46 0 70KB
PMP® / CAPM® Formulas Cheat Sheet Earned Value Management BAC
EV AC SV CV SPI SPIC
No Formula. No Formula. It is sometimes expressed as a %age of BAC. No Formula. It is sometimes shown as a %age of BAC or PV. No Formula. SV = EV – PV CV = EV – AC SPI = EV / PV SPIC =∑EV / ∑PV
CPI CPIC Budget % Spent
CPI = EV / AC CPIC = ∑EV / ∑AC Σ 100
PV
Project % Complete
ETC
EAC VAC TCPI
Σ 100 ETC = (BAC – EV) / CPI ETC = (BAC – EV) ETC = (BAC – EV) / CPIp EAC = AC + ETC EAC = AC + (BAC – EV) EAC = AC + (BAC – EV) / CPI EAC = BAC / CPI EAC = AC + [(BAC – EV) / (CPI * SPI)] VAC = BAC – EAC TCPI = (BAC – EV) / (BAC – AC) TCPI = (BAC – EV) / (EAC – AC)
Estimation Earned Schedule Management SVT
ES - AT
SPIT
ES / AT
E = (O + P + M) / 3
Network Diagram TF = LS – ES Total Float TF = LF – EF Free Float FF = ESSuccessor – ESPresent – DurPresent
Project Selection Methods PV / DCF NPV ROI BCR CBR IRR PP Opp Cost
PV = FV / (1 + r)n PV = FV * DF NPV = ∑PV ROI = Return / Investment BCR = Benefits / Costs CBR = Costs / Benefits Formula not needed. Higher is better. No formula. Lesser the better. No formula.
Triangular − + − −
= √ Dist. 18 PERT E = (O + P + 4*M) / 6 σ = (P – O) / 6 Range Est. R = E ± (n * σ) Var. Var = σ2 Path Var. VarPath = ∑(Var) Path St.
= √ Deviation
Sigma Values
1σ = 68.27% 2σ = 95.45% 3σ = 99.73% 4σ - 99.994% 5σ = 99.99994% 6σ = 99.999999%
Communication Channels C = n*(n – 1) / 2
Expected Monetary Value
Procurement
EMVR EMVR = P * I EMVP EMVP = ∑EMVR Net Benefit Net Benefit = EMVP – Cost
− Pt. of Total = + Assumption !ℎ #$%&
About PMP® Formulas Pocket Guide
4 Ways to Use this Guide
This guide is based on PMBOK® Guide 6th Edition. It can Pg. 1 - PMP Formulas be used for CAPM® PMP® exam preparation. The guide Pg. 2 - Abbreviations & brief explanations. has been compiled with great care but it has not been Print just Pg.1 or both as a back-to-back sheet. independently verified. You can use it for reference but - Fold & carry it in your pocket to memorize it should not replace your primary study material. The formulas usage of this guide does not guarantee success in the - Pin it beside study table for quick reference certification exams. - Save it as an image on your PC Desktop - Save it on your mobile for any time viewing
Copyright 2016-18 https://www.pmbypm.com
Version: 2.1 Release Date: November 22, 2018
1
PMP® / CAPM® Formulas Cheat Sheet Earned Value Management BAC PV
Budget At Completion Planned Value
CPI CPIC
Cost Performance Index Cumulative Cost Performance Index
EV AC SV CV SPI SPIC
Earned Value
CPIP
Projected Future CPI
Actual Cost Schedule Variance Cost Variance Schedule Performance Index Cumulative Schedule Performance Index
ETC EAC VAC TCPI
Estimate To Complete Estimate At Completion Variance At Completion To Complete Performance Index
Earned Schedule Management
Network Diagram
SVT
Schedule Variance (Time)
TF
Total Float
SPIT
Schedule Performance Index (Time) Earned Schedule Actual Time
FF ES LS EF LF Dur
Free Float Early Start Late Start Early Finish Late Finish Duration
ES AT
Estimation E O P M SD or σ Var VarPath n
Expected Value Optimistic Value Pessimistic Value Most Likely Value Standard Deviation or Sigma Variance of an Activity Variance of a Network Path Sigma multiplication Factor
Project Selection Methods
Procurement
PV DCF FV r n DF NPV ROI BCR CBR IRR PP Opp. Cost
PTA CP TP TC
C n
Expected Monetary Value EMVR P I EMVP
Expected Monetary Value for Risk Probability Impact (Monetary Value) Expected Monetary Value for Project
Point of Total Assumption Ceiling Price Target Price Target Cost
Present Value Discounted Cash Flow Future Value Discount Rate Number of years Discount Factor Net Present Value Return on Investment Benefit Cost Ratio Cost Benefit Ratio Internal Rate of Return Payback Period Opportunity Cost
Communication Channels Number of Communication Channels Number of Stakeholders
Follow Us On Social Media for Exam Tips, Updates, Articles, & latest Discounts/Offers Linkedin http://linkedin.com/groups/4456858/ Facebook http://www.facebook.com/pmbypm Quora http://quora.com/profile/Praveen-Malik-16 Pinterest http://in.pinterest.com/pmbypm/ Slideshare http://www.slideshare.net/pmalik2/ Twitter http://twitter.com/pmbypm Free PMP Exam Prep Guide https://www.pmbypm.com/how-to-get-pmp-certification/
Copyright This sheet is compiled by Praveen Malik & is available at no cost to PMP aspirants. It can freely downloaded by joining our FB group (https://www.facebook.com/groups/pmi.exam.prep). You can only use it for your own exam prep & not for any other purpose. Unauthorized copying, modification, or distribution is strictly prohibited.
Copyright 2016-18 https://www.pmbypm.com
Version: 2.1 Release Date: November 22, 2018
2