48 0 305KB
Taylor Safety Engineering
The QRAQ Project Volume 26 Systematic ALARP Analysis Version 1 Issue 2 January 2017
J.R.Taylor
QRAQ 24 Systematic ALARP Analysis
© J.R.Taylor 2014
i
QRAQ 24 Systematic ALARP Analysis
The QRAQ project Quality of Risk Assessment for Process Plant Lessons Learned Analysis ITSA Prunusvej 39, 3450 Allerød, Denmark Issue Date V1I1 Feb 2014 V1I2 Jan 2017
© J.R.Taylor 2014
Author JRT JRT
Approval
Release
ii
QRAQ 24 Systematic ALARP Analysis
QRAQ publications 1. The QRAQ Project – Introduction 2. Quality and completeness of hazard identification 3. Consequence calculation models 4. Risk assessment frequency data 5. Risk analysis methodologies 6. Risk acceptance criteria 7. Ignition frequency 8. Jet fire models 9. Fire water monitors as a risk reduction measure 10. Boilover and fire induced tank explosion 11. Self evacuation as a risk reduction measure 12. Major hazards scenarios - Model validation against actual accidents 13. In preparation 14. Gas impoundment 15. Domino effects and escalation 16. Momentum jets 17. Fire and Gas Detection Mapping 18. Marine risk 19. Hydrogen Sulphide Release Modelling and Incidents 20. Human error in process plant operations and maintenance 21. SIL assessment using LOPA 22. Assessment of simultaneous operations 23. In preparation 24. Systematic ALARP Analysis 25. Safety Barrier and Bow Tie Diagrams 26. Lessons Learned Analysis 27. Closing the Gaps in Risk Analysis 28. Plant layout risk analysis 29. QRA for instrumented safety systems 30. Emergency Planning for Oil and Gas Installations 31. Cost benefit assessment of Risk Analysis 32. A catalogue of failure modes
© J.R.Taylor 2014
iii
QRAQ 24 Systematic ALARP Analysis
© J.R.Taylor 2014
iv
QRAQ 24 Systematic ALARP Analysis Preface This report is the 24th in the series of reports covering various aspects of the quality of process risk assessment studies. ALARP assessment and ALARP demonstration have become an important part of process plant risk assessment, but the analyses performed vary greatly in quality. This report is based on results for about 30 such analyses for major process plant, and is intended to provide a reproducible approach to such assessments J.R.Taylor Abu Dhabi 2014
© J.R.Taylor 2014
v
QRAQ 24 Systematic ALARP Analysis
Updating history
Issue
Date
Initial version
Dec 2012
Issue 2
Jan 2017
© J.R.Taylor 2014
Affected
Change Initial release
Table 3.1
Improved data for costing
vi
QRAQ 24 Systematic ALARP Analysis
© J.R.Taylor 2014
vii
QRAQ 24 Systematic ALARP Analysis Contents 1. 2.
Introduction ........................................................................................................................1 Examples ............................................................................................................................3 2.1 An oil/gas separation unit jet fire induced vessel explosion – back-fitting mitigation measures .................................................................................................................................3 2.2 Example - Gasoline pipeline jet fire accident prevention ...........................................6 2.3 Lessons from the examples .........................................................................................8 3. Systematic ALARP Analysis..............................................................................................9
© J.R.Taylor 2014
viii
QRAQ 24 Systematic ALARP Analysis
© J.R.Taylor 2014
ix
QRAQ 24 Systematic ALARP Analysis
1. Introduction ALARP assessment and ALARP demonstration have become an important part of process plant risk assessment, but the analyses performed vary greatly in quality. This report is based on results for about 30 such analyses for major process plant, and is intended to provide a reproducible approach to such assessments. Risk levels are now routinely assessed according to risk criteria such as those given in R2P2 or ADNOC COP V5-06. Quantitative ALARP analysis is carried out as follows: 1. Hazard scenarios giving risk in the Medium zone, between acceptable and unacceptable are identified, on an area by area basis. 2. All credible risk reduction measures are identified for each of the hazards identified in step 1. The criterion for selection of measures at this stage is that they are recommended in industry guidelines. 3. Where a measure is already incorporated into the design, this is noted and no further analysis is performed for this measure, except that it is taken into account in the risk assessment. 4. New measures are selected from a systematic check list, which is intended to cover all loss prevention measures currently available and with demonstrated efficacy 5. The practicality of each new measure is measured. Measures may be impractical for example due to: a. Having no risk reduction effect in the actual case b. Be unreliable in the actual environment c. There being insufficient spaces, or difficulties of placement in the actual plant (applies for plant already constructed, although cost benefit analysis may be required taking into account backfitting engineering costs and loss of production while modifications are made) d. Interference with operations or operational safety e. Possible hazards arising from the risk reduction measures itself (e.g. steam curtains) f. Other reasons 6. For the measures considered practical in an engineering sense, the following are calculated: a. The probabilities of loss of life (PLL) for the hazards of concern (i.e. the ones for which risk is reduced by the measure) prior to risk reduction. b. The asset risk prior to risk reduction c. The environmental risk prior to risk reduction d. The consequence reduction factor for each measure for human life, asset and environmental ( a factor of 1.0 indicates no risk reduction)
© J.R.Taylor 2014
1
QRAQ 24 Systematic ALARP Analysis e. The frequency reduction factor for each measure for human life, asset and environmental f. The residual risk for human life, asset and environment once the measures are implemented. g. The maximum justifiable investment (MJS) for the risk reduction measure, calculated as the reduction in annual loss multiplied by number of years over which the investment in risk reduction is capitalized. For statistical loss of life, the valuations specified in standards and guidelines are used h. The cost of each risk reduction measure is estimated. (This can be done using generic costing data () or using data developed for design costing. i. The implied cost of averting a fatality (ICAF) is calculated. j. Values of ICAF which are above the guideline levels are considered disproportionate.
© J.R.Taylor 2014
2
QRAQ 24 Systematic ALARP Analysis
2. Examples The following examples are based on actual cases from oil and gas industry applications.
2.1 An oil/gas separation unit jet fire induced vessel explosion – back-fitting mitigation measures The first example considered is for a separator unit in which gas is taken from a crude oil and gas mixture. The risk reduction potential for this project is restricted by the fact that the units are mainly gas separation and compression facilities handing hydrocarbon gas. If a release of gas occurs through a large hole, a fairly large inventory will be released, irrespective of any shutdown etc. Also in case of large or full bore releases, the release will be very rapid, forming fully developed gas jets in a few seconds. Shutdown by ESD will have little effect on human risk in the immediate area, since ESD takes about 2 minutes for detection, reaction and closure. Most lethal effects occur in a shorter period than this. However if ESD valve close, the pressure in the separator vessels will begin to drop as soon as closure is achieved. For this example, pressure has been calculated to drop by half in under 4 minutes due to discharge through the release hole. This is sufficiently fast to prevent excessive jet fire heating of neighbouring vessels, Long period releases from small and medium size holes can be subject to risk reduction by: 1. Detecting the gas release or fire 2. Shutting down and depressurising 3. Setting up a cordon excluding all persons, vehicles etc. which could serve as an ignition source 4. Possibly, using water spray from fire water monitors to help suppress release and to lower the potential for ignition (Fire water monitors have little effectiveness in suppressing H2S). 5. Self evacuation and the use of personal escape masks can significantly reduce risk for those employees not immediately affected by very high concentrations. The estimated success rate in the case where all carry full face masks, or escape masks and goggles, is conservatively set to 95% (Ref 13: Self Evacuation as a risk reduction measure, QRAQ report): The processing facility is designed in order to minimize the likelihood of buildings being subjected to flammable gas cloud in case of a gas release in the processing area. Operator amenity rooms and substation are pressurized and gas tight buildings to minimize ingress of gas in the building. As per dispersion modelling results, these buildings are not expected to be subjected to flammable gas concentrations even in case of large releases in the plant.
© J.R.Taylor 2014
3
QRAQ 24 Systematic ALARP Analysis As the plant is relative open and uncongested, high explosion overpressures are not expected to be generated. The amenity room and substation building are designed as blast resilient buildings. 2.1.1 Risk reduction measures for jet fire induced vessel explosion A range of risk reduction measures were considered for this scenario. Some of these may be implemented in the design. Maximum Justifiable Investment (MJI) for assets and personnel is calculated. The expected value of risk reduction in value of risk per year for personnel is calculated: MJIhuman
1 × 10-3 × 0.5 × $ 107 ×8 ×3 $120,000
=
=
Per year, frequency of release 50% risk reduction Maximum ICAF value Amortisation period selected by policy Persons
Here, the maximum reasonable ICAF value of $10 million is used. 50% risk reduction is calculated, and accounts for the fact that some fatalities occur immediately in the case of accidents, and are not therefore subject to risk reduction Jet fire damage is the largest contribution for asset risk. MJI for business interruption risk is significant and is calculated as: MJIBI
=
2×10-3 × 0.2 ×1 ×8 × 500,000,000
=
Frequency per year from LSAR map Approximate probability of damage (impingement probability) Year, expected downtime Amortisation period selected by policy $ Value of Production Per Year
Approx. US $ 1,600,000
Based on the MJS the following risk reduction measures are discussed. 2.1.2 Prevention of Jet fire induced explosion Jet fire is one of the most probable causes of serious accident consequences in a oil/gas separation plant. The possibilities exist for jet fires to impinge on other vessels and cause these to rupture. The active fire protection systems which may be installed:
© J.R.Taylor 2014
4
QRAQ 24 Systematic ALARP Analysis • • • •
Firewater system with deluge spray system Fire hydrants and monitors Inert gas extinguishing system for protection of operator rooms, local substations Portable firefighting equipment and emergency response personel.
The time taken for a jet fire to cause vessel rupture is calculated as 4 to 10 minutes. If operators in the area are not killed or seriously injured there is ample time for the operator to evacuate to a safe distance provided that he is trained to do so. The fact that the operator can evacuate when there is a possibility of fire induced explosion means that there is no human risk benefit from the protection measure. The cost of providing fire water monitors for the installation is estimated to be $10,000 per separator vessel, that is $40,000 It is concluded that fire water monitor provision for the separators is cost beneficial. This should be sufficient to conclude that no further protection is necessary, provided that the fixed fire water monitors can be put into operation and aimed within about 4 minutes (Ref 14: Birk). 2.1.3 Pre-aiming of fire water monitors Pre-aiming of fire water monitor is a zero cost measure. It is therefore recommended that fire water monitors should be pre aimed. The angle of attack for the fire monitor streams should be checked to ensure that the line of attack is not obstructed. Emergency plans emphasizing the need for rapid response are also recommended. 2.1.4 Provision of deluge system A deluge system is often fitted to separators. However a deluge system is unable to provide complete protection against jet fire (the jet fire blows the water away). However it has been shown in experiments that a deluge system can increase the time for fire induced rupture to occur. This would allow more time for fire response and for depressurisation. The value of the deluge system is therefore only realised if there is also a good firefighting service, an ability to fight jet fires despite high heat radiation, which requires powerful portable fire water monitors, or if there is a good depressurisation system with pressure reduction to a low level within 10 minutes. 2.1.5 Rapid depressurisation For the actual case, rapid depressurisation was found to be not ALARP, since it would require a very large increase in flare and flare piping size, costing several million dollars. Worse, back fitting would require shutdown for the unit for some tens of days, resulting in a very large business interruption cost. 2.1.6 Firefighting Provision of rapid response firefighting was found to be practical, but would require a fire tender with a large water capacity and a large mounted fire water monitor. The cost of this was found to be $2.2 million, and therefore not justifiable on an ALARP basis. However the
© J.R.Taylor 2014
5
QRAQ 24 Systematic ALARP Analysis investment could be determined to be beneficial if it could reduce risk in a wider range of scenarios. This requires a plant wide analysis.
2.2 Example - Gasoline pipeline jet fire accident prevention A gasoline pipeline is to run close to a construction large worker construction camp, with about 5000 workers living in container type caravans. The accident frequency level for the worker group is calculated by standard QRA techniques to be about 5*10-5 per year, for a number of fatalities calculated to be about 800 using standard QRA techniques, based on simple affected area and assuming a uniform distribution of persons at the construction camp. A more realistic estimate is about 200 persons, taking self-evacuation into account, based on incident records. In either case, the risk levels are considered to be unacceptable, based on national risk criteria. The risk is to be reduced. The baseline ICAF value is calculated to be ICAFbaseline
= 800 ×5×10-5 × $10,000,000 × 8 = $ 3,200,000
Where 8 is the amortisation factor to convert loss per year into a capitalised value. It corresponds to a yearly return on investment of about 10%. Note that the construction camp is semi-permanent. The possible risk reduction methods studied are: • • • •
Provision of a leak detection and automatic shutdown system for the gasoline pumps Provision of a larger corrosion allowance for the pipeline Fencing of the pipeline right of way to reduce the probability of third party interference Provision of a fire wall or a berm between the pipeline and the construction camp
2.2.1 Automatic shutdown system The automatic shutdown system can be implemented very simply in an ordinary DCS or a safety computer. A simple temperature compensated mass balance detection system is sufficient for the purpose, since small leaks are not a large threat to the construction camp. The cost involved may be for an additional safety computer, two mass flow meters, and temperature sensors, with a total cost of about $40,000. (This assumes that the DCS communications system will be used to transmit the signals). This cost would certainly be justified, provided that the safety measure is effective. The response time of the safety system depends on the time for the pressure wave due to the pipe leak to reach the end of the pipeline (For the present case about 50 seconds) and the time for the pump to run down in speed and stop, about 90 seconds in this case. The response time could be shortened by fitting an ESD valve at the pump discharge, together with a minimum flow bypass valve back to the gasoline storage tank. The response time for ESD is estimated to be about 30 seconds in all.
© J.R.Taylor 2014
6
QRAQ 24 Systematic ALARP Analysis With an overall response time of about 2 minutes there is a possibility of significant fuel loss, and of a fire affecting part of the construction camp, but the possibility of a large flow through the camp is eliminated. The extent of the fire could be calculated by calculating the spread of a running pool. This requires more advanced modelling than is typical for QRA, but is quite feasible. The implementation described above could be made to satisfy a SIL 1 requirement, i.e. capable of reducing risk by a factor of 10. The risk reduction is far larger than the cost, and the residual average loss is reduced to $320,000. It would be possible to improve the reliability of the shutdown system to SIL2 level, by duplicating the instruments, or using SIL2 rated types, and providing a SIL2 rated communication. The cost of this is estimated to be much less than the residual average loss. Improvement of the reliability to a 2oo3 system might be preferred anyway, in order to reduce the probability of unwanted pipeline shyutdowns. 2.2.2 Provision of piping with a higher corrosion allowance One approach to prevention of release is to increase pipe thickness, by selecting a higher pipe schedule. Increasing the schedule from 40 to 80 for example, reduces the failure rate due to corrosion by a factor of about 12 (see QRAQ report 27), at a cost of about $30000 for one kilometre of pipe. This measure reduces risk only for corrosion related failures however, typically about 30 to 40% of the total failures. The cost is nevertheless significantly less than the benefit in risk reduction. AN INCREASED CORROSION ALLOWANCE WILL ONLY REDUCE RISK IF THE INSPECTION INTERVAL IS KEPT LOW. IF THE IMPROVED CORROSION RESISTANCE IS USED AS A REASON FOR REDUCING INSPECTION INTERVAL, THEN THERE WILL BE LESS OR NO RISK REDUCTION. 2.2.3 Provision of right of way fencing Provision of fencing for the right of way is feasible in the desert environment considered, and may be feasible for new pipelines in most places, with sufficient planning. For the half kilometer of pipeline concerned here, fencing is straightforward. The cost is about $50,000. This measure reduces the likelihood of third party interference with pipelines to nearly nothing, but interference by the company’s own contractors when installing other pipes is still possible. This measure reduces risk only for Third party interference related failures however, typically about 45% of the total failures. The cost is nevertheless significantly less than the benefit in risk reduction.
© J.R.Taylor 2014
7
QRAQ 24 Systematic ALARP Analysis 2.2.4 Provision of a berm protecting the camp from the pipeline A 3 m. high berm can be constructed at the actual cost at the location of about $100,000 (The price varies widely from location to location, depending on availability of materials and transport cost). Ideally, the risk reduction is 100%. The jet fire risk is reduced effectively to zero. This though requires CFD modelling to confirm. There is a possibility of mist and vapour from the release drifting over the berm, and then igniting, causing an explosion. This illustrates that a full range of scenarios needs to be considered when evaluating risk reduction measures. 2.2.5 Overall assessment for the scenario Overall, the provision of the berm provides inherent safety for the scenario. Automated shutdown though is preferred, because it reduces the explosion risk, as well as the jet fire risk. The increased pipeline schedule and fencing options may be preferred by the company because they also reduce business interruption risk as well as human risk. However, a much larger project is involved in this case, because it would probably make sense for the entire pipeline, not just for the section threatening the construction camp.
2.3 Lessons from the examples One of the lessons from the example is that ALARP analysis requires expertise in detailed scenario consequence analysis and loss prevention engineering, and in cost estimating. Standard cost estimating tables may be used for some solutions, but for others, local costs need to be taken into account. A second lesson is that scenario by scenario analysis alone may not produce a result which is ALARP. Some measures will be able to reduce risk for several scenarios. If such measures are considered, a plant wide analysis may be required. A third lesson is that ALARP assessment may require considerable effort, with careful assessment of all safety measures. A QRA is needed as a basis, but most regulatory QRA’s (COMAH type) will not be adequate for the detailed assessments. For example, impingement probabilities for jet fires, engulfment probabilities for pool fires, and smoke obscuration calculation for evacuation etc. are needed (see QRAQ 27 Living Risk Analysis). In example 2, a CFD calculation was needed to validate effectiveness for the berm. Overall, there is a considerable amount of work required in true cost benefit analysis. It will be noted that for each measure, there were several aspects to be taken into account in assessing the practicality, not just the hypothetical cost and benefit. Practicality and overall pros and cons need to be considered.
© J.R.Taylor 2014
8
QRAQ 24 Systematic ALARP Analysis
3. Systematic ALARP Analysis One of the main problems with carrying out ALARP assessment has been that the persons able to make the risk assessment are only rarely experienced loss prevention engineers, and even loss prevention engineers are rarely experienced in accident prevention and equipment integrity assessment. Risk reduction requires a multi-disciplinary effort. ALARP workshops have only recently been introduced, and are difficult because the calculations needed take too long to be usable in a workshop, using conventional risk assessment approaches. The workshops can provide risk reduction proposals, which can later be evaluated. One of the biggest problems with ALARP assessment at present is that it is not repeatable. If two teams or two consultants are assigned to make the assessment they will generally arrive at very different suggestions. A further problem is the underlying model in process plant QRA, which assumes that any accident results from a release, and that the release occurs at a random point in time, independent of the presence of persons. This ignores the fact that about 30% of accidents are caused by latent failures and latent design errors, and that these are often triggered by persons. It also ignores the fact that about 20% of accidents are caused by human error in the field. This problem will be addressed in a separate report. The approach taken here to ensure reproducibility of ALARP assessments is to provide an exhaustive list of risk reduction measures, along with: • • • • • •
Description of the applicability of the measures, according to scenario, equipment type and process fluid. Description of the features which can make the measures impractical. Description of limitations of the measures. Description of the way in which risk is reduced Approach to calculation of the risk reduction. Guidance on calculation of the cost
In use, the scenarios are identified and the measures which can be used to reduce risk are selected from the check list. The check list can be applied by an individual analyst, or can be used as an aid in an ALARP workshop. The check list is based on the risk reduction and ALARP assessment sections of 85 QRAs and safety cases, covering a wide range of plant types.
© J.R.Taylor 2014
9
QRAQ 24 Systematic ALARP Analysis
S.No.
1
Risk Reduction Measures
Layout spacing between equipments
2
Layout spacing between units
3
Layout spacing to CR, workshops, offices, dwellings
Equipment Applicability
All types with flammable content
All types with flammable content
All types
© J.R.Taylor 2014
Applicability for Assets and Business Interruption
Practicality Assessment
Effectiveness
JI Calculation
Cost calculation
Reference
All flammables
Has little impact on human risk, except perhaps by reducing the possibility of domino effects.
Will have some impact in reducing domino effects. Generally considered to have little impact because practical distances correspond to small releases only. See reference
Depends on availability of land/space. Otherwise easily applied.
Effectiveness depends on the range of jet fire, pool fire and explosions versus spacing distances
Full QRA with different layouts or sensitivity study for a range of items.
Site land value and additional piping
QRAQ 28
All flammables
Reduces risk to personnel in neighbouring units or trains to a limited extent. Practical distances have limited effe
Will have some impact in reducing domino effects. For effectiveness reference
Depends on availability of land/space. Otherwise easily applied.
Effectiveness depends on the range of jet fire, pool fire and explosions versus spacing distances
Full QRA with different layouts or sensitivity study for a range of items.
Site land value
QRAQ 28
All hazardous materials
This can in some cases completely eliminate risk, in otheres eliminates risk due to mall and medium releases
Depends on availability of land/space. Otherwise easily applied.
Effectiveness depends on the range of toxic plumes, jet fire, pool fire and explosions versus spacing distances
Full QRA with different locations of human groups is simplest.
Site land value may be an issue, often a no cost issue for green field sites.
QRAQ 28
Hazard applicability
Applicability Human Risk
1
QRAQ 24 Systematic ALARP Analysis S.No.
4
Risk Reduction Measures
Battery Limit ESD valves
Equipment Applicability
All equipment
© J.R.Taylor 2014
Hazard applicability
Applicability Human Risk
All hazardous fluids
Can limit the duration of a release. The inventory may be small enough to reduce gas plume volumes and release time and therefore toxic gas exposure time. Calculation is needed for exposure time versus escape time. In most cases the inventory will be too large to have much impact on human risk, because self evavuation typically take less than 2 minutes whereas even after ESD closure, releases will generally last longer than this.
Applicability for Assets and Business Interruption
Limits the duration of releases, and the pressure once the ESD valves are closed. This may be shorter than the jet fire damage time, in which case, jet fire risk will be reduced. Limits the amount of liquid release and therefore pool size.
Practicality Assessment
Battery limit ESD's will usually be practical
2
Effectiveness
Effectiveness of ESD depends on purpose. Seldom effective in reducing human risk from fire, unless trapped inventory is very small. Effective for human risk from toxics if inventory is limited, check the pressure fall over the person escape time. Effective in supporting fire fighters to prevent escalation
JI Calculation
Cost calculation
Reference
Full QRA with different layouts or sensitivity study for a range of items. QRA Pro calculates for bote ESD and no ESC
Cost of valve, installation and cabling. Small (2inch) valves about $400, 16 inc $8000, 46 inch $2.5 m!
QRAQ 29
QRAQ 24 Systematic ALARP Analysis S.No.
5
6
Risk Reduction Measures
Inventory isolation ESD valves
Pipeline sectioning ESD
Equipment Applicability
Storage vessels, tanks, columns
Pipelines
© J.R.Taylor 2014
Hazard applicability
All hazardous fluids
All hazardous fluids
Applicability Human Risk
Can limit the duration of a release. The inventory may be small enough to reduce gas plume volumes and release time and therefore toxic gas exposure time. Calculation is needed for exposure time versus escape time. Since most releases are from piping reduces the frequency of large releases, since most releases will be limited to piping inventory.
Rarely has an impact on human risk, because ESD times and inter valve inventory self relief or drain down times are much longer than self evacuation times.
Applicability for Assets and Business Interruption Limits the duration of releases, and the pressure once the ESD valves are closed. This may be shorter than the jet fire damage time, in which case, jet fire risk will be reduced. Limits the amount of liquid release and therefore pool size. Generally more effective than just battery limit ESD. When fitted at vessel outlets, reduces the initial amount prior to valve closure plus piping inventory, and large inventory release frequency to vesse failure frequency.
Reduces the inventory released from pipeline failures to that from the ESD shutdown time and section inventory. In this way, reduces the extent of consequences for liquid releases, and the duration for all releases.
Practicality Assessment
Practical if there is sufficient space to insert the valve. Sometimes you can achieve a good solution by replacing a block valve with an ESD valve, or even by placing an actuator on an existing block valve.
Pipeline sectioning ESD's are almost always practical for single phase pipelines. The can cause hammer problems for multiphase pipelines.
3
Effectiveness
Effectiveness of inventory isolation ESD is twofold - Limits amount of release to piping inventory plus release while ESD valves closing. - Limits large inventory relese frequency to the failure rate for the vessel. Effectiveness calculation requires both ESD and No ESD calculatio n to be calculated
It is necessary to calculate the trade off between reduced release inventory, versus the increase frequency of release from flanges
JI Calculation
Cost calculation
Reference
Compare limited release QRA with full inventory release QRA (In QRA Pro select ESD an No ESD calculations can compare results
Cost of valve, installation and cabling. Small (2inch) valves about $400, 16 inc $8000, 46 inch $2.5 m!
QRAQ 29
Compare limited release QRA with full inventory release QRA (In QRA Pro select ESD an No ESD calculations can compare results
Cost of valve, installation and cabling. Small (2inch) valves about $400, 16 inc $8000, 46 inch $2.5 m!
QRAQ 29
QRAQ 24 Systematic ALARP Analysis S.No.
7
8
Risk Reduction Measures
Blow Down
Flare system
Equipment Applicability
All pressurised process
All process and pipelines with flammable gas
© J.R.Taylor 2014
Hazard applicability
All gases
Flammable gas, in some cases ground flare for flammable liquids
Applicability Human Risk
No impact on human risk from initial accident, may reduce the likelihood or extent of escalation risk (see asset column)
No real impact on human safety, (except in cases where vents are used as an alternative, and the vents are a threat to human life or welfare).
Applicability for Assets and Business Interruption
Practicality Assessment
Reduces pressures over a 15 to 30 minute period, and can reduce the probability of escalation damage. For unignited releases, reduces the period for which potential for ignition exists.
Nearly always practical in main process plant. Can be problematic on small platforms because of the limitations on knock out capacity Due to long blowdown times the main value is in shortening fire fighting duration.
Allows blowdown and pressure relief of flammable material to proceed safely i.e is a necessary part of blowdown and relief.
Usually a necessary requirement. Costly in land. Reliability and liquid entry calculations needed.
4
Effectiveness
JI Calculation
Cost calculation
Calculate the difference in release rates for the blowdown versus no blowdown cases.
Calculate dynamic QRA, with blowdown option selected
Cost of blw down valves and flare. Blowdown is usually needed for maintenance though so usually no cost. Added capacity for rapid blow down is very expensive typically >$10 m.
Completely effective for overpressure protection within its capacity. Capacity may be for full fire engulfment, staggered relief, or may be very high for hex tube rupture
Not needed for full capacity. Determine probability of extended vessel engulfment for staggered relief
Cost of land plus flare system
Reference
QRAQ 24 Systematic ALARP Analysis S.No.
9
10
11
Risk Reduction Measures
Equipment Applicability
Flammable material drainage
All process and storage with flammable liquid
Drain fire seals
All process and storage with flammable liquid
Fire Detection
All process and storage
© J.R.Taylor 2014
Hazard applicability
Flammable liquids
Flammable liquids
Flammable fluids
Applicability for Assets and Business Interruption
Practicality Assessment
No effect on human risk except via limitation of domino effects
Reduces the possibility of flame spread and the probability of BLEVE or FIVE due to fire engulfment (pool fires)
Rarely any effect on human risk, except possibly from unexpected escalation.
Reduces the possibility of flame spread between fire zones, and therefore escalation potential.
Applicability Human Risk
Can provide good alarm for persons who cannot see the fire, improves self evacuation probability.
Provides ability to activate ESD and deluge if these are not automatic, call out emergency personnel.
Effectiveness
JI Calculation
Cost calculation
Reference
Generally a requirement.for new plants. High capacity non blocking types needed if there is a flammable oil or solvent scenario. Extremely difficult to back fit.
Capacity needs to be matched to fire water demand for largest fires.
Cost of escalation, domino effect calculation for pool fire only. (In Riskmap, input pool fires onle then do pool fire calculationn.
Civil engineering calculations
Process Safety Engineering Handbook.
Generally practical
Eliminates an escalation hazard which has caused may sever accidents. Need to be kept clear. Not practical in sanding conditions.
As above
Civil engineering calculations
Process Safety Engineering Handbook.
Effectiveness depends on coverage calculation
Comparative QRA with and without evacuation, fire fighting response. Fire and gas mapping for probability determination
Flame Detector: 3812 USD
QRAQ 17 Fire and Gas mapping
Always practical
5
QRAQ 24 Systematic ALARP Analysis S.No.
12
13
14
Risk Reduction Measures
Melting plugs
Melting links
Linear fire detectors (twin wire with melting insulaion)
Equipment Applicability
Especially at pumps, sometimes at skids
Especially at pumps, sometimes at skids
Tank rim seals, above small tanks, kettle reactors, contactors etc
© J.R.Taylor 2014
Hazard applicability
Flammable fluids, most effective for liquids
Applicability Human Risk
Very little impact, because if the fire is big enough to melt the plug it is big enough to see.
Flammable fluids, most effective for liquids
Very little impact, because if the fire is big enough to melt the plug it is big enough to see.
Flammable fluids, most effective for liquids
Very little impact, because if the fire is big enough to melt the detectors it is big enough to see. Effective in unmanned areas esp. at pumps.. Effective in floating roof tanks but has reliability systems
Applicability for Assets and Business Interruption
Practicality Assessment
Effectiveness
Good supplement to UV/IR or IR3 alarms where visibility is obscured
Quite practical, although tubing is a nuisance during maintenance
Quite effective when located at the most likely release points, not subject to obstruction, not subject to obstruction shadowing like optical detectors. Plugs need replacing at about 10 year intervals
Good supplement to UV/IR or IR3 alarms where visibility is obscured
Low reliability due to damage and bypassing when maintenance is carried out
Quite effective when located over the most likely release points, not subject to obstruction , not subject to obstruction shadowing like optical detectors..
Low reliability due to damage and to bypassing when maintenance is carried out
Quite effective when located over the most likely release points, not subject to obstruction shadowing like optical detectors. Plugs need replacing at about 10 year intervals
Good supplement to UV/IR or IR3 alarms where visibility is obscured
6
JI Calculation
Cost calculation
Reference
QRAQ 24 Systematic ALARP Analysis S.No.
15
16
17
Risk Reduction Measures
Gas Detection
Deluge
Sprinklers
Equipment Applicability
All process and storage
Pressure vessels, tanks, columns. Can be used on critical piping. Transformers
Buildinngs
© J.R.Taylor 2014
Hazard applicability
Flammable and toxic gas, volatile liquids
Applicability Human Risk
Can provide good alarm for persons who cannot see hear or smell the release, improves self evacuation probability.
Applicability for Assets and Business Interruption
Provides ability to activate ESD and deluge if these are not automatic, call out emergency personnel.
Flammable fluids, solids
Can provide protection for escape routes, see below
Provides protection for vessels subject to pool fire engulfment. Provides limited
Flammable fluids, structural fire hazards.
Little direct effect on human risk, but reduces risk by limiting fire spread.
Provide protection for buildings
Practicality Assessment
Effectiveness
JI Calculation
Cost calculation
Reference
Always practical
Effectiveness depends on coverage calculation. Limited number of suppliers for open path toxic gas. H2S can be detected by flammable gas detectors if the concentration is not too high
Compartive QRA with and without evacuation and emergency shutdown
Point Type Gas Detector: 2610 USD Open Path Detector: 9477 USD
QRAQ 17 Fire and Gas mapping
Fully effective against pool fire if well maintaine and there are no dry spots. Some value in delaying BLEVE for the case of jet fires
Comparative QRA with and without pool fires. Also dynamic QRA for jet fires
Generally practical if there is a clean water supple e.g. from a tank. Vulnerable to blockage by contamination when used with sea water, and with rust. Need frequent testing Cannot be used where there is electrinic or electrical equipment, such as control rooms, communications rooms and cable spreading rooms
7
Generally effective if designed correctly,
Process Safety Engineering Handbook.
Process Safety Engineering Handbook.
QRAQ 24 Systematic ALARP Analysis S.No.
18
19
20
Risk Reduction Measures
Equipment Applicability
Applicability Human Risk
A major part of plant asset protection
Usually very practical. Some measurements may be difficult such as level in a stirred reactor.
One of the major protection devices for batch processes, with direct impact on many scenario types
Generally very practical, especially if fail safe. Need to be designed to prevent unautorised bypass.
Prevents injury and fatality due to overpressure explosion
Generally required by regulations for pressure vessels etc. but dimensioning may be flexible. API 521 allows engineer to specify the overpressor cases
Process Trips (Level, temperature and pressure)
All process equipment
Flammable
One of the major aids to avoilding major hazards accidents due to process disturbances. Note that these scenarios are generally not included in regulatory QRA, but are an essential part of a SIL review
Interlocks
All process equipment sequential operation such as start up. Batch production.
All hazardous materials, reactive materials
One of the major protection devices for batch processes, with direct impact on many scenario types
PSV's
All pressurised process equipment, boilers, hudraulics, pneumatics
© J.R.Taylor 2014
Applicability for Assets and Business Interruption
Hazard applicability
All hazardous materials, water in boilers
Prevents injury and fatality due to overpressure explosion
Practicality Assessment
8
Effectiveness
JI Calculation
API 14c level is usually required as a minimum. Extension to additional parametes, SIL 2 or 3 on the basis of SIL review. Calculate by LOPA based SIL review.
Cost calculation
Reference
Process Safety Engineering Handbook.
Process Safety Engineering Handbook. Risk analysis for machinery.
Comparative QRA with and without overpressure explosion
Process Safety Engineering Handbook.
QRAQ 24 Systematic ALARP Analysis S.No.
21
22
23
24
Applicability for Assets and Business Interruption
Risk Reduction Measures
Equipment Applicability
Burst Disk
Batch reactors, reciprocating compressors, heat exchangures with high pressure tubing, cryo tanks, pentane tanks
All hazardous materials
Prevents injury and fatality due to overpressure explosion
Prevents injury and fatality due to overpressure explosion
Generally not used on oil and gas systems because the disk remains open after relieving. Is used though on some heat exchangers because PSV's do not react fast enough for tube rupture cases
Thermal Relief Valves
piping subject to solar heating, heat traced piping, cryogenic piping.
All hazardous liquids (usually not relevant for gases or gas padded liquid).
Eliminates one cause of pipeline rupture, reduces risk probability slightly. This is not usually taken into account in QRA, because causal analysis is not usually made.
Eliminates one cause of pipeline rupture, reduces risk probability slightly. This is not usually taken into account in QRA, because causal analysis is not usually made.
Generally a requirement for vulnerable piping. May introduce new risks of vapour or gas release
Design for maximum pressure
Batch reactors, heat exchangers, continuous reactors, pump discharge piping
All hazardous materials
Eliminates one cause of pipeline rupture, reduces risk probability slightly. This is not usually taken into account in QRA, because causal analysis is not usually made.
Eliminates one cause of pipeline rupture, reduces risk probability slightly. This is not usually taken into account in QRA, because causal analysis is not usually made.
Is practical where accidental pressures are not too high.
Explosion panels
Buildings or vessels handling flammable dust, compressor crank cases.
Flammable dusts, lube oil mist
Eliminates a limited risk for reciprocating compressors and for dust handling plant or plant with a dust generation problem (sugar, flour, coal, peat)
Eliminates a major asset and BI risk for reciprocating compressors and for dust handling plant or plant with a dust generation problem (sugar, flour, coal, peat)
Generally practical but there must be a free area for blast relief fire jet.
© J.R.Taylor 2014
Hazard applicability
Applicability Human Risk
Practicality Assessment
9
Effectiveness
JI Calculation
Cost calculation
Reference
Process Safety Engineering Handbook.
Proper causal analysis based QRA
Process Safety Engineering Handbook.
Inherently safe, 100% effective where feasible
Proper causal analysis based QRA
Process Safety Engineering Handbook. DOD costing manual.
100% effective where feasible and provided they are dimensioned and installed correctly
QRA for runaway reaction Fr, of explosion * 5 * damage cost > cost of quench system
Usually completely effective, reliability high, see ref.
Fr, of explosion * damage cost * 5 > additional cost of quench system
Cost of reactor, possibly building and cost of quench vessel and piping.
Process Safety Engineering Handbook. DOD costing manual.
QRAQ 24 Systematic ALARP Analysis S.No.
25
Risk Reduction Measures
Quench Tanks
26
Quench Injection
27
Snuffing for activated charcoal absorbers with nitrogen
28
Snuffing for sulphur tanks and pits with steam
29
Temporary safe refuge (TSR)
Equipment Applicability
Hazard applicability
Applicability Human Risk
Applicability for Assets and Business Interruption
Practicality Assessment The speed rundown of reactants needs to be faster than the rate of temperature rise (determined from thermal rate rise experiments) The speed rundown of reactants needs to be faster than the rate of temperature rise (determined from thermal rate rise experiments)
Effectiveness
JI Calculation
The solution is fully effective provided that the run down is fast enough and the quench fluid can
QRA for runaway reaction Fr, of explosion * 5 * damage cost > cost of quench system
The solution is fully effective provided that the injection is fast enough and the quench fluid can
QRA for runaway reaction Fr, of explosion * 5 * damage cost > cost of injection system
Applicable to batch reactors with exothermic reactions
Applicable when the reactor overheats or temperature rise too fast
Applicable to batch reactors with exothermic reactions
Applicable when the reactor overheats or temperature rise too fast
Eliminates a risk of reactor explosion and resulting operator injury or fatality
Eliminates a risk of reactor explosion and resulting reactor and installation damage
Applicable when there is a possibility of autoignition in absorber
Eliminates a risk of fire and of possible duct explosion, which may cause injury or fatality
Eliminates a risk of fire and of possible duct explosion. Eliminates a risk of possible building explosion
Readily practical
100% effective if properly designed and there is sufficient nitrogen
Reduces the risk from sulphur fire and resulting sulphur dioxide release
Reduces the risk of damage to the tank or pit.
Readily practical.
Necessary for sulphur pits – frequency of fires is otherwise high
Reduces the human consequences of major hazards accidents.
No impact from TSR as such but good protection for controls if integrated with an instrument and electrical room (IER).
Readily practical. Complete TSR’s are available as commercial modules
Applicable for vent ducting with flammable VOC absorbers Always applicable for liquid sulphur tanks. Not needed for closed sulphur vessels. Applicable where there is a risk of flammable or toxic gas release
© J.R.Taylor 2014
Applicable for vapour cloud explosions, flammable and toxic gas releases
Eliminates a risk of reactor explosion and resulting operator injury or fatality
Eliminates a risk of reactor explosion and resulting reactor and installation damage
10
Cost calculation
Cost of reactor, possibly building and cost of quench vessel and piping.
Cost of reactor, possibly building and cost of quench vessel and piping.
Cost is minimal sensors, a few runs of tubing and connection to nitrogen supply
Reference
Process Safety Engineering Handbook. DOD costing manual.
Process Safety Engineering Handbook. DOD costing manual. Process Safety Engineering Handbook.
Process Safety Engineering Handbook.
QRA and ICAF calculation versus cost
Commercial module prices available
API 752 Safety Engineering Handbook
QRAQ 24 Systematic ALARP Analysis S.No.
30
31
32
33
34
Risk Reduction Measures
TSR and CR HVAC gas detection and ESD
Equipment Applicability
Eliminates flammable and toxic gas ingress
Hazard applicability
Applicability Human Risk
Applicability for Assets and Business Interruption
Applicable for VCE, and toxic gas
Reduces the number of people at risk from VCE etc, and toxic risk a) because operators can spend standby time in the shelter (permanent safe refuge) and b) provide a safe location for emergency muster
No impact for asset or BI risk from TSR, but good protection of local control if I&E rooms are in the TSR. Prevents damage to control ssystem
TSR Blast Valves
Fitted to TSR if there is an explosion risk
Applicable for VCE
Vent Purging
High velocity air supply or CO2 or nitrogen injection
Applicable to chemical process venting where vapour is flammable
Ducting Fire Shutters
Shutters close rapidly on fire detection in ducts
Applicable for vent ducts with flammable vapour
Vent Ducting blast panels
Explosion rupture discs at intervals to limit pressure rise
© J.R.Taylor 2014
Applicable for vent ducts with flammable vapour
May save lives if explosion indoors is possible, but usually minimal effect
Little impact on human safety
May save lives if explosion indoors is possible, but usually minimal effect
Practicality Assessment
Always practical
Effectiveness
JI Calculation
Cost calculation
Reference
Fully effective except for very highly toxic gases such as MIC
Justification not really needed if TSR and bunkerised control rooms are implemented
About $4000 for dual flammable and dual toxic gas detectors, $500 for HVAC circuit breakers and $800 for good HVAC duct valve
API 752 and Process Safety Engineering Handbook
About $2000 per duct depending on size
API 752 and Process Safety Engineering Handbook
Cost of blanket gas per kg * 5*vapour generation rate (kg/yr)
Process Safety Engineering Handbook
About $1500 per shutter depending on duct size, but many may be needed depending on duct length. See ref. for spacing
Process Safety Engineering Handbook
About $1000 per shutter depending on duct size, but many may be needed depending on duct length. See ref. for spacing
Justification not really needed if TSR and bunkerised control rooms are implemented for explosion risk Fr. of explosion * damage + Fr. of fire * damage > gas supply cost py.
Always practical
Highly effective if dimensioned correctly. Need to have a very rapid response in some cases
Very effective in preventing explosion and resulting damage and fire spread in ducts
Can be difficult to obtain adequate blanket gas supply at some locations
Highly effective if dimensioned correctly
Very effective in preventing fire spread and run up to explosion in ducts
Spacing of shutters for effective suppression can be difficult
Require explosion detectors and very rapid actuation
( Fr. of explosion * damage) * amortisation factor > shutter cost.
Very effective in preventing explosion and resulting damage and fire spread in ducts
In some cases the appropriate panel size is larger than the duct. In these cases a weak section of duct can be installed
Requires panels speed at less than the explosion pressure run up distance
( Fr. of explosion * damage) * amortisation factor > shutter cost.
11
Process Safety Engineering Handbook
QRAQ 24 Systematic ALARP Analysis S.No.
Risk Reduction Measures
Equipment Applicability
Hazard applicability
Applicability Human Risk
Applicability for Assets and Business Interruption
Practicality Assessment
Effectiveness
JI Calculation
Cost calculation
Reference
Effective if the wall is strong and high enough, and buildings and protected tanks can tolerate the behind wall blast. Effective also in stopping projectiles
Fr. of design basis explosions * damage cost* amortisation factor > cost of wall
Wall should be 20% wider and higher than the protected item. Wall cost including reinforcement and labour $100 per cubic m.
Process Safety Engineering Handbook
Wall cost including reinforcement and labour $100 per cubic m. Indoor wall 50% more than non protective wall
Process Safety Engineering Handbook
outdoor in a safe location
35
36
37
38
Blast Wall
Fire Wall
Protection of critical installations e,g, CR or toxic fluid tanks
Protection of critical installations e,g, CR or tanks Separation of units to prevent fire propagation
Protection berm
Protection of critical installations e,g, CR or tanks Separation of units to prevent fire propagation
Fixed Fire Water Monitors
Protection of installations by cooling (with water) and by liquid fire suppression
© J.R.Taylor 2014
VCR, BLEVE or reactor explosion
Pressurised flammable fluids
Effective in limiting human consequences
Can have relevance for persons in otherwise CR and OR close to fire sources e.g. in jet fire or flash fire range. Useful also for
Pressurised flammable fluids
Can have relevance for persons in otherwise CR and OR close to fire sources e.g. in jet fire or flash fire range. Useful also for
Flammable liquids and gases
Little impact on human risk for humans except for firemen. Can have relevance for human if used to create a water curtain for toxic gas e.g, ammonia or HF,
Effective in limiting asset damage and BI consequences
Effective in limiting asset damage and BI consequences
Evaluate the pressure and impulse for typical large explosions vs. needed wall thickness and behind wall pressure
Generally applicable. Fire walls require fire doors and fireproof penetration seals
Effective for design basis fires for 30, 60 or 120 minutes depending on spec.
Fr. fire * Pr. Escalation * cost of escalation damage * amortisation factor > cost of wall
Effective in limiting asset damage and BI consequences
Generally practical. Needs frequent inspection to ensure that fire doors are kept closed, or use automatic door closers.
Completely effective for preventing liquid spread and heat radiation protection.
Fr. fire * Pr. Escalation * cost of escalation damage * amortisation factor > berm land valuation
Effective in limiting asset damage and BI consequences
Generally applicable provided that activation can be rapid.
Effective in cooling and suppression provided that they are adequately dimensioned
Fr. of impinging fire * Pr. Escalation * cost of escalation damage *
12
Indoor $15 to $30 pr m2 plus installation Mineral wool $25 per m2 plus $50 for cladding installed Limited cost for berm if excavated soil can be used. Largest part of the cost is the land use. Needed height calculated from heat radiation mapping
Process Safety Engineering Handbook
Process Safety Engineering Handbook
QRAQ 24 Systematic ALARP Analysis S.No.
Risk Reduction Measures
Equipment Applicability
Hazard applicability
(with foam)
39
40
Pre-aimed remotely activated monitors
Oscillating Monitors
Protection of vessels and tanks against escalation due to flame impingement and heat radiation
Protection of Tanks against escalation due to flame impingement
© J.R.Taylor 2014
Applicability Human Risk
Applicability for Assets and Business Interruption
Practicality Assessment
Effectiveness
Great care is needed when applying water curtains to prevent the water causing more evaporation of liquefied gases e.g. cryogenic ammonia, LPG or LNG
Flammable liquids and gases Jet fires Pool fires
Flammable liquids and cryogenic gases Pool fires
Limited affect – self evacuation is faster than deployment. Can protect CRs
JI Calculation
Cost calculation
Reference
amortisation factor > Fire system cost.
Effective in limiting asset damage and BI consequences
Practical
Limited affect – self evacuation is faster than deployment. Can protect CRs Effective in limiting asset damage and BI consequences
Practical
13
Generally applicable and more effective than manually aimed monitors due to faster activation. . Effective in cooling and suppression provided that they are adequately dimensioned
Effective against radiation and to some extent against flame impingement. Care needed to ensure reliability
Generally there is no doubt that a system will be installed, the only question is its design basis and capacity, where risk optimisation is possible Fr. of impinging fire * Pr. Escalation * cost of escalation damage * amortisation factor > Fire system cost.
Fr. of impinging fire * Pr. Escalation * cost of escalation damage * amortisation factor > Fire system cost.
Process Safety Engineering Handbook
Process Safety Engineering Handbook
QRAQ 24 Systematic ALARP Analysis S.No.
41
42
43
44
Risk Reduction Measures
Equipment Applicability
Remotely aimed monitors
Protection of vessels and tanks against escalation due to flame impingement and heat radiation
Deluge
Protection of vessels and tanks by cooling against escalation due to flame impingement and heat radiation
Hazard applicability
Flammable liquids and gases Jet fires Pool fires
Applicability Human Risk
Limited affect – self evacuation is faster than deployment. Can protect CRs Little impact on human risk for humans except for firemen. Can be used as a water curtain as described above
Applicability for Assets and Business Interruption
Effective in limiting asset damage and BI consequences
Flammable liquids and gases Jet fires Pool fires
Limited affect – self evacuation is faster than deployment. Can protect CRs Little impact on human risk for humans except for firemen.
Foam deluge
Protection of vessels and tanks by cooling against escalation due to flame impingement and heat radiation
Flammable liquids and gases Jet fires Pool fires
Limited affect – self evacuation is faster than deployment. Can protect CRs Little impact on human risk for humans except for firemen.
Effective in limiting asset damage and BI consequences
Foam pourers
Floating roof tank fires, esp rim seal fires.
Crude oil and refined products
Virtually no effect on human risk except indirectly by reducing the probability of boilover
Effective in limiting asset damage and BI consequences
© J.R.Taylor 2014
Effective in limiting asset damage and BI consequences
Practicality Assessment
Practical
Practical
Effectiveness
Generally applicable and more effective than manually aimed monitors due to ability to activate and aim when heat radiation field is intense. . Effective in cooling and suppression provided that they are adequately dimensioned and maintained
Not fully effective against jet fires but do delay escalation
Practical
Very effective but requires care in refreshing foam solution. Dry types have a slow activation time, prefilled types are fast.
Practical
Effective against rim fires. Ineffective against full surface fires in large tanks
14
JI Calculation
Fr. of impinging fire * Pr. Escalation * cost of escalation damage * amortisation factor > Fire system cost.
Fr. of impinging fire * Pr. Escalation * cost of escalation damage * amortisation factor > Fire system cost.
Cost calculation
Reference Process Safety Engineering Handbook
Process Safety Engineering Handbook
Process Safety Engineering Handbook
Process Safety Engineering Handbook
QRAQ 24 Systematic ALARP Analysis Applicability for Assets and Business Interruption
S.No.
Risk Reduction Measures
Equipment Applicability
46
Water curtains for heat radiation
All process equipment and process plant buildings
47
Water curtains for gas diversion
Specific hazards such as HF, flammable vapour dispersing towards fired heaters etc.
Flammable and some toxic gas releases
Effective against flammable and toxic gas ingress to an area
Effective against heat radiation and flammable gas ingress to an area
Requires very fast activation of large quantities of water
48
Water curtains for gas absorption
Specific hazards such as HF, ammonia
HF, ammonia
Effective against heat radiation and flammable and toxic gas ingress to an area
Effective against toxic gas ingress to an area
Requires very fast activation of large quantities of water
49
Water spray for explosion suppression
Hazard applicability
Pool fires Jet fires
Applicability Human Risk
Effective against heat radiation if activated rapidly
Effective for heat radiation from pool and jet fires
Practicality Assessment Requires large quantities of water, needs careful drainage design
Effectiveness
Effective
Difficult design
Difficult design
Still experimental
50
Explosion suppression
Injection of flame supressing vapour inside vessels and dry powder pneumatic transfer pipes
51
Clean gas, Energen or CO2 fire suppression
Switch rooms control rooms Server rooms
51
In cabinet smoke detection ASD
Switch cabinets Cable terminal cabinets Server cabinets
© J.R.Taylor 2014
Flammable gas and vapour
Effective in preventing confined explosion consequences
Electrical fires
Little impact on human risk, can increase human risk
Electrical fires
Little impact on human risk, can increase human risk
Effective in preventing confined explosion consequences
Effective in preventing electrical fires
Effective in preventing electrical fires
Practical
Practical
Practical
15
JI Calculation
Cost calculation
Reference Process Safety Engineering Handbook Process Safety Engineering Handbook
Process Safety Engineering Handbook Process Safety Engineering Handbook Process Safety Engineering Handbook
Process Safety Engineering Handbook Process Safety Engineering Handbook
QRAQ 24 Systematic ALARP Analysis S.No.
52
53
Risk Reduction Measures
Manual firefighting
Area Classification
54
Tank blanketing
55
Sub-surface foam injection
56
57
58
Emergency Scrubber
Passive fire protection
Fire proofing
Equipment Applicability
Alll
Areas with flammable gas and liquids, flammable dust Fixed roof tanks with volatile flammables. Slop tanks Degassing tanks
Hazard applicability
Liquid fire suppression Equipment cooling
Flammable gas and liquids, flammable dust
Flammable vapour
Applicability Human Risk
Little impact on initial human risk, self evacuation is more effective. Rescue is important
Reduces likelihood of ignition
Protects against tank explosion
Applicability for Assets and Business Interruption
Effective if correctly dimensioned and response is fast enough
Effective
Effective
Practicality Assessment
Effectiveness
JI Calculation
Cost calculation
Reference Process Safety Engineering Handbook
Practical
Effectiveness varies. There will always be fire sizes which cannot be handled. Needs a fairly complex effectiveness calculation
Practical
Effectiveness varies. Needs a calculation of ignition probabilities see QRAQ vol 7
Process Safety Engineering Handbook QRAQ vol 7
Effective if designed correctly
Process Safety Engineering Handbook
Practical
Process Safety Engineering Handbook Toxic gas vents and leak containment enclosures
Vessels, piping
Steel structures
© J.R.Taylor 2014
Toxic gas
Flammable gas or liquid
Flammable gas or liquid
Effective if properly dimensioned
Protects against FITE and BLEVE
Protects against structural collapse
Process Safety Engineering Handbook
Practical
Effective
Effective
Practical
Practical
16
Depends on type and fire type and duration
Process Safety Engineering Handbook Process Safety Engineering Handbook
QRAQ 24 Systematic ALARP Analysis S.No.
59
60
Risk Reduction Measures
Flame shielding
Blast Resilience
62
Human occupancy separation
63
Limited human occupancy
65
Flares
Hazard applicability
Applicability Human Risk
Flares
Reduces heat radiation intensity at work areas at the flare site
Applicability for Assets and Business Interruption
Practicality Assessment
Effectiveness
Self evacuation
Rescue
JI Calculation
Cost calculation
Reference Process Safety Engineering Handbook Process Safety Engineering Handbook
Blast proofing
61
64
Equipment Applicability
Process Safety Engineering Handbook Control room, workshop, offices and operator room locations
Process area
All
All
© J.R.Taylor 2014
All
All
All
All
Effective up to scenario sizes at the design basis
Effectiveness determined by detailed QRA
Zero manning design for operations phase
Requires extensive design consideration, expensive
Possible
Effectiveness determined by detailed QRA including evacuation
Possible
Effectiveness determined by detailed QRA including evacuation
17
QRA Pro Handbook
QRA Pro Handbook
Risk analysis for Process Plant pipelines and Transport Risk analysis for Process Plant pipelines and Transport
QRAQ 24 Systematic ALARP Analysis S.No.
Risk Reduction Measures
66
Temporary gas refuge
67
Blast and fire proof operator rooms
68
69
70
Equipment Applicability
Hazard applicability
Applicability Human Risk
Applicability for Assets and Business Interruption
Practicality Assessment
Effectiveness
Cost calculation
Reference Process Safety Engineering Handbook Process Safety Engineering Handbook Process Safety Engineering Handbook
Personal gas alarm
Escape mask
JI Calculation
Process equipment with toxic gas
Practical
About 95% for positive pressure types
Process Safety Engineering Handbook Process Safety Engineering Handbook
Low ignition probability
71
Bunds
Storage areas
Prevention of liquid spread
72
Impoundment basins
Storage areas
Prevention of gas dispersion
73
Hazardous fluid collecting basins
Storage areas for LPG, LNG
© J.R.Taylor 2014
Pool fire
Effective, but limited applicability
Process Safety Engineering Handbook
Effective
Requires CFD calculations
Limits potential heat radiation area
Limits potential heat radiation area
Practical if there is space
18
Process Safety Engineering Handbook Process Safety Engineering Handbook
QRAQ 24 Systematic ALARP Analysis
© J.R.Taylor 2014
19