Quarry Operations In Charge
40,127.35
1,530.60
191.33
1.00
30,000.00
1,144.31
143.04
30,000.00
1,090.10
41.58
5.20
30,000.00
375.00
14.30
1.79
30,000.00
600.00
22.89
2.86
916.67
34.97
4.37
2,500.00
95.36
11.92
2,500.00
95.36
11.92
2,145.58
81.84
10.23
-
-
-
-
-
-
Notes:
Particulars No. of Working Days / Month No. of Working Hours / Day Minimum Daily Wage Allowances Direct Labor & Workers Engineers Vacation / Sick Leave 13th Month Pay Overtime Multiplier (6pm-10pm) Overtime Multiplier (10pm-12pm) Overtime Multiplier (Sundays / Holidays) Estimated Overtime (6pm - 10pm) Estimated Overtime (10pm - 12pm) Estimated Overtime (Sundays / Holidays)
Quantity
Unit / Remarks
26.22 Days 8.00 Hours 352.00 Pesos / Day 20.66 Pesos / Day 916.67 Pesos / Month 1.00 1.00 1.25 1.35 2.00 12.00 4.00
Month / Year Month / Year x Base Rate x Base Rate x Base Rate Hours / Month Hours / Month Hours / Month
Comments 314.6 days / year divided by 12 months / year Meal P 0.00 / meal P 0.00 / mo.
average of 2 hour(s)/day for average of 0 hour(s)/day for average of 1 Sunday(s)/month
Transportation
2 day(s) / week 1 day(s) / week
Uniform/Clothing P 0.00 / day P 291.67 / mo.
Factor Factor Factor
Recreation P 83.33 / mo.
Medical/Insurance P 20.66 / day P 541.67 / mo.
5.72% of Total Hours / Month 0.00% of Total Hours / Month 1.91% of Total Hours / Month
-
LABOR PRODUCTIVITY Code
Description Rebar Works
LP1.1 LP1.2 LP1.3 LP1.4 LP1.5 LP1.6
Rebars Fabrication Rebar Installation (on ground) Rebar Installation (on wall) Rebar Installation (on suspended slab) Rebar Installation (on column) Rebar Installation (on elevated beams)
1 1 1 1 1 1
Steelman Steelman Steelman Steelman Steelman Steelman
4 4 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Laborer Laborer Mason Mason Mason Mason Mason Mason Mason Mason Mason Mason Mason Mason Mason Mason Mason Mason Mason Mason Mason Mason Mason Mason Mason Mason Mason Mason Laborer Mason Mason Mason Mason Mason
Masonry & Concreting Works LP2.1 LP2.2 LP2.3 LP2.4 LP2.5 LP2.6 LP2.7 LP2.8 LP2.9 LP2.10 LP2.11 LP2.12 LP2.13 LP2.14 LP2.15 LP2.16 LP2.17 LP2.18 LP2.19 LP2.20 LP2.21 LP2.22 LP2.23 LP2.24 LP2.25 LP2.26 LP2.27 LP2.27.1 LP2.28 LP2.29 LP2.30 LP2.31 LP2.32 LP2.33
Mortar Mixing - using bagger mixer Mortar Mixing - manual CHB Laying (150mm (6") thick) CHB Laying (100mm (4") thick) Plastering Corner Edging Scouring Finishing of CHB joint Floor Cement Finishing Concrete topping Rub Concrete Floor tiles Wall tiles Red bricks Marble slab Marble wall Tile capping Peeble Wash-out (Floor) Peeble Wash-out (Wall) Peeble Wash-out (Stair) Concreting (Footings & Grade Slab) Concreting (Floor Beams) Concreting (Roof Beams) Concreting (Suspended Slab) Concreting (Roof Slab) Concreting (Walls & Stair) Concreting (Column) Concreting (Walls/Column/Slab) Placing escombro riprap Grouted Riprap Stone Masonry Paper Holder Installation Soap Holder Installation RCP Installation 8" dia.
LABOR PRODUCTIVITY Code LP2.34 LP2.35 LP2.36 LP2.37 LP2.38 LP2.39 LP2.40 LP2.41 LP2.42 LP2.43 LP2.44 LP2.45 LP2.46 LP2.47 LP2.48 LP2.49 LP2.50 LP2.51 LP2.52 LP2.53 LP2.54 LP2.55 LP2.56 LP2.57 LP2.58
Description RCP Installation 10" dia. RCP Installation 12" dia. RCP Installation 15" dia. RCP Installation 18" dia. RCP Installation 24" dia. RCP Installation 30" dia. RCP Installation 36" dia. RCP Installation 42" dia. RCP Installation 48" dia. RCP Installation 54" dia. RCP Installation 60" dia. RCP Installation 72" dia. RCP collaring 8" dia. RCP collaring 10" dia. RCP collaring 12" dia. RCP collaring 15" dia. RCP collaring 18" dia. RCP collaring 24" dia. RCP collaring 30" dia. RCP collaring 36" dia. RCP collaring 42" dia. RCP collaring 48" dia. RCP collaring 54" dia. RCP collaring 60" dia. RCP collaring 72" dia.
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Mason Mason Mason Mason Mason Mason Mason Mason Mason Mason Mason Mason Mason Mason Mason Mason Mason Mason Mason Mason Mason Mason Mason Mason Mason
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
- Carpenter - Carpenter - Carpenter - Carpenter - Carpenter - Carpenter - Carpenter - Carpenter - Carpenter - Carpenter - Carpenter - Carpenter - Carpenter - Carpenter - Carpenter - Carpenter - Carpenter
Form & Carpentry Works LP3.1 LP3.2 LP3.3 LP3.4 LP3.5 LP3.6 LP3.7 LP3.8 LP3.9 LP3.10 LP3.11 LP3.12 LP3.13 LP3.14 LP3.15 LP3.16 LP3.17
Batterboard Installation Forms Fabrication Forms Installation - Slab on Fill Forms Installation - Wall on ground Forms Installation - Wall above 10' Forms Installation - Beams Forms Installation - Columns Forms Installation - Suspended Slab up to 18' Forms Installation - Suspended Slab 19' to 36' Forms Installation - Suspended Slab 36" up Forms Installation - Stairs Forms Stripping - Wall on Ground Forms Stripping - Wall above 10' Forms Stripping - Beams Forms Stripping - Columns Forms Stripping - Columns Forms Stripping - Suspended slab up to 18'
LABOR PRODUCTIVITY Code LP3.18 LP3.19 LP3.20 LP3.21 LP3.22 LP3.23 LP3.24 LP3.25 LP3.26 LP3.27 LP3.28 LP3.29 LP3.30 LP3.31 LP3.32 LP3.33 LP3.34 LP3.35 LP3.36 LP3.37 LP3.38 LP3.39 LP3.40 LP3.41 LP3.42 LP3.43 LP3.44 LP3.45 LP3.46 LP3.47 LP3.48
Description Forms Stripping - Suspended slab 19' to 36' Forms Stripping - Suspended slab 36' up Plywood Partition Ceiling Joist Ceiling plywood board Partition Frame work Partition plywood board Floor framing T & G Flooring Truss Fabrication Truss Installation Purlins Installation Facia Board Installation Jamb Installation Wooden Flush Door Installation Wooden panel Door Installation Lockset Installation for Wooden Door Closer Installation for Wooden Door Stopper Installation for Wooden Door Fabrication of plywood cabinet Fabrication & installation of plywood capping Installation of cabinet door hinges Installation of cabinet door piano hinges Installation of cabinet handle Installation of cabinet door catches Installation & alignment of Wooden Baseboard Installation & alignment of Wooden Cornice Installation of wooden hand railings Fabrication of Wooden Flush Door Planing of rough lumber (No alignment) Planing of rough lumber (including alignment) SPECIAL WORK ITEMS PAVEMENT WORKS
LP4.1 LP4.2 LP4.3 LP4.4
Asphalt Pavement Cutting Concrete Pavement Cutting Sealant Application Broom Finishing STEEL WELDING & CUTTING
LP5.1 LP5.2
Welding t=18 Welding t=16
2 2 2 2 2 2 2 2 2 2 4 2 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
- Carpenter - Carpenter - Carpenter - Carpenter - Carpenter - Carpenter - Carpenter - Carpenter - Carpenter - Carpenter - Carpenter - Carpenter - Carpenter - Carpenter - Carpenter - Carpenter - Carpenter - Carpenter - Carpenter - Carpenter - Carpenter - Carpenter - Carpenter - Carpenter - Carpenter - Carpenter - Carpenter - Carpenter - Carpenter - Carpenter - Carpenter
LABOR PRODUCTIVITY Code LP5.3 LP5.4 LP5.5 LP5.6 LP5.7 LP5.8 LP5.9 LP5.10 LP5.11 LP5.12 LP5.13 LP5.14
Description Welding t=14 Welding t=12 Welding t=10. Welding t=8 Welding t=6 Cutting t=18 Cutting t=16 Cutting t=14 Cutting t=12 Cutting t=10 Cutting t=8 Cutting t=6 PILING WORKS
LP6.1
Sheet Pile Cutting PIPE FITTING
LP7.1 LP7.2 LP7.3 LP7.4 LP7.5 LP7.6 LP7.7 LP7.8
Pipe Fitting 300mm Pipe Fitting 400mm Pipe Fitting 500mm Pipe Fitting 600mm Pipe Fitting 800mm Pipe Fitting 900mm Pipe Fitting 1050mm Pipe Fitting 1200mm MISCELLANEOUS STEEL WORKS
LP8.1
Ladder Rung Installation MISCELLANEOUS CONCRETING RELATED WORKS
LP9.1 LP9.2 LP9.3 LP9.4 LP9.5 LP9.6
Sleeve Mortar Concrete Chipping Concrete Curing Waterstop Installation Polyethelene Laying Joint Filler Installation MISCELLANEOUS EXCAVATION PROTECTION WORKS
LP10.1
Sandbagging
LABOR PRODUCTIVITY Code
Description MISCELLANEOUS SITE WORKS
LP11.1 SCAFFOLDING WORKS LP12.1 LP12.2 LP12.3 LP12.4
Set/Dismantle of Scaffoldings (1-3 Layers) Set/Dismantle of Scaffoldings (4-6 Layers) Set/Dismantle of Scaffoldings (7-9 Layers) Set/Dismantle of Scaffoldings (10-15 Layers) MISCELLANEOUS RAIL WORKS
LP13.1
Sleepers Installation
0
Productivity
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Laborer Laborer Laborer Laborer Laborer Laborer Laborer Laborer Laborer Laborer Laborer Laborer Laborer Laborer Laborer Laborer Laborer Laborer Laborer Laborer Laborer Laborer Laborer Laborer Laborer Laborer
4 Laborer 4 Laborer
2 Laborer
Productivity
Manhrs Capacity
176.00 160.00 144.00 144.00 128.00 128.00
kgs/day kgs/day kgs/day kgs/day kgs/day kgs/day
22.00 20.00 18.00 18.00 16.00 16.00
kgs/hr kgs/hr kgs/hr kgs/hr kgs/hr kgs/hr
0.045 0.050 0.056 0.056 0.063 0.063
mhr/kgs mhr/kgs mhr/kgs mhr/kgs mhr/kgs mhr/kgs
1.30 1.08 15.63 18.75 0.90 1.20 1.50 4.00 4.00 1.00 6.00 0.46 0.38 0.40 0.50 0.40 4.00 5.25 4.50 3.75 3.00 2.66 2.61 2.58 2.58 2.50 3.21 3.21 0.27 1.00 1.00 1.00 1.00 26.00
cu.m./hr cu.m./hr pcs/hr pcs/hr sq.m./hr l.m./hr l.m./hr sq.m./hr sq.m./hr sq.m./hr sq.m./hr sq.m./hr sq.m./hr sq.m./hr sq.m./hr sq.m./hr l.m./hr sq.m./day sq.m./day sq.m./day cu.m./day cu.m./day cu.m./day cu.m./day cu.m./day cu.m./day cu.m./day cu.m./day cu.m./hr cu.m./hr cu.m./hr set/day set/day pcs/day
1.30 1.08 1.25 1.50 0.90 1.20 1.50 4.00 4.00 1.00 6.00 0.46 0.38 0.40 0.50 0.40 4.00 0.66 0.56 0.47 0.38 0.33 0.33 0.32 0.32 0.31 0.40 0.35 0.27 1.00 1.00 1.00 1.00 3.25
cu.m./hr cu.m./hr sm/hr sm/hr sq.m./hr l.m./hr l.m./hr sq.m./hr sq.m./hr sq.m./hr sq.m./hr sq.m./hr sq.m./hr sq.m./hr sq.m./hr sq.m./hr l.m./hr sq.m./hr sq.m./hr sq.m./hr cu.m./hr cu.m./hr cu.m./hr cu.m./hr cu.m./hr cu.m./hr cu.m./hr cu.m./hr cu.m./hr cu.m./hr cu.m./hr set/hr set/hr pcs/hr
0.772 0.926 0.800 0.667 1.111 0.833 0.667 0.250 0.250 1.000 0.167 2.174 2.632 2.500 2.000 2.500 0.250 1.524 1.778 2.133 2.667 3.008 3.065 3.101 3.101 3.200 2.492 2.857 3.750 1.000 1.000 1.000 1.000 0.308
mhr/cu.m. mhr/cu.m. mhr/pc mhr/pc mhr/sq.m. mhr/l.m. mhr/l.m. mhr/sq.m. mhr/sq.m. mhr/sq.m. mhr/sq.m. mhr/sq.m. mhr/sq.m. mhr/sq.m. mhr/sq.m. mhr/sq.m. mhr/l.m. mhr/sq.m. mhr/sq.m. mhr/sq.m. mhr/cu.m. mhr/cu.m. mhr/cu.m. mhr/cu.m. mhr/cu.m. mhr/cu.m. mhr/cu.m. mhr/cu.m. mhr/cu.m. mhr/cu.m. mhr/cu.m. mhr/pc mhr/pc mhr/pc.
2 2 3 3 3 4 4 4 5 5 5 6 1 1 2 2 2 2 2 2 2 2 2 2 2
Laborer Laborer Laborer Laborer Laborer Laborer Laborer Laborer Laborer Laborer Laborer Laborer Laborer Laborer Laborer Laborer Laborer Laborer Laborer Laborer Laborer Laborer Laborer Laborer Laborer
Productivity
Productivity
Manhrs Capacity
24.00 22.00 20.00 18.00 16.00 14.00 12.00 10.00 8.00 6.00 4.00 2.00 25.00 23.00 21.00 19.00 17.00 15.00 13.00 11.00 9.00 7.00 5.00 3.00 1.00
pcs/day pcs/day pcs/day pcs/day pcs/day pcs/day pcs/day pcs/day pcs/day pcs/day pcs/day pcs/day pcs/day pcs/day pcs/day pcs/day pcs/day pcs/day pcs/day pcs/day pcs/day pcs/day pcs/day pcs/day pcs/day
3.00 2.75 2.50 2.25 2.00 1.75 1.50 1.25 1.00 0.75 0.50 0.25 3.13 2.88 2.63 2.38 2.13 1.88 1.63 1.38 1.13 0.88 0.63 0.38 0.13
pcs/hr pcs/hr pcs/hr pcs/hr pcs/hr pcs/hr pcs/hr pcs/hr pcs/hr pcs/hr pcs/hr pcs/hr pcs/hr pcs/hr pcs/hr pcs/hr pcs/hr pcs/hr pcs/hr pcs/hr pcs/hr pcs/hr pcs/hr pcs/hr pcs/hr
0.333 0.364 0.400 0.444 0.500 0.571 0.667 0.800 1.000 1.333 2.000 4.000 0.320 0.348 0.381 0.421 0.471 0.533 0.615 0.727 0.889 1.143 1.600 2.667 8.000
mhr/pc. mhr/pc. mhr/pc. mhr/pc. mhr/pc. mhr/pc. mhr/pc. mhr/pc. mhr/pc. mhr/pc. mhr/pc. mhr/pc. mhr/pc. mhr/pc. mhr/pc. mhr/pc. mhr/pc. mhr/pc. mhr/pc. mhr/pc. mhr/pc. mhr/pc. mhr/pc. mhr/pc. mhr/pc.
32.00 1.50 1.50 1.00 0.85 0.65 0.85 1.20 0.80 0.60 0.50 8.00 1.55 1.95 2.35 1.50 3.60
bd.ft. / hr sq.m. / hr sq.m. / hr sq.m. / hr sq.m. / hr sq.m. / hr sq.m. / hr sq.m. / hr sq.m. / hr sq.m. / hr sq.m. / hr sq.m. / hr sq.m. / hr sq.m. / hr sq.m. / hr sq.m. / hr sq.m. / hr
32.00 1.50 1.50 1.00 0.85 0.65 0.85 1.20 0.80 0.60 0.50 8.00 1.55 1.95 2.35 1.50 3.60
bd.ft. / hr sq.m. / hr sq.m. / hr sq.m. / hr sq.m. / hr sq.m. / hr sq.m. / hr sq.m. / hr sq.m. / hr sq.m. / hr sq.m. / hr sq.m. / hr sq.m. / hr sq.m. / hr sq.m. / hr sq.m. / hr sq.m. / hr
0.031 0.667 0.667 1.000 1.176 1.538 1.176 0.833 1.250 1.667 2.000 0.125 0.645 0.513 0.426 0.667 0.278
mhr/bd.ft. mhr/sq.m. mhr/sq.m. mhr/sq.m. mhr/sq.m. mhr/sq.m. mhr/sq.m. mhr/sq.m. mhr/sq.m. mhr/sq.m. mhr/sq.m. mhr/sq.m. mhr/sq.m. mhr/sq.m. mhr/sq.m. mhr/sq.m. mhr/sq.m.
Productivity 2.40 1.85 0.99 5.87 1.49 7.50 1.98 4.13 14.00 5.75 5.00 2.29 4.38 5.33 0.33 0.25 0.50 0.50 1.00 0.50 2.50 2.00 1.50 3.00 3.00 2.50 2.00 1.00 0.25 120.00 48.00
sq.m. / hr sq.m. / hr sq.m. / hr bd.ft. / hr sq.m. / hr bd.ft. / hr sq.m. / hr bd.ft. / hr bd.ft. / hr bd.ft. / hr bd.ft. / hr m / hr bd.ft. / hr bd.ft. / hr pc. / hr pc. / hr pc. / hr pc. / hr pc. / hr sq.m. / hr l.m. / hr pc. / hr l.m. / hr pc. / hr pc. / hr l.m. / hr l.m. / hr l.m. / hr pc. / hr bd.ft. / hr bd.ft. / hr
Productivity 2.40 1.85 0.99 5.87 1.49 7.50 1.98 4.13 14.00 5.75 5.00 2.29 4.38 5.33 0.33 0.25 0.50 0.50 1.00 0.50 2.50 2.00 1.50 3.00 3.00 2.50 2.00 1.00 0.25 120.00 48.00
sq.m. / hr sq.m. / hr sq.m. / hr bd.ft. / hr sq.m. / hr bd.ft. / hr sq.m. / hr bd.ft. / hr bd.ft. / hr bd.ft. / hr bd.ft. / hr m / hr bd.ft. / hr bd.ft. / hr pc. / hr pc. / hr pc. / hr pc. / hr pc. / hr sq.m. / hr l.m. / hr pc. / hr l.m. / hr pc. / hr pc. / hr l.m. / hr l.m. / hr l.m. / hr pc. / hr bd.ft. / hr bd.ft. / hr
20.00 10.00 15.00 20.00
l.m./hr. l.m./hr. l.m./hr. sq.m./hr.
#REF! #REF!
l.m./hr. l.m./hr.
Manhrs Capacity 0.417 0.541 1.009 0.170 0.672 0.133 0.504 0.242 0.071 0.174 0.200 0.437 0.228 0.188 3.000 4.000 2.000 2.000 1.000 2.000 0.400 0.500 0.667 0.333 0.333 0.400 0.500 1.000 4.000 0.008 0.021
mhr/sq.m. mhr/sq.m. mhr/sq.m. mhr/bd.ft. mhr/sq.m. mhr/bd.ft. mhr/sq.m. mhr/bd.ft. mhr/bd.ft. mhr/bd.ft. mhr/bd.ft. mhr/m mhr/bd.ft. mhr/bd.ft. mhr/pc. mhr/pc. mhr/pc. mhr/pc. mhr/pc. mhr/sq.m. mhr/l.m. mhr/pc. mhr/l.m. mhr/pc. mhr/pc. mhr/l.m. mhr/l.m. mhr/l.m. mhr/pc. mhr/bd.ft. mhr/bd.ft.
Productivity
Productivity #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
l.m./hr. l.m./hr. l.m./hr. l.m./hr. l.m./hr. l.m./hr. l.m./hr. l.m./hr. l.m./hr. l.m./hr. l.m./hr. l.m./hr.
20.00
pc./hr
0.50 0.45 0.40 0.35 0.30 0.25 0.20 0.15
joint/hr joint/hr joint/hr joint/hr joint/hr joint/hr joint/hr joint/hr
10.00
each/hr
0.48 0.03 0.45 15.00 240.00 5.76
l.m./hr. c.m./hr. c.m./hr. l.m./hr. sq.m./hr sq.m./hr
3.24
c.m./hr.
Manhrs Capacity
Productivity
Productivity
4.00 3.00 2.00 1.00
sets/hr sets/hr sets/hr sets/hr
0.10
c.m./hr.
Manhrs Capacity
SSS MONTHLY CONTRIBUTION SCHEDULE Range Monthly EMPLOYER - EMPLOYEE of Salary SOCIAL SECURITY EC TOTAL CONTRIBUTIO Compensation Credit ER EE Total ER ER 1,000.00 1,249.99 1,000.00 70.70 33.30 104.00 10.00 80.70 1,250.00 1,749.99 1,500.00 106.00 50.00 156.00 10.00 116.00 1,750.00 2,249.99 2,000.00 141.30 66.70 208.00 10.00 151.30 2,250.00 2,749.99 2,500.00 176.70 83.30 260.00 10.00 186.70 2,750.00 3,249.99 3,000.00 212.00 100.00 312.00 10.00 222.00 3,250.00 3,749.99 3,500.00 247.30 116.70 364.00 10.00 257.30 3,750.00 4,249.99 4,000.00 282.70 133.30 416.00 10.00 292.70 4,250.00 4,749.99 4,500.00 318.00 150.00 468.00 10.00 328.00 4,750.00 5,249.99 5,000.00 353.40 166.70 520.10 10.00 363.40 5,250.00 5,749.99 5,500.00 388.70 183.30 572.00 10.00 398.70 5,750.00 6,249.99 6,000.00 424.00 200.00 624.00 10.00 434.00 6,250.00 6,749.99 6,500.00 459.40 216.60 676.00 10.00 469.40 6,750.00 7,249.99 7,000.00 494.70 233.30 728.00 10.00 504.70 7,250.00 7,749.99 7,500.00 530.00 250.00 780.00 10.00 540.00 7,750.00 8,249.99 8,000.00 565.40 266.60 832.00 10.00 575.40 8,250.00 8,749.99 8,500.00 600.70 283.30 884.00 10.00 610.70 8,750.00 9,249.99 9,000.00 636.00 300.00 936.00 10.00 646.00 9,250.00 9,749.99 9,500.00 671.40 316.60 988.00 10.00 681.40 9,750.00 - 10,249.99 10,000.00 706.70 333.30 1,040.00 10.00 716.70 10,250.00 - 10,749.99 10,500.00 742.00 350.00 1,092.00 10.00 752.00 10,750.00 - 11,249.99 11,000.00 777.40 366.60 1,144.00 10.00 787.40 11,250.00 - 11,749.99 11,500.00 812.70 383.30 1,196.00 10.00 822.70 11,750.00 - 12,249.99 12,000.00 848.00 400.00 1,248.00 10.00 858.00 12,250.00 - 12,749.99 12,500.00 883.40 416.60 1,300.00 10.00 893.40 12,750.00 - 13,249.99 13,000.00 918.70 433.30 1,352.00 10.00 928.70 13,250.00 - 13,749.99 13,500.00 954.00 450.00 1,404.00 10.00 964.00 13,750.00 - 14,249.99 14,000.00 989.40 466.60 1,456.00 10.00 999.40 14,250.00 - 14,749.99 14,500.00 1,024.70 483.30 1,508.00 10.00 1,034.70 14,750.00 over 15,000.00 1,060.10 500.00 1,560.10 30.00 1,090.10 Note: Effective rates starting January 1, 2007
MPLOYEE TOTAL CONTRIBUTION EE Total 33.30 114.00 50.00 166.00 66.70 218.00 83.30 270.00 100.00 322.00 116.70 374.00 133.30 426.00 150.00 478.00 166.70 530.10 183.30 582.00 200.00 634.00 216.60 686.00 233.30 738.00 250.00 790.00 266.60 842.00 283.30 894.00 300.00 946.00 316.60 998.00 333.30 1,050.00 350.00 1,102.00 366.60 1,154.00 383.30 1,206.00 400.00 1,258.00 416.60 1,310.00 433.30 1,362.00 450.00 1,414.00 466.60 1,466.00 483.30 1,518.00 500.00 1,590.10
PHILHEALTH MONTHLY CONTRIBUTION SCHEDULE Range of Monthly Contribution Compensation Salary Base x ER x EE 4,999.99 - below 4,000.00 50% 50.00 50% 50.00 5,000.00 5,999.99 5,000.00 50% 62.50 50% 62.50 6,000.00 6,999.99 6,000.00 50% 75.00 50% 75.00 7,000.00 7,999.99 7,000.00 50% 87.50 50% 87.50 8,000.00 8,999.99 8,000.00 50% 100.00 50% 100.00 9,000.00 9,999.99 9,000.00 50% 112.50 50% 112.50 10,000.00 - 10,999.99 10,000.00 50% 125.00 50% 125.00 11,000.00 - 11,999.99 11,000.00 50% 137.50 50% 137.50 12,000.00 - 12,999.99 12,000.00 50% 150.00 50% 150.00 13,000.00 - 13,999.99 13,000.00 50% 162.50 50% 162.50 14,000.00 - 14,999.99 14,000.00 50% 175.00 50% 175.00 15,000.00 - 15,999.99 15,000.00 50% 187.50 50% 187.50 16,000.00 - 16,999.99 16,000.00 50% 200.00 50% 200.00 17,000.00 - 17,999.99 17,000.00 50% 212.50 50% 212.50 18,000.00 - 18,999.99 18,000.00 50% 225.00 50% 225.00 19,000.00 - 19,999.99 19,000.00 50% 237.50 50% 237.50 20,000.00 - 20,999.99 20,000.00 50% 250.00 50% 250.00 21,000.00 - 21,999.99 21,000.00 50% 262.50 50% 262.50 22,000.00 - 22,999.99 22,000.00 50% 275.00 50% 275.00 23,000.00 - 23,999.99 23,000.00 50% 287.50 50% 287.50 24,000.00 - 24,999.99 24,000.00 50% 300.00 50% 300.00 25,000.00 - 25,999.99 25,000.00 50% 312.50 50% 312.50 26,000.00 - 26,999.99 26,000.00 50% 325.00 50% 325.00 27,000.00 - 27,999.99 27,000.00 50% 337.50 50% 337.50 28,000.00 - 28,999.99 28,000.00 50% 350.00 50% 350.00 29,000.00 - 29,999.99 29,000.00 50% 362.50 50% 362.50 30,000.00 - up 30,000.00 50% 375.00 50% 375.00 Note: Effective rates starting January 1, 2007
Total 100.00 125.00 150.00 175.00 200.00 225.00 250.00 275.00 300.00 325.00 350.00 375.00 400.00 425.00 450.00 475.00 500.00 525.00 550.00 575.00 600.00 625.00 650.00 675.00 700.00 725.00 750.00
PHILHEALTH MONTHLY CONTRIBUTION SCHEDULE Range of Monthly Contribution Compensation Salary Base Employer Employee 4,000.00 - below 4,000.00 2% 100.00 2% 100.00 4,001.00 5,000.00 5,000.00 2% 100.00 2% 100.00 5,001.00 6,000.00 6,000.00 2% 120.00 2% 120.00 6,001.00 7,000.00 7,000.00 2% 140.00 2% 140.00 7,001.00 8,000.00 8,000.00 2% 160.00 2% 160.00 8,001.00 9,000.00 9,000.00 2% 180.00 2% 180.00 9,001.00 - 10,000.00 10,000.00 2% 200.00 2% 200.00 10,001.00 - 11,000.00 11,000.00 2% 220.00 2% 220.00 11,001.00 - 12,000.00 12,000.00 2% 240.00 2% 240.00 12,001.00 - 13,000.00 13,000.00 2% 260.00 2% 260.00 13,001.00 - 14,000.00 14,000.00 2% 280.00 2% 280.00 14,001.00 - 15,000.00 15,000.00 2% 300.00 2% 300.00 15,001.00 - 16,000.00 16,000.00 2% 320.00 2% 320.00 16,001.00 - 17,000.00 17,000.00 2% 340.00 2% 340.00 17,001.00 - 18,000.00 18,000.00 2% 360.00 2% 360.00 18,001.00 - 19,000.00 19,000.00 2% 380.00 2% 380.00 19,001.00 - 20,000.00 20,000.00 2% 400.00 2% 400.00 20,001.00 - 21,000.00 21,000.00 2% 420.00 2% 420.00 21,001.00 - 22,000.00 22,000.00 2% 440.00 2% 440.00 22,001.00 - 23,000.00 23,000.00 2% 460.00 2% 460.00 23,001.00 - 24,000.00 24,000.00 2% 480.00 2% 480.00 24,001.00 - 25,000.00 25,000.00 2% 500.00 2% 500.00 25,001.00 - 26,000.00 26,000.00 2% 520.00 2% 520.00 26,001.00 - 27,000.00 27,000.00 2% 540.00 2% 540.00 27,001.00 - 28,000.00 28,000.00 2% 560.00 2% 560.00 28,001.00 - 29,000.00 29,000.00 2% 580.00 2% 580.00 29,001.00 - 30,000.00 30,000.00 2% 600.00 2% 600.00 Note: Effective rates starting January 1, 2007
Total 200.00 200.00 240.00 280.00 320.00 360.00 400.00 440.00 480.00 520.00 560.00 600.00 640.00 680.00 720.00 760.00 800.00 840.00 880.00 920.00 960.00 1,000.00 1,040.00 1,080.00 1,120.00 1,160.00 1,200.00